Georgia Power Company’s 2025 Integrated Resource Plan
Where it stands: Decided as of Jul 15, 2025
Draft research, not yet verified. Open a source to check any detail.
What it is
Commission approved the July 15, 2025 Stipulation. Georgia Power must file Large Load Economic Development Reports quarterly covering the large load queue, enrollment in demand management and battery storage programs, customer surveys, engagement outcomes, and challenges. By stipulation the Commission authorized Georgia Power to file for certification of 6,000 to 8,500 MW of resources. (The companion docket 56003 is the 2025 Demand-Side Management plan.)
The facts
- Regulator
- Georgia Public Service Commission
- Docket number
- 56002
- Type
- Other
- Utility
- Georgia Power Company
- State
- Georgia
- Filed
- Jan 31, 2025
- Status date
- Jul 15, 2025
- Large-load rules
- Yes
Projects served by Georgia Power Company
- CoreSite AT1 Atlanta
- DataBank Lithia Springs Campus (ATL5 and ATL6)
- DC BLOX Atlanta East (Conyers)
- Digital Realty Atlanta Connected Campus (ATL13 and ATL14)
- EdgeConneX Atlanta Campus (ATL01 and ATL02)
- Equinix AT1 Atlanta
- Equinix AT4 Atlanta
- Google Columbia County Data Center (White Oak Technology Park)
- Google Douglas County data center
- H5 Data Centers Atlanta
- Microsoft ATL80
- Nixon Technology Center
Related cases and proceedings
- Court case · PendingMorris et al. v. Meta Platforms, Inc. et al. (Stanton Springs wells)
- Utility commission · DecidedLarge Load Contract deemed filed for review under the Docket No. 44280 Large Load Contract Review Process (Joint Statement of Commission Staff and Georgia Power Company, July 27, 2026)
- Utility commission · In effectTime of Use, Revenue Neutral, Schedule TOU-RN-14
- Utility commission · DecidedGeorgia Power Company’s Applications for the Certification of Capacity from the 2029-2031 All-Source RFP (Docket 56298) and of Supplemental Resources for 2028-2031 Capacity (Docket 56310)
- Utility commission · In effectSchedule PLL-18, Power and Light Large
- Utility commission · DecidedOrder Approving Revisions to Georgia Power Company's Rules and Regulations (large load rules)
- Utility commission · Pending before the commissionRTP Revenue Credit and Allocation Methodology
In the record
- Utility case, Jan 31, 2025. Utility case filed: Georgia Power Company’s 2025 Integrated Resource Plan Georgia Public Service Commission, 56002
Sources
- 1Stipulation, Docket Nos. 56002 and 56003, Georgia Power 2025 Integrated Resource Plan
Georgia Public Service CommissionTier 1 · PSC 2025 Annual Report, pp. 6-7 (56002 approval July 15, 2025; quarterly report requirement; certification authorization); Order Adopting Stipulation issued July 31, 2025 · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Georgia Power Company’s 2025 Integrated Resource Plan." Last activity 2025-07-15. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-georgia-power-irp-2025