Time of Use, Revenue Neutral, Schedule TOU-RN-14
Where it stands: In effect as of Jun 1, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
Customers whose peak demand equals or exceeds 100 MW may take service under Schedule TOU-RN only if they were under contract for service under Schedule TOU-RN prior to February 1, 2025. Contract period 12 months; minimum monthly bill is the basic service charge plus applicable riders; summer peak energy is offset by countervailing winter energy charges.
The facts
- Regulator
- Georgia Public Service Commission
- Type
- Large load tariff
- Utility
- Georgia Power Company
- State
- Georgia
- Filed
- Jun 1, 2026
- Status date
- Jun 1, 2026
- Large-load rules
- Yes, for loads of 100 MW or more
Projects served by Georgia Power Company
- CoreSite AT1 Atlanta
- DataBank Lithia Springs Campus (ATL5 and ATL6)
- DC BLOX Atlanta East (Conyers)
- Digital Realty Atlanta Connected Campus (ATL13 and ATL14)
- EdgeConneX Atlanta Campus (ATL01 and ATL02)
- Equinix AT1 Atlanta
- Equinix AT4 Atlanta
- Google Columbia County Data Center (White Oak Technology Park)
- Google Douglas County data center
- H5 Data Centers Atlanta
- Microsoft ATL80
- Nixon Technology Center
Related cases and proceedings
- Court case · PendingMorris et al. v. Meta Platforms, Inc. et al. (Stanton Springs wells)
- Utility commission · DecidedLarge Load Contract deemed filed for review under the Docket No. 44280 Large Load Contract Review Process (Joint Statement of Commission Staff and Georgia Power Company, July 27, 2026)
- Utility commission · DecidedGeorgia Power Company’s Applications for the Certification of Capacity from the 2029-2031 All-Source RFP (Docket 56298) and of Supplemental Resources for 2028-2031 Capacity (Docket 56310)
- Utility commission · DecidedGeorgia Power Company’s 2025 Integrated Resource Plan
- Utility commission · In effectSchedule PLL-18, Power and Light Large
- Utility commission · DecidedOrder Approving Revisions to Georgia Power Company's Rules and Regulations (large load rules)
- Utility commission · Pending before the commissionRTP Revenue Credit and Allocation Methodology
In the record
- Utility case, Jun 1, 2026. Utility case filed: Time of Use, Revenue Neutral, Schedule TOU-RN-14 Georgia Public Service Commission
Sources
- 1Electric Service Tariff, Schedule TOU-RN-14, Time of Use, Revenue Neutral (effective with bills for the billing month of June 2026)
Georgia Power CompanyTier 1 · Schedule TOU-RN-14, Subsection J (100 MW restriction and February 1, 2025 contract cutoff), Subsections H-I (period and minimum bill); tariff footer (effective June 2026 billing month) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Time of Use, Revenue Neutral, Schedule TOU-RN-14." Last activity 2026-06-01. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-georgia-power-tou-rn-14-2026