What it is
Commission investigation into how Georgia Power credits Real Time Pricing (RTP) revenue against fuel costs. RTP is the schedule used by the company’s largest customers, including data centers. The question is whether the current method shifts fuel, firm pipeline transportation and hedging costs from RTP and large load customers to other customer classes; Public Interest Advocacy Staff estimated in the parent fuel case (Docket 56765) that it could raise other customers’ per-unit fuel cost 5 to 11 percent by 2028 and leave about $118 million of 2027 pipeline costs outside the RTP class. Hearings were held September 1 and October 15, 2026, with a further hearing on November 12, 2026; findings are due by December 31, 2026 under the May 28, 2026 fuel case stipulation.
The facts
- Regulator
- Georgia Public Service Commission
- Docket number
- 57171
- Type
- Other
- Utility
- Georgia Power Company
- State
- Georgia
- Large-load rules
- Yes
Projects served by Georgia Power Company
- CoreSite AT1 Atlanta
- DataBank Lithia Springs Campus (ATL5 and ATL6)
- DC BLOX Atlanta East (Conyers)
- Digital Realty Atlanta Connected Campus (ATL13 and ATL14)
- EdgeConneX Atlanta Campus (ATL01 and ATL02)
- Equinix AT1 Atlanta
- Equinix AT4 Atlanta
- Google Columbia County Data Center (White Oak Technology Park)
- Google Douglas County data center
- H5 Data Centers Atlanta
- Microsoft ATL80
- Nixon Technology Center
Related cases and proceedings
- Utility commission · DecidedGeorgia Power Company’s Applications for the Certification of Capacity from the 2029-2031 All-Source RFP (Docket 56298) and of Supplemental Resources for 2028-2031 Capacity (Docket 56310)
- Utility commission · DecidedGeorgia Power Company’s 2025 Integrated Resource Plan
- Utility commission · In effectSchedule PLL-18, Power and Light Large
- Utility commission · DecidedOrder Approving Revisions to Georgia Power Company's Rules and Regulations (large load rules)
Sources
- 1Commission Calendar, November 2026 (Docket No. 57171 hearing, November 12, 2026)
Georgia Public Service CommissionTier 1 · Commission Calendar, November 2026, November 12 entry (9:35 am, Docket No. 57171 RTP Revenue Credit and Allocation Methodology Hearing); PSC homepage Upcoming Events list, same entry · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "RTP Revenue Credit and Allocation Methodology." Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-georgia-power-rtp-57171