Skip to content

Project File

Edged Atlanta Campus (Tilford Yard)

Atlanta,Fulton County,GeorgiaExpandingFirst public 2025Last checked Nov 13, 2026

EdgedDeveloper and operator

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

5 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: First public date
  • Still to confirm: Electric utility
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Edged Atlanta Campus (Tilford Yard) is an expanding data center project in Atlanta, Fulton County, Georgia. Edged is named as operator. It was first public in 2025. It was announced at 168 MW.

Edged Atlanta Campus (Tilford Yard) is an expanding data center project in Atlanta, Fulton County, Georgia. Edged is named as operator. It was announced at 168 MW. 5 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Atlanta, Fulton County, Georgia. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

168 MWAnnounced capacity
1Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Fulton County, Georgia.See every project on the map

Timeline

  1. · New projectFirst public record of Edged Atlanta Campus (Tilford Yard)Expanding

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Georgia HB 1063: Requires utility contracts shielding other customers from data center costs

    The act covers data centers with a peak annual electricity demand of 100 megawatts or greater, under agreements with an electric utility entered into on or after the effective date of the act; this project has 168 MW announced on record, but the project's peak annual electricity demand and the date of its electric service agreement is not on record.

    “As used in this part, the term 'data center' means a facility, campus of facilities, or array of interconnected facilities used by an entity or other business enterprise to operate, manage, or maintain a computer, group of computers, or other organized assembly of hardware and software for the primary purpose of processing, storing, retrieving, or transmitting data and that have a peak annual electricity demand of 100 megawatts or greater.” (Section 1, new Code Section 46-3-80)

    Rule checks: Project is in Georgia; 168 MW on record (announced), threshold 100 MW (Section 1, new Code Section 46-3-80). Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Georgia SB 410: Ends new data center tax breaks, sets large load contract terms

    The act covers large load customers with an expected total peak demand of 100 megawatts or greater at premises on one tract or contiguous tracts of land, under contracts entered into on or after the effective date of the act; this project has 168 MW announced on record, but the project's expected total peak demand and the date of its electric service contract is not on record.

    “As used in this Code section, the term 'large load customer' means customers with an expected total peak demand of 100 megawatts or greater at one or more premises located on one tract or contiguous tracts of land.” (Part I, Section 1-2, new Code Section 46-2-25.4(a))

    Rule checks: Project is in Georgia; 168 MW on record (announced), threshold 100 MW (Part I, Section 1-2, new Code Section 46-2-25.4(a)). Still to check: who it covers: not checked

Bills and laws in Georgia

All 14 in Bill Watch

Who's involved

  • Developer and operatorEdged

Public records

1 records found so far. 8 kinds of record are still being collected.

See every record

Questions people ask

Where is Edged Atlanta Campus (Tilford Yard)?
Edged Atlanta Campus (Tilford Yard) is a data center project in Atlanta, Fulton County, Georgia.
Who operates Edged Atlanta Campus (Tilford Yard)?
Edged is named as the operator of Edged Atlanta Campus (Tilford Yard).
How big is Edged Atlanta Campus (Tilford Yard)?
Edged Atlanta Campus (Tilford Yard) was announced at 168 MW of capacity.
What stage is Edged Atlanta Campus (Tilford Yard)?
Edged Atlanta Campus (Tilford Yard) is expanding. It was first public in 2025.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Atlanta City Council votes to define data centers limit locations
    Atlanta City Council
    Tier 1 · Captured 2026-11-08 · Open the source
  2. 2
    PowerSecure powers Edged Energy’s new sustainable data center in Atlanta
    PowerSecure (Southern Company)
    Tier 4 · Captured 2026-11-08 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page