GeorgiaGeorgia General Assembly2025-2026Bill
SB 476: Ends new data center sales tax exemption certificates statewide
Official title: Income Tax Reduction Act of 2026
Draft research, not yet verified: traced to the official record by an AI research agent; an editor has not checked it yet.
Where it stands
Died or failed as of Feb 12, 2026. The official record says: Senate Passed/Adopted.
- Filed (done)
- In committee (done)
- Passed one chamber (done)
- Passed both chambers (not reached)
- Signed into law (not reached)
- In effect (not reached)
- Died or failed (current stage)
What it does
Incentive restriction
Applies to: high-technology companies claiming the O.C.G.A. 48-8-3(68) exemption (Georgia)
“After the effective date of this Act, no new certificates of exemption from sales and use tax to a high-technology company shall be issued pursuant to the former provisions of this paragraph as they existed prior to the effective date of this Act; provided, however, that any certificate of exemption issued prior to the effective date of this Act shall continue to be governed by the provisions of this paragraph as it existed immediately prior to the effective date of this Act;”
Section 5-22, reenacted paragraph (68) of Code Section 48-8-3
Incentive restriction
Applies to: high-technology data centers and their customers (Georgia)
“After the effective date of this Act, no new certificates of exemption from sales and use tax to a high-technology data center or a high-technology data center customer shall be issued pursuant to the former provisions of this paragraph as they existed prior to the effective date of this Act; provided, however, that any certificate of exemption issued prior to the effective date of this Act shall continue to be governed by the provisions of this paragraph as it existed immediately prior to the effective date of this Act;”
Section 5-22, reenacted paragraph (68.1) of Code Section 48-8-3
Effective date
Applies to: the whole act, except Part II as provided in subsection (b) (Georgia)
Starts: 2027-01-01.
“Except as otherwise provided in subsection (b) of this section, this Act shall become effective on January 1, 2027, and shall be applicable to taxable years beginning on or after January 1, 2027.”
Part VI, Section 6-1(a)
Who it touches
No project we track is matched to this bill or order: its rules do not reach them, or a check found it does not apply.
Other projects we track in Georgia (82), not affected
- 75 South Data Center CampusProposed
- Aligned ATL-01Operating
- Aligned Data Centers ATL-01 (Lithia Springs)Operating
- ATL03 (Red Oak Road)Proposed
- ATL11 (Stonewall Tell Road)Proposed
- Bridgeport (Revised) Technological FacilityProposed
- CoreSite AT1 AtlantaOperating
- DataBank ATL1 Midtown AtlantaOperating
- DataBank ATL4 South FultonOperating
- DataBank ATL5 (Atlanta)Operating
- DataBank ATL6 (Atlanta)Operating
- DataBank Atlanta West End Campus (ATL2 and ATL3)Operating
- DataBank Lithia Springs Campus (ATL5 and ATL6)Under construction
- DataBank Project IndoIn permitting
- Data Center at 0 Social Circle ParkwayProposed
- DC BLOX Atlanta East (Conyers)Under construction
- DC BLOX Atlanta West (Douglasville)Under construction
- Digital Realty ATL15 and ATL16 (Fort Gillem)Proposed
- Digital Realty Atlanta Connected Campus (ATL13 and ATL14)Operating
- EdgeConneX Atlanta Campus (ATL01 and ATL02)Operating
- Edged Atlanta Campus (Tilford Yard)Expanding
- Equinix AT1 AtlantaOperating
- Equinix AT4 AtlantaOperating
- Fairburn Technology CenterProposed
- Flexential Atlanta - AlpharettaOperating
- Flexential Atlanta-Douglasville CampusOperating
- Flexential Atlanta - NorcrossOperating
- Google Columbia County Data Center (White Oak Technology Park)Approved
- Google Douglas County data centerOperating
- Google LaGrange Data CenterUnder construction
- Gregory Road Data CenterProposed
- H5 Data Centers AtlantaOperating
- Hampton Technology ParkProposed
- Highway 16 Interstate Health DevelopmentProposed
- Kingston Technology HubProposed
- Meta Newton Data Center (Stanton Springs)Operating
- Microsoft ATL06 (East Point)Under construction
- Microsoft ATL50Proposed
- Microsoft ATL80Proposed
- Microsoft CCO06 (Palmetto)Under construction
- Microsoft FTY01 (Douglasville)Under construction
- Nixon Technology CenterProposed
- OpenAI Project CamelliaIn permitting
- Project ArrowheadProposed
- Project AvemoreProposed
- Project AzeleaProposed
- Project Bunkhouse (Digital Realty Stilesboro Campus)Under construction
- Project BusCancelled
- Project GracieIn permitting
- Project RubyProposed
- Project SailProposed
- Project Squash (Pumpkin Center)Under construction
- QTS ATL2 EastProposed
- QTS Atlanta 1Operating
- QTS Atlanta 1 (Atlanta)Operating
- QTS Augusta (Augusta; listed as in development)Proposed
- QTS Augusta CampusProposed
- QTS Blakely (Blakely; listed as in development)Proposed
- QTS Blakely CampusIn permitting
- QTS Fayetteville CampusUnder construction
- QTS Fayetteville (Fayetteville; listed as in development)Proposed
- QTS Suwanee 1Operating
- QTS Suwanee 1 (Suwanee)Operating
- Rock House Road Data Center SiteProposed
- Southeast Data Center Campus (Fayetteville)Proposed
- STACK ATL02 Lithia SpringsUnder construction
- Stillwater Technology ParkCancelled
- Stonewall Tell Data CenterProposed
- Stream Data Center (Douglas County)Proposed
- Stream Data Centers AtlantaProposed
- Strickland Tract Data CenterProposed
- Switch KEEP 2.0 Atlanta NorthUnder construction
- Switch Switch ATLANTA (Atlanta)Operating
- Switch The KeepOperating
- T5@Atlanta IIIUnder construction
- T5 ATL IV (Coweta County)Proposed
- T5 ATL IV (Fairburn)Proposed
- The Crossings (Union City)Proposed
- Vantage Data Center DouglasvilleUnder construction
- Vantage Data Center Stacks RoadProposed
- Vantage Data Center WestlakeProposed
- Wallace Jackson Data Center CampusProposed
Who acted
- CosponsorAnavitarteSenate, district 31st
- CosponsorHufstetlerSenate, district 52nd
- CosponsorRobertsonSenate, district 29th
- CosponsorWalker IIISenate, district 20th
- Primary sponsorTillerySenate, district 19th
Timeline
Every official action on record, oldest first. An action that moved the bill to a new stage names that stage.
- · SenateSenate Passed/AdoptedStage: Passed one chamber
- · HouseReferred to the House Ways and Means Committee
More from Georgia
- SB 530 · Died or failedDeposits data center tax collections into a property tax relief fund
- HB 1323 · Died or failedRequires new data centers to operate as hybrid power facilities
- HB 1063 · Passed one chamberRequires utility contracts shielding other customers from data center costs
- HB 1059 · Died or failedBans new data center permits through 2028, creates impact commission
- SB 436 · Died or failedBans usage nondisclosure deals, pauses new data center tax certificates
- HB 1012 · Died or failedBans new data center construction permits until March 2027
Sources
- 1
- 2
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "SB 476: Ends new data center sales tax exemption certificates statewide." Bill Watch. Updated 2026-11-13. Accessed 2026-11-29. https://datacenterfactcheck.org/policy/bills/ga-2025-26-sb-476
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page