Project File
Project Ruby
Columbus,Muscogee County,GeorgiaProposedFirst public 2026Filing entity: Muscogee Property 1 LLCLast checked Nov 8, 2026
Habitat Real Estate PartnersDeveloperChoose ColumbusPublic partner
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Capacity
- Confirmed: First public date
- Still to confirm: Electric utility
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Project Ruby is a proposed data center project in Columbus, Muscogee County, Georgia. Habitat Real Estate Partners is named as developer. It was first public in 2026. It was announced at 600 MW.
Project Ruby is a proposed data center project in Columbus, Muscogee County, Georgia. Habitat Real Estate Partners is named as developer. It was announced at 600 MW. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Columbus, Muscogee County, Georgia. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Timeline
- · New projectFirst public record of Project RubyProposed
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Georgia HB 1063: Requires utility contracts shielding other customers from data center costs
The act covers data centers with a peak annual electricity demand of 100 megawatts or greater, under agreements with an electric utility entered into on or after the effective date of the act; this project has no capacity figure on record, but the project's peak annual electricity demand and the date of its electric service agreement is not on record.
“As used in this part, the term 'data center' means a facility, campus of facilities, or array of interconnected facilities used by an entity or other business enterprise to operate, manage, or maintain a computer, group of computers, or other organized assembly of hardware and software for the primary purpose of processing, storing, retrieving, or transmitting data and that have a peak annual electricity demand of 100 megawatts or greater.” (Section 1, new Code Section 46-3-80)
Rule checks: Project is in Georgia; 600 MW on record (not stated), threshold 100 MW (Section 1, new Code Section 46-3-80). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Georgia SB 410: Ends new data center tax breaks, sets large load contract terms
The act covers large load customers with an expected total peak demand of 100 megawatts or greater at premises on one tract or contiguous tracts of land, under contracts entered into on or after the effective date of the act; this project has no capacity figure on record, but the project's expected total peak demand and the date of its electric service contract is not on record.
“As used in this Code section, the term 'large load customer' means customers with an expected total peak demand of 100 megawatts or greater at one or more premises located on one tract or contiguous tracts of land.” (Part I, Section 1-2, new Code Section 46-2-25.4(a))
Rule checks: Project is in Georgia; 600 MW on record (not stated), threshold 100 MW (Part I, Section 1-2, new Code Section 46-2-25.4(a)). Still to check: who it covers: not checked
Bills and laws in Georgia
- SB 410 · Passed one chamber · Mar 6, 2026Ends new data center tax breaks, sets large load contract terms
- SB 34 · Died or failed · Feb 26, 2026Bars shifting data center power costs onto other utility customers
- HB 1387 · Died or failed · Feb 20, 2026Funds homestead exemption from property taxes collected on data centers
- SB 530 · Died or failed · Feb 19, 2026Deposits data center tax collections into a property tax relief fund
- HB 1323 · Died or failed · Feb 18, 2026Requires new data centers to operate as hybrid power facilities
- HB 1063 · Passed one chamber · Feb 17, 2026Requires utility contracts shielding other customers from data center costs
Who's involved
- DeveloperHabitat Real Estate Partners
- Public partnerChoose Columbus
Power
Capacity, as announced or filed
- 432 MW · Campus critical load (four buildings, as shown on the authority site map)Dec 2025 · it_load
- 600 MW · Campus total (four buildings, as shown on the authority site map)Dec 2025 · what the figure measures is not stated
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is Project Ruby?
- Project Ruby is a data center project in Columbus, Muscogee County, Georgia.
- Who is developing Project Ruby?
- Habitat Real Estate Partners is named as the developer of Project Ruby.
- How big is Project Ruby?
- Project Ruby was announced at 600 MW of capacity.
- What stage is Project Ruby?
- Project Ruby is proposed. It was first public in 2026.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Project Ruby Updates (FAQ)
Development Authority of Columbus (Choose Columbus)Tier 1 · Captured 2026-11-08 · Open the source - 2Project Ruby Data Center Site, Muscogee County, Georgia (site map)
Choose Columbus / Development Authority of ColumbusTier 2 · Captured 2026-11-14 · Open the source - 3Columbus, Georgia Set to Benefit from Major New Technology Center Campus (press release)
Choose Columbus / Development Authority of ColumbusTier 2 · Captured 2026-11-14 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page