Project File

Microsoft FTY01 (Douglasville)

Douglasville,Douglas County,GeorgiaUnder constructionFirst public 2021Filing entity: Microsoft CorporationLast checked Nov 9, 2026

MicrosoftDeveloper and operator

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

5 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: First public date
  • Still to confirm: Electric utility
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Microsoft FTY01 (Douglasville) is a under-construction data center project in Douglasville, Douglas County, Georgia. Microsoft is named as operator. It was first public in 2021. No site capacity figure is published for this project.

Microsoft FTY01 (Douglasville) is an under-construction data center project in Douglasville, Douglas County, Georgia. Microsoft is named as operator. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Douglasville, Douglas County, Georgia. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

9Public records we have found
1Tax agreement on record
1,050,000Water flow, gallons per day (estimated water supply demand, 1.05 MGD)

For homeowners

What this project means if you live nearby

Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work

  1. Property tax

    The campus's actual property tax bill is unpublished; for five years its deal substituted fixed payments for normal taxation.

    Not known yet
  2. Tax breaks

    From 2020 to 2026 the campus paid fixed payments in lieu of taxes under a city bond deal, below normal property tax.

    Comes to the community
  3. Money for schools and services

    No community payment by Microsoft for this campus is in the records read; its incentive deal required investment, jobs, and wages.

    Not known yet
  4. Electricity bill

    No record read in this pass names the electric utility serving this campus, so no local rate history can be shown yet.

    Not known yet
  5. Water

    The county water and sewer authority supplies this campus; its 2021 filing estimated demand at 1.05 million gallons a day.

    Comes to the community
  6. Jobs

    The campus's incentive deal promised twenty net new full-time jobs at a $33.65 average hourly wage by the end of 2025.

    Comes from the community
  7. Next door: height, setbacks, noise

    The site plan keeps 56 of about 160 acres open, behind city stream buffers of 50 feet plus a 25-foot setback.

    Not known yet
  8. Your say

    The one member-level vote on record, in September 2026, ended the campus's tax deal; the 2020 approval tallies were not printed in records read.

    Not known yet

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Douglas County, Georgia.See every project on the map

The land, to scale

One football field
160 acres, about 121 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · DecisionCity of Douglasville: Adopted as part of the consent agenda: AYES Caldwell, Davis, Hudson, Mayor Pro Tem T. Miller, and Watts; ABSENT Estes and N. Miller for Microsoft FTY01 (Douglasville)RES-2026-37 (Item 26-301), consent agenda item 7.A
  2. · FilingFiled with City of Douglasville for Microsoft FTY01 (Douglasville)RES-2026-37 (Item 26-301), consent agenda item 7.A
  3. · DecisionGeorgia Environmental Protection Division, Air Protection Branch: Narrative (May 21, 2024) recommends issuing Permit No. 7376-097-0097-S-01-1 for 21 additional emergency generators at Building 2 (GN22-GN42); the 30-day public review ended June 21, 2024 with no comments. Issuance of the -01-1 perm...Application No. 29231
  4. · FilingFiled with Georgia Environmental Protection Division, Air Protection Branch for Microsoft FTY01 (Douglasville)Application No. 29231
  5. · DecisionGeorgia Environmental Protection Division, Air Protection Branch: Issued October 13, 2022 (issuance date per the EPD narrative for Application No. 29231; the posted permit copy leaves its issuance-date field blank) (air permit) for Microsoft FTY01 (Douglasville)Permit No. 7376-097-0097-S-01-0 (Application No. 28295; AIRS No. 04-13-097-00097)
  6. · FilingFiled with Georgia Environmental Protection Division, Air Protection Branch: air permit for Microsoft FTY01 (Douglasville)Permit No. 7376-097-0097-S-01-0 (Application No. 28295; AIRS No. 04-13-097-00097)
  7. · DecisionAtlanta Regional Commission (review); Georgia Department of Community Affairs (DRI program): Preliminary regional review completed; submitting local government is the City of Douglasville; DRI trigger is a land disturbance permit for Microsoft FTY01 (Douglasville)DRI #3426; ARC review code R2110181
  8. · FilingFiled with Atlanta Regional Commission (review); Georgia Department of Community Affairs (DRI program) for Microsoft FTY01 (Douglasville)DRI #3426; ARC review code R2110181
All 12 events for this project

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Georgia HB 1063: Requires utility contracts shielding other customers from data center costs

    The act covers data centers with a peak annual electricity demand of 100 megawatts or greater, under agreements with an electric utility entered into on or after the effective date of the act; this project has 60.5 MW on record (generator capacity), but the project's peak annual electricity demand and the date of its electric service agreement is not on record.

    “As used in this part, the term 'data center' means a facility, campus of facilities, or array of interconnected facilities used by an entity or other business enterprise to operate, manage, or maintain a computer, group of computers, or other organized assembly of hardware and software for the primary purpose of processing, storing, retrieving, or transmitting data and that have a peak annual electricity demand of 100 megawatts or greater.” (Section 1, new Code Section 46-3-80)

    Rule checks: Project is in Georgia. Still to check: size: unknown, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Georgia SB 410: Ends new data center tax breaks, sets large load contract terms

    The act covers large load customers with an expected total peak demand of 100 megawatts or greater at premises on one tract or contiguous tracts of land, under contracts entered into on or after the effective date of the act; this project has 60.5 MW on record (generator capacity), but the project's expected total peak demand and the date of its electric service contract is not on record.

    “As used in this Code section, the term 'large load customer' means customers with an expected total peak demand of 100 megawatts or greater at one or more premises located on one tract or contiguous tracts of land.” (Part I, Section 1-2, new Code Section 46-2-25.4(a))

    Rule checks: Project is in Georgia. Still to check: size: unknown, who it covers: not checked

Bills and laws in Georgia

All 14 in Bill Watch

Who's involved

Power

Capacity, as announced or filed

  • 60.5 MW · FTY01 facility generator fleet (Douglasville, Douglas County)Feb 2022 · generator_capacity
  • 60.5 MW · Building 1 generator fleet, Permit No. 7376-097-0097-S-01-0Oct 2022 · generator_capacity

From the filings

Numbers stated in permits, agreements, and decisions, as printed. Each links to the filing.

  • Development Authority of the City of Douglasville; City of Douglasville, Tax Incentives Agreement dated December 21, 2020 (Series 2020 Bond); RES-2020-46 (2020-11-16); RES-2020-52 (2020-12-07); first amendment RES-2021-82 (2021-11-15)

    Stated in the filing
    $400 million
    Stated in the filing
    20 net new full-time jobs
    Stated in the filing
    $34 per hour (minimum average hourly wage, excluding benefits)
  • Georgia Environmental Protection Division, Air Protection Branch, Application No. 29231

    Stated in the filing
    21 generators proposed at Building 2 (GN22-GN42: twenty 3,000 kW and one 500 kW), installation and construction 2025
    Stated in the filing
    99 tons per year sitewide NOx limit (synthetic minor)
    Stated in the filing
    2023-01 Building 1 generator installation date (construction August 2022) per EPD equipment list
    Stated in the filing
    42 generators facility-wide if Permit -01-1 issues as recommended (GN1-GN42)
    Stated in the filing
    2022-10-13 date Permit No. 7376-097-0097-S-01-0 was issued (per EPD narrative)
  • Atlanta Regional Commission (review); Georgia Department of Community Affairs (DRI program), DRI #3426; ARC review code R2110181

    Stated in the filing
    $14.1 million estimated annual property tax, stated as to be made in PILOT payment
    Stated in the filing
    159.5 acres (site area as computed on the DRI form: 67.94 impervious acres of 159.50 acres)
    Water flow
    1,050,000 gallons per day (estimated water supply demand, 1.05 MGD)
    Stated in the filing
    980,000 sq ft
    Stated in the filing
    0.266 MGD (estimated sewage flow)
    Stated in the filing
    $125 million estimated value at build-out, as stated
    Stated in the filing
    4 buildings
  • Georgia Environmental Protection Division, Air Protection Branch, Permit No. 7376-097-0097-S-01-0 (Application No. 28295; AIRS No. 04-13-097-00097)

    Generator capacityEstimated
    60.5 MWSee the project_capacity row cap-microsoft-fty01-generator-fleet-b1 for the ruling basis.
    Stated in the filing
    21 generators
    Stated in the filing
    500 hours per year per generator (total annual operation must be less than 500)

Public records

9 records found so far. 5 kinds of record are still being collected.

See every record

Questions people ask

Where is Microsoft FTY01 (Douglasville)?
Microsoft FTY01 (Douglasville) is a data center project in Douglasville, Douglas County, Georgia.
Who operates Microsoft FTY01 (Douglasville)?
Microsoft is named as the operator of Microsoft FTY01 (Douglasville).
How big is Microsoft FTY01 (Douglasville)?
The site covers 160 acres.
What stage is Microsoft FTY01 (Douglasville)?
Microsoft FTY01 (Douglasville) is under construction. It was first public in 2021.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    City Council Regular Meeting agenda packet, September 8, 2026, Item 26-301 (RES-2026-37) with the Tax Incentives Agreement, RES-2020-52, and RES-2021-82 attached
    City of Douglasville (CivicWeb)
    Tier 1 · Captured 2026-11-09 · Open the source
  2. 2
    SIP Application Review Narrative, Application No. 29231: Microsoft Corporation - FTY01 Facility (Jada Levers, May 21, 2024, with addendum)
    Georgia Environmental Protection Division, Air Protection Branch
    Tier 1 · Captured 2026-11-09 · Open the source
  3. 3
    ARC Preliminary Report: FTY01 1601 North River Road, DRI #3426 (ARC review code R2110181)
    Atlanta Regional Commission
    Tier 1 · Captured 2026-11-09 · Open the source
  4. 4
    Microsoft aiming to build 1 million sq ft data center in Douglasville, GA (FTY101 DRI, 2021-08-19)
    Elevate Douglas Economic Partnership
    Tier 1 · Captured 2026-11-08 · Open the source
  5. 5
    Air Quality Permit No. 7376-097-0097-S-01-0: Microsoft Corporation - FTY01 Facility, Douglasville, Douglas County
    Georgia Environmental Protection Division, Air Protection Branch
    Tier 1 · Captured 2026-11-08 · Open the source
  6. 6
    City Council Regular Meeting minutes, September 8, 2026 (published in the September 21, 2026 agenda packet)
    City of Douglasville (CivicWeb)
    Tier 1 · Captured 2026-11-09 · Open the source
  7. 7
    Staff report for special use permit application S2025-13 (March 3 2026 meeting)
    Douglas County Georgia
    Tier 1 · Captured 2026-11-08 · Open the source
  8. 8
    Board of Commissioners minutes June 17 2025
    Douglas County Georgia
    Tier 1 · Captured 2026-11-08 · Open the source
  9. 9
    Microsoft will establish its next U.S. datacenter region in Georgia's Fulton and Douglas Counties (2021-02-11)
    Microsoft Azure Blog
    Tier 4 · Captured 2026-11-08 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page