Large Load Contract deemed filed for review under the Docket No. 44280 Large Load Contract Review Process (Joint Statement of Commission Staff and Georgia Power Company, July 27, 2026)

Where it stands: Decided as of Aug 26, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

A customer whose peak demand is less than 100 MW is not a large load customer and the Contract Review Process does not apply. If the Commission allows the customer to terminate early and the termination fee is less than the customer’s obligation, Georgia Power will record the deficiency as a regulatory asset, will not seek recovery of any deficiency balance from non-large-load customers, and will not seek a return on the deficiency balance. Georgia Power files a semi annual Large Load Portfolio Report within ninety days after each six month contract period. Six contracts were previously reviewed under this process.

The facts

Regulator
Georgia Public Service Commission
Docket number
44280
Type
Other
Utility
Georgia Power Company
State
Georgia
Filed
Jul 27, 2026
Status date
Aug 26, 2026
Large-load rules
Yes, for loads of 100 MW or more

Projects served by Georgia Power Company

Related cases and proceedings

In the record

  1. Utility case, Jul 27, 2026. Utility case filed: Large Load Contract deemed filed for review under the Docket No. 44280 Large Load Contract Review Process (Joint Statement of Commission Staff and Georgia Power Company, July 27, 2026) Georgia Public Service Commission, 44280

Sources

  1. 1
    Joint Statement of Commission Staff and Georgia Power Company Regarding Large Load Contract Deemed Filed for Purposes of Review, July 27, 2026 (statement dated August 26, 2026)
    Georgia Public Service Commission
    Tier 1 · Joint Statement, paras. 1-3 (contract deemed filed July 27, 2026; statement filed August 26, 2026), paras. 10-11 (termination deficiency; semi annual report), para. B (six contracts previously reviewed) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Large Load Contract deemed filed for review under the Docket No. 44280 Large Load Contract Review Process (Joint Statement of Commission Staff and Georgia Power Company, July 27, 2026)." Last activity 2026-08-26. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-georgia-power-large-load-contract-review-2026