Utility commission
Schedule PLL-18, Power and Light Large
Where it stands: In effect as of Apr 1, 2025
Draft research, not yet verified. Open a source to check any detail.
What it is
The standard large service schedule, from 500 kW. Customers with expected total peak demand of 100 MW or more on one tract or contiguous tracts may take service under it only if they contracted for service before February 1, 2025; larger new loads must use custom contracts under the 2025 rules. Minimum monthly bill is $256 plus $13.63 per kW of billing demand. Billing demand is never less than the greatest of the contract minimum, 50 percent of total contract capacity, or 500 kW. Contract term is 5 years.
The facts
- Regulator
- Georgia Public Service Commission
- Type
- Large load tariff
- Utility
- Georgia Power Company
- State
- Georgia
- Status date
- Apr 1, 2025
- Large-load rules
- Yes, for loads of 0.5 MW or more
Projects served by Georgia Power Company
- CoreSite AT1 Atlanta
- DataBank Lithia Springs Campus (ATL5 and ATL6)
- DC BLOX Atlanta East (Conyers)
- Digital Realty Atlanta Connected Campus (ATL13 and ATL14)
- EdgeConneX Atlanta Campus (ATL01 and ATL02)
- Equinix AT1 Atlanta
- Equinix AT4 Atlanta
- Google Columbia County Data Center (White Oak Technology Park)
- Google Douglas County data center
- H5 Data Centers Atlanta
- Microsoft ATL80
- Nixon Technology Center
Related cases and proceedings
- Utility commission · DecidedLarge Load Contract deemed filed for review under the Docket No. 44280 Large Load Contract Review Process (Joint Statement of Commission Staff and Georgia Power Company, July 27, 2026)
- Utility commission · In effectTime of Use, Revenue Neutral, Schedule TOU-RN-14
- Utility commission · DecidedGeorgia Power Company’s Applications for the Certification of Capacity from the 2029-2031 All-Source RFP (Docket 56298) and of Supplemental Resources for 2028-2031 Capacity (Docket 56310)
- Utility commission · DecidedGeorgia Power Company’s 2025 Integrated Resource Plan
- Utility commission · DecidedOrder Approving Revisions to Georgia Power Company's Rules and Regulations (large load rules)
- Utility commission · Pending before the commissionRTP Revenue Credit and Allocation Methodology
Sources
- 1Schedule PLL-18, Power and Light Large
Georgia Power CompanyTier 1 · Schedule PLL-18, First Revision page 5.00, pages 1-3 (Applicability cutoff; Monthly Rate and Minimum Monthly Bill; Term of Contract) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Schedule PLL-18, Power and Light Large." Last activity 2025-04-01. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-georgia-power-pll18