Project File · Public records
Every public record we have for Microsoft FTY01 (Douglasville)
Douglasville, Douglas County, GeorgiaUnder constructionFirst public 2021Filing entity: Microsoft CorporationLast checked Nov 9, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
9 of 9 records
2026
Public decisionApprovedSep 8, 2026City of Douglasville
City of Douglasville, RES-2026-37 (Item 26-301), consent agenda item 7.A
Adopted as part of the consent agenda: AYES Caldwell, Davis, Hudson, Mayor Pro Tem T. Miller, and Watts; ABSENT Estes and N. Miller
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Minutes of September 8, 2026, item 7: consent agenda motion by Councilmember Davis, seconded by Councilmember Caldwell, RESULT: ADOPTED; item 7.A is RES-2026-37
Recorded voteSep 8, 2026Douglasville City Council
Adopt RES-2026-37 approving the execution and delivery of a Cancellation of Bond and Termination of Bond Documents with Microsoft Corporation and the Development Authority of the City of Douglasville, Georgia, and terminating the Tax Incentives Agreement dated December 21, 2020, related to the Microsoft Corporation Project (consent agenda item 7.A, Item 26-301)
5 yes, 2 absent. Chris Watts (Councilmember): yes; Devetrion Caldwell (Councilmember): yes; Elena Hudson (Councilmember): yes; Howard Estes (Councilmember): absent; Nycole Miller (Councilmember): absent; Samuel Davis (Councilmember): yes; Terry Miller (Councilmember (Mayor Pro Tem)): yes.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Minutes of September 8, 2026, item 7 (Consent Agenda): motion by Councilmember Davis, seconded by Councilmember Caldwell, RESULT: ADOPTED; AYES and ABSENT printed by name
2025
Zoning ruleIn effectSep 2025Douglas County
Data center zoning amendments adopted after the 2025 moratorium
After its 2025 moratorium Douglas County adopted zoning text amendments for data centers; under the amended code a data center over 50000 square feet requires a special use permit.
Unified Development Code text amendments (September 2025)
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
Staff report for application S2025-13 (2026-03-03) reciting that text amendments responsive to the moratorium were adopted in September 2025
Development ruleExpiredMar 20, 2025Douglas County
Moratorium on data center applications over 50000 square feet
Douglas County paused land use map amendments rezonings special use permits variances and public hearings for data center campuses over 50000 square feet while it studied the use; the Board extended the pause once and then replaced it with adopted zoning text amendments in September 2025.
Board of Commissioners moratorium resolution (2025)
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
Minutes of 2025-06-17 item 6 (extension approved 5-0; staff stated the moratorium expired the next day); county staff report for application S2025-13 (2026-03-03)
2024
Public decisionUnder reviewMay 21, 2024Georgia Environmental Protection Division, Air Protection Branch
Georgia Environmental Protection Division, Air Protection Branch, Application No. 29231
Narrative (May 21, 2024) recommends issuing Permit No. 7376-097-0097-S-01-1 for 21 additional emergency generators at Building 2 (GN22-GN42); the 30-day public review ended June 21, 2024 with no comments. Issuance of the -01-1 permit was not verified in this pass.
- Phase 2 emergency generators proposed:
- 21 generators proposed at Building 2 (GN22-GN42: twenty 3,000 kW and one 500 kW), installation and construction 2025
- Stated in the filing:
- 99 tons per year sitewide NOx limit (synthetic minor)
- Stated in the filing:
- 2023-01 Building 1 generator installation date (construction August 2022) per EPD equipment list
- Emergency generators proposed total:
- 42 generators facility-wide if Permit -01-1 issues as recommended (GN1-GN42)
- Stated in the filing:
- 2022-10-13 date Permit No. 7376-097-0097-S-01-0 was issued (per EPD narrative)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Background Information and Updated Equipment List (Table 1): Building 1 GN1-GN21 installed January 2023, construction August 2022; Building 2 GN22-GN42 installation and construction 2025
2022
Air permitIssuedOct 13, 2022Georgia Environmental Protection Division, Air Protection Branch
Georgia Environmental Protection Division, Air Protection Branch, Permit No. 7376-097-0097-S-01-0 (Application No. 28295; AIRS No. 04-13-097-00097)
Issued October 13, 2022 (issuance date per the EPD narrative for Application No. 29231; the posted permit copy leaves its issuance-date field blank)
- Generator capacity:
- 60.5 MW
- Emergency generators:
- 21 generators
- Operating hours cap:
- 500 hours per year per generator (total annual operation must be less than 500)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Permit cover page: installation and operation of twenty 3,000 kW emergency generators and one 500 kW emergency generator at 1601 North River Road, Douglasville, GA 30122
2021
Public decisionFiledOct 18, 2021Atlanta Regional Commission (review); Georgia Department of Community Affairs (DRI program)
Atlanta Regional Commission (review); Georgia Department of Community Affairs (DRI program), DRI #3426; ARC review code R2110181
Preliminary regional review completed; submitting local government is the City of Douglasville; DRI trigger is a land disturbance permit
- Stated in the filing:
- $14.1 million estimated annual property tax, stated as to be made in PILOT payment
- Acres:
- 159.5 acres (site area as computed on the DRI form: 67.94 impervious acres of 159.50 acres)
- Water flow:
- 1,050,000 gallons per day (estimated water supply demand, 1.05 MGD)
- Building gross area:
- 980,000 sq ft
- Stated in the filing:
- 0.266 MGD (estimated sewage flow)
- Stated in the filing:
- $125 million estimated value at build-out, as stated
- Data center buildings planned:
- 4 buildings
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Description and DRI Additional Information Form: 980,000 sq ft of data center warehouse across 4 buildings on a 160-acre parcel at 1601 North River Road; developer/applicant and property owner Microsoft Corporation
2020
Tax agreementReplaced by a later filingDec 21, 2020Development Authority of the City of Douglasville; City of Douglasville
Development Authority of the City of Douglasville; City of Douglasville, Tax Incentives Agreement dated December 21, 2020 (Series 2020 Bond); RES-2020-46 (2020-11-16); RES-2020-52 (2020-12-07); first amendment RES-2021-82 (2021-11-15)
Executed December 21, 2020 in connection with the Authority's Taxable Industrial Development Revenue Bond (Microsoft Corporation Project), Series 2020, authorized December 1, 2020 in an amount not to exceed $400,000,000; terminated in 2026 (see the 2026 council minutes document)
- Announced investment:
- $400 million
- Expected jobs:
- 20 net new full-time jobs
- Stated in the filing:
- $34 per hour (minimum average hourly wage, excluding benefits)
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Agreement text and Schedule 1 (Tax Incentive Schedule): fixed PILOT payments for Years 1-15; performance goals of $400 million investment, 20 net new full-time jobs, and a $33.65 minimum average hourly wage by December 31, 2025
Tax agreementDec 7, 2020Douglasville
Bond lease and payment in lieu of taxes agreement (Development Authority of the City of Douglasville; City of Douglasville Revised 2020 Tax Plan)
The Authority held title under a lease structure financed by its Series 2020 taxable industrial development revenue bond (not to exceed $400,000,000), and Microsoft paid fixed payments in lieu of taxes under Schedule 1 of the Tax Incentives Agreement instead of normal ad valorem tax: $500,000 per year in Years 1 through 5, then rising 15 percent per year to $2,022,778.87 in Year 15. Year 1 commences on the earlier of January 1 of the first calendar year after a certificate of occupancy for any portion of the project, or January 1, 2024; during the construction period the project is valued at 75 percent of fair market value for PILOT purposes. Property transferred to the Authority is capped at $400 million at original cost; anything above that pays normal ad valorem tax. Performance goals: at least $400 million of capital investment, 20 net new full-time jobs, and a minimum average hourly wage of $33.65 excluding benefits by the calendar year ending December 31, 2025, with repayment of tax incentives (the Reduced Amount, adjusted by actual performance) on a shortfall. First amendment approved by RES-2021-82 (November 15, 2021). TERMINATED: Microsoft exercised its option to purchase the project; the Authority approved the bond cancellation on August 28, 2026 and the City Council adopted RES-2026-37 on September 8, 2026 approving the Cancellation of Bond and Termination of Bond Documents, ending the Tax Incentives Agreement; under the agreement the project reverts to normal ad valorem taxation from January 1 of the year after the lease terminates.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Tax Incentives Agreement Sections 1, 5, and 8 and Schedule 1; RES-2020-52 (December 7, 2020); RES-2026-37 in the September 8, 2026 minutes
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Power and utility
Interconnection, large load rate classes, utility agreements, commission dockets. Usually held by: Electric utility and utility commission.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1City Council Regular Meeting agenda packet, September 8, 2026, Item 26-301 (RES-2026-37) with the Tax Incentives Agreement, RES-2020-52, and RES-2021-82 attached
City of Douglasville (CivicWeb)Tier 1 · Captured 2026-11-09 · Open the source - 2SIP Application Review Narrative, Application No. 29231: Microsoft Corporation - FTY01 Facility (Jada Levers, May 21, 2024, with addendum)
Georgia Environmental Protection Division, Air Protection BranchTier 1 · Captured 2026-11-09 · Open the source - 3ARC Preliminary Report: FTY01 1601 North River Road, DRI #3426 (ARC review code R2110181)
Atlanta Regional CommissionTier 1 · Captured 2026-11-09 · Open the source - 4Microsoft aiming to build 1 million sq ft data center in Douglasville, GA (FTY101 DRI, 2021-08-19)
Elevate Douglas Economic PartnershipTier 1 · Captured 2026-11-08 · Open the source - 5Air Quality Permit No. 7376-097-0097-S-01-0: Microsoft Corporation - FTY01 Facility, Douglasville, Douglas County
Georgia Environmental Protection Division, Air Protection BranchTier 1 · Captured 2026-11-08 · Open the source - 6City Council Regular Meeting minutes, September 8, 2026 (published in the September 21, 2026 agenda packet)
City of Douglasville (CivicWeb)Tier 1 · Captured 2026-11-09 · Open the source - 7Staff report for special use permit application S2025-13 (March 3 2026 meeting)
Douglas County GeorgiaTier 1 · Captured 2026-11-08 · Open the source - 8Board of Commissioners minutes June 17 2025
Douglas County GeorgiaTier 1 · Captured 2026-11-08 · Open the source - 9Microsoft will establish its next U.S. datacenter region in Georgia's Fulton and Douglas Counties (2021-02-11)
Microsoft Azure BlogTier 4 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page