Data Center Fact Check tracks 6 data center projects in Douglasville, Georgia as of November 2026: 3 under construction and 3 operating, totaling about 223 MW announced where a figure is published.
Douglasville has 6 tracked data centers. Their announced capacity totals about 223 MW where a figure is published. Of those, 3 under construction and 3 operating. Every project we track here is listed below, with the public records behind it. Every figure comes from the public record linked on this page.
Data center projects in Douglasville
- Aligned ATL-01
OperatingDouglasville
- Aligned Data Centers ATL-01 (Lithia Springs)
OperatingDouglasville
- DC BLOX Atlanta West (Douglasville)
Under constructionDouglasville200 MW announced
- Flexential Atlanta-Douglasville Campus
OperatingDouglasville23 MW announced
- Microsoft FTY01 (Douglasville)
Under constructionDouglasville
- Vantage Data Center Douglasville
Under constructionDouglasville
Who serves this place
- Not collected yet.
More places in Douglas County
Douglasville is part of Douglas County.
Nearby places
- Lithia Springs5 data center projects tracked
For homeowners
What the projects here mean if you live nearby
Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work
Property tax
Microsoft FTY01 (Douglasville):The campus's actual property tax bill is unpublished; for five years its deal substituted fixed payments for normal taxation.
Not known yet
Tax breaks
Microsoft FTY01 (Douglasville):From 2020 to 2026 the campus paid fixed payments in lieu of taxes under a city bond deal, below normal property tax.
Comes to the community
Money for schools and services
Microsoft FTY01 (Douglasville):No community payment by Microsoft for this campus is in the records read; its incentive deal required investment, jobs, and wages.
Not known yet
Electricity bill
Microsoft FTY01 (Douglasville):No record read in this pass names the electric utility serving this campus, so no local rate history can be shown yet.
Not known yet
Water
Microsoft FTY01 (Douglasville):The county water and sewer authority supplies this campus; its 2021 filing estimated demand at 1.05 million gallons a day.
Comes to the community
Jobs
Microsoft FTY01 (Douglasville):The campus's incentive deal promised twenty net new full-time jobs at a $33.65 average hourly wage by the end of 2025.
Comes from the community
Next door: height, setbacks, noise
Microsoft FTY01 (Douglasville):The site plan keeps 56 of about 160 acres open, behind city stream buffers of 50 feet plus a 25-foot setback.
Not known yet
Your say
Microsoft FTY01 (Douglasville):The one member-level vote on record, in September 2026, ended the campus's tax deal; the 2020 approval tallies were not printed in records read.
Not known yet
Tax breaks and payments
2020 · Microsoft FTY01 (Douglasville)
Bond lease and payment in lieu of taxes agreement (Development Authority of the City of Douglasville; City of Douglasville Revised 2020 Tax Plan)
The Authority held title under a lease structure financed by its Series 2020 taxable industrial development revenue bond (not to exceed $400,000,000), and Microsoft paid fixed payments in lieu of taxes under Schedule 1 of the Tax Incentives Agreement instead of normal ad valorem tax: $500,000 per year in Years 1 through 5, then rising 15 percent per year to $2,022,778.87 in Year 15. Year 1 commences on the earlier of January 1 of the first calendar year after a certificate of occupancy for any portion of the project, or January 1, 2024; during the construction period the project is valued at 75 percent of fair market value for PILOT purposes. Property transferred to the Authority is capped at $400 million at original cost; anything above that pays normal ad valorem tax.
All tax records for Microsoft FTY01 (Douglasville)
Court cases and commission dockets in Georgia (8)
Bills and laws in Georgia
- SB 410 · Passed one chamber · Mar 6, 2026Ends new data center tax breaks, sets large load contract terms
- SB 34 · Died or failed · Feb 26, 2026Bars shifting data center power costs onto other utility customers
- HB 1387 · Died or failed · Feb 20, 2026Funds homestead exemption from property taxes collected on data centers
- SB 530 · Died or failed · Feb 19, 2026Deposits data center tax collections into a property tax relief fund
- HB 1323 · Died or failed · Feb 18, 2026Requires new data centers to operate as hybrid power facilities
- HB 1063 · Passed one chamber · Feb 17, 2026Requires utility contracts shielding other customers from data center costs
- SB 476 · Died or failed · Feb 12, 2026Ends new data center sales tax exemption certificates statewide
- HB 1059 · Died or failed · Jan 29, 2026Bans new data center permits through 2028, creates impact commission
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Officials we track for Douglasville
The lawmakers and local officials whose recorded jurisdiction is Douglasville, with the bills and votes we have on record for each.
- Chris WattsCouncilmember · Ward 4
- Devetrion CaldwellCouncilmember · Ward 3, Post 1
- Elena HudsonCouncilmember · Ward 2, Post 2
- Howard EstesCouncilmember · Ward 5
- Nycole MillerCouncilmember · Ward 2, Post 1
- Samuel DavisCouncilmember · Ward 3, Post 2
- Terry MillerCouncilmember (Mayor Pro Tem) · Ward 1
Questions people ask
- How many data centers are in Douglasville?
- Data Center Fact Check tracks 6 data center projects in Douglasville as of November 2026. Of those, 3 under construction and 3 operating.
- What is the biggest data center in Douglasville?
- By announced capacity, the biggest data center in Douglasville is DC BLOX Atlanta West (Douglasville), announced at 200 MW. It is under construction.
- How much power do data centers in Douglasville use?
- The 6 projects tracked in Douglasville have announced about 223 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
- 1City Council Regular Meeting agenda packet, September 8, 2026, Item 26-301 (RES-2026-37) with the Tax Incentives Agreement, RES-2020-52, and RES-2021-82 attached
City of Douglasville (CivicWeb)Tier 1 · Open the source - 2City Council Regular Meeting minutes, September 8, 2026 (published in the September 21, 2026 agenda packet)
City of Douglasville (CivicWeb)Tier 1 · Open the source - 3Air Quality Permit No. 7376-097-0097-S-01-0: Microsoft Corporation - FTY01 Facility, Douglasville, Douglas County
Georgia Environmental Protection Division, Air Protection BranchTier 1 · Open the source - 4ARC Preliminary Report: FTY01 1601 North River Road, DRI #3426 (ARC review code R2110181)
Atlanta Regional CommissionTier 1 · Open the source - 5Microsoft will establish its next U.S. datacenter region in Georgia's Fulton and Douglas Counties (2021-02-11)
Microsoft Azure BlogTier 4 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Douglasville." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-ga-douglasville
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page