Every public record we have for Microsoft FTY01 (Douglasville)

Douglasville, Douglas County, GeorgiaUnder constructionFirst public 2021Filing entity: Microsoft CorporationLast checked Nov 9, 2026

Download CSV

Records marked draft were traced to their source by an AI research agent and have not passed verification yet.

What the public record holds

2 of 9 records · showing tax breaks and payments only ·

2020

  • Tax agreementReplaced by a later filingDec 21, 2020Development Authority of the City of Douglasville; City of Douglasville

    Development Authority of the City of Douglasville; City of Douglasville, Tax Incentives Agreement dated December 21, 2020 (Series 2020 Bond); RES-2020-46 (2020-11-16); RES-2020-52 (2020-12-07); first amendment RES-2021-82 (2021-11-15)

    Executed December 21, 2020 in connection with the Authority's Taxable Industrial Development Revenue Bond (Microsoft Corporation Project), Series 2020, authorized December 1, 2020 in an amount not to exceed $400,000,000; terminated in 2026 (see the 2026 council minutes document)

    Announced investment:
    $400 million
    Expected jobs:
    20 net new full-time jobs
    Stated in the filing:
    $34 per hour (minimum average hourly wage, excluding benefits)
    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Agreement text and Schedule 1 (Tax Incentive Schedule): fixed PILOT payments for Years 1-15; performance goals of $400 million investment, 20 net new full-time jobs, and a $33.65 minimum average hourly wage by December 31, 2025

  • Tax agreementDec 7, 2020Douglasville

    Bond lease and payment in lieu of taxes agreement (Development Authority of the City of Douglasville; City of Douglasville Revised 2020 Tax Plan)

    The Authority held title under a lease structure financed by its Series 2020 taxable industrial development revenue bond (not to exceed $400,000,000), and Microsoft paid fixed payments in lieu of taxes under Schedule 1 of the Tax Incentives Agreement instead of normal ad valorem tax: $500,000 per year in Years 1 through 5, then rising 15 percent per year to $2,022,778.87 in Year 15. Year 1 commences on the earlier of January 1 of the first calendar year after a certificate of occupancy for any portion of the project, or January 1, 2024; during the construction period the project is valued at 75 percent of fair market value for PILOT purposes. Property transferred to the Authority is capped at $400 million at original cost; anything above that pays normal ad valorem tax. Performance goals: at least $400 million of capital investment, 20 net new full-time jobs, and a minimum average hourly wage of $33.65 excluding benefits by the calendar year ending December 31, 2025, with repayment of tax incentives (the Reduced Amount, adjusted by actual performance) on a shortfall. First amendment approved by RES-2021-82 (November 15, 2021). TERMINATED: Microsoft exercised its option to purchase the project; the Authority approved the bond cancellation on August 28, 2026 and the City Council adopted RES-2026-37 on September 8, 2026 approving the Cancellation of Bond and Termination of Bond Documents, ending the Tax Incentives Agreement; under the agreement the project reverts to normal ad valorem taxation from January 1 of the year after the lease terminates.

    Draft research, not yet verifiedLast checked Nov 9, 2026
    Where it says this

    Tax Incentives Agreement Sections 1, 5, and 8 and Schedule 1; RES-2020-52 (December 7, 2020); RES-2026-37 in the September 8, 2026 minutes

Records we are still collecting

These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.

  • Building and site permits

    Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.

  • Water supply and use

    Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.

  • Power and utility

    Interconnection, large load rate classes, utility agreements, commission dockets. Usually held by: Electric utility and utility commission.

  • Courts and disputes

    Lawsuits, appeals, settlements. Usually held by: State and federal courts.

  • Company filings

    Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.

Sources

  1. 1
    City Council Regular Meeting agenda packet, September 8, 2026, Item 26-301 (RES-2026-37) with the Tax Incentives Agreement, RES-2020-52, and RES-2021-82 attached
    City of Douglasville (CivicWeb)
    Tier 1 · Captured 2026-11-09 · Open the source
  2. 2
    SIP Application Review Narrative, Application No. 29231: Microsoft Corporation - FTY01 Facility (Jada Levers, May 21, 2024, with addendum)
    Georgia Environmental Protection Division, Air Protection Branch
    Tier 1 · Captured 2026-11-09 · Open the source
  3. 3
    ARC Preliminary Report: FTY01 1601 North River Road, DRI #3426 (ARC review code R2110181)
    Atlanta Regional Commission
    Tier 1 · Captured 2026-11-09 · Open the source
  4. 4
    Microsoft aiming to build 1 million sq ft data center in Douglasville, GA (FTY101 DRI, 2021-08-19)
    Elevate Douglas Economic Partnership
    Tier 1 · Captured 2026-11-08 · Open the source
  5. 5
    Air Quality Permit No. 7376-097-0097-S-01-0: Microsoft Corporation - FTY01 Facility, Douglasville, Douglas County
    Georgia Environmental Protection Division, Air Protection Branch
    Tier 1 · Captured 2026-11-08 · Open the source
  6. 6
    City Council Regular Meeting minutes, September 8, 2026 (published in the September 21, 2026 agenda packet)
    City of Douglasville (CivicWeb)
    Tier 1 · Captured 2026-11-09 · Open the source
  7. 7
    Staff report for special use permit application S2025-13 (March 3 2026 meeting)
    Douglas County Georgia
    Tier 1 · Captured 2026-11-08 · Open the source
  8. 8
    Board of Commissioners minutes June 17 2025
    Douglas County Georgia
    Tier 1 · Captured 2026-11-08 · Open the source
  9. 9
    Microsoft will establish its next U.S. datacenter region in Georgia's Fulton and Douglas Counties (2021-02-11)
    Microsoft Azure Blog
    Tier 4 · Captured 2026-11-08 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page