Project File

Google Columbia County Data Center (White Oak Technology Park)

Columbia County,GeorgiaApprovedFirst public 2026Filing entity: TC Green Jacket, LLCLast checked Nov 8, 2026

TC Green JacketDeveloperTurner ConstructionBuilderGoogleEnd user and operatorDevelopment Authority of Columbia CountyPublic partner

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

5 of 6 details confirmed

  • Confirmed: County
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: Electric utility
  • Confirmed: First public date
  • Still to confirm: City or address
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Google Columbia County Data Center (White Oak Technology Park) is an approved data center project in Columbia County, Georgia. Google is named as operator. It was first public in 2026. It was announced at 1,400 MW.

Google Columbia County Data Center (White Oak Technology Park) is an approved data center project in Columbia County, Georgia. Google is named as operator. It was announced at 1,400 MW. 5 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Columbia County, Georgia. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

1,400 MWAnnounced capacity
7Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Columbia County, Georgia.See every project on the map

The land, to scale

One football field
3,140 acres, about 2,375 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · New projectFirst public record of Google Columbia County Data Center (White Oak Technology Park)Approved

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Georgia HB 1063: Requires utility contracts shielding other customers from data center costs

    The act covers data centers with a peak annual electricity demand of 100 megawatts or greater, under agreements with an electric utility entered into on or after the effective date of the act; this project has 1,400 MW announced on record, but the project's peak annual electricity demand and the date of its electric service agreement is not on record.

    “As used in this part, the term 'data center' means a facility, campus of facilities, or array of interconnected facilities used by an entity or other business enterprise to operate, manage, or maintain a computer, group of computers, or other organized assembly of hardware and software for the primary purpose of processing, storing, retrieving, or transmitting data and that have a peak annual electricity demand of 100 megawatts or greater.” (Section 1, new Code Section 46-3-80)

    Rule checks: Project is in Georgia; 1,400 MW on record (announced), threshold 100 MW (Section 1, new Code Section 46-3-80). Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Georgia SB 410: Ends new data center tax breaks, sets large load contract terms

    The act covers large load customers with an expected total peak demand of 100 megawatts or greater at premises on one tract or contiguous tracts of land, under contracts entered into on or after the effective date of the act; this project has 1,400 MW announced on record, but the project's expected total peak demand and the date of its electric service contract is not on record.

    “As used in this Code section, the term 'large load customer' means customers with an expected total peak demand of 100 megawatts or greater at one or more premises located on one tract or contiguous tracts of land.” (Part I, Section 1-2, new Code Section 46-2-25.4(a))

    Rule checks: Project is in Georgia; 1,400 MW on record (announced), threshold 100 MW (Part I, Section 1-2, new Code Section 46-2-25.4(a)). Still to check: who it covers: not checked

Bills and laws in Georgia

All 14 in Bill Watch

Who's involved

Public records

7 records found so far. 8 kinds of record are still being collected.

See every record

Questions people ask

Where is Google Columbia County Data Center (White Oak Technology Park)?
Google Columbia County Data Center (White Oak Technology Park) is a data center project in Columbia County, Georgia.
Who operates Google Columbia County Data Center (White Oak Technology Park)?
Google is named as the operator of Google Columbia County Data Center (White Oak Technology Park).
How big is Google Columbia County Data Center (White Oak Technology Park)?
Google Columbia County Data Center (White Oak Technology Park) was announced at 1,400 MW of capacity. The site covers 3,140 acres.
What stage is Google Columbia County Data Center (White Oak Technology Park)?
Google Columbia County Data Center (White Oak Technology Park) is approved. It was first public in 2026.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Order Approving Revisions to Georgia Power Company's Rules and Regulations, Docket No. 44280, with the PSC news release of January 23, 2025 (Exhibits Q and P)
    Georgia Public Service Commission
    Tier 1 · Captured 2026-11-07 · Open the source
  2. 2
    Schedule PLL-18, Power and Light Large
    Georgia Power Company
    Tier 1 · Captured 2026-11-08 · Open the source
  3. 3
    Stipulation, Docket Nos. 56002 and 56003, Georgia Power 2025 Integrated Resource Plan
    Georgia Public Service Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  4. 4
    Electric Service Tariff, Schedule TOU-RN-14, Time of Use, Revenue Neutral (effective with bills for the billing month of June 2026)
    Georgia Power Company
    Tier 1 · Captured 2026-11-08 · Open the source
  5. 5
    Order Adopting Stipulation and Granting Certification, Docket Nos. 56298 and 56310
    Georgia Public Service Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  6. 6
    Joint Statement of Commission Staff and Georgia Power Company Regarding Large Load Contract Deemed Filed for Purposes of Review, July 27, 2026 (statement dated August 26, 2026)
    Georgia Public Service Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  7. 7
    Commission Calendar, November 2026 (Docket No. 57171 hearing, November 12, 2026)
    Georgia Public Service Commission
    Tier 1 · Captured 2026-11-11 · Open the source
  8. 8
    Columbia County, Google and Georgia Power Partner to Protect Ratepayers and Make Growth Work for Residents
    Columbia County, Georgia
    Tier 1 · Captured 2026-11-08 · Open the source
  9. 9
    Planning Commission staff report, rezoning file RZ26-01-03 (multiple parcels to D-C Data Center)
    Columbia County Planning Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  10. 10
    DRI #4736 Initial Information Form: Project JGK-Mass Grading
    Georgia Department of Community Affairs
    Tier 1 · Captured 2026-11-08 · Open the source
  11. 11
    DRI #4736 Information Form Part 2: Project JGK-Mass Grading
    Georgia Department of Community Affairs
    Tier 1 · Captured 2026-11-08 · Open the source
  12. 12
    Georgia - Google Data Center Locations
    Google
    Tier 4 · Captured 2026-11-08 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page