Project File
75 South Data Center Campus
Spalding County,GeorgiaProposedFirst public 2026Filing entity: Industrial VI Enterprises, LLCLast checked Nov 13, 2026
Industrial VI EnterprisesDeveloper
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
4 of 6 details confirmed
- Confirmed: County
- Confirmed: Stage
- Confirmed: Capacity
- Confirmed: First public date
- Still to confirm: City or address
- Still to confirm: Electric utility
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
75 South Data Center Campus is a proposed data center project in Spalding County, Georgia. Industrial VI Enterprises is named as developer. It was first public in 2026. It was announced at 450 MW.
75 South Data Center Campus is a proposed data center project in Spalding County, Georgia. Industrial VI Enterprises is named as developer. It was announced at 450 MW. 4 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Spalding County, Georgia. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Timeline
- · New projectFirst public record of 75 South Data Center CampusProposed
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Georgia HB 1063: Requires utility contracts shielding other customers from data center costs
The act covers data centers with a peak annual electricity demand of 100 megawatts or greater, under agreements with an electric utility entered into on or after the effective date of the act; this project has 450 MW announced on record, but the project's peak annual electricity demand and the date of its electric service agreement is not on record.
“As used in this part, the term 'data center' means a facility, campus of facilities, or array of interconnected facilities used by an entity or other business enterprise to operate, manage, or maintain a computer, group of computers, or other organized assembly of hardware and software for the primary purpose of processing, storing, retrieving, or transmitting data and that have a peak annual electricity demand of 100 megawatts or greater.” (Section 1, new Code Section 46-3-80)
Rule checks: Project is in Georgia; 450 MW on record (announced), threshold 100 MW (Section 1, new Code Section 46-3-80). Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Georgia SB 410: Ends new data center tax breaks, sets large load contract terms
The act covers large load customers with an expected total peak demand of 100 megawatts or greater at premises on one tract or contiguous tracts of land, under contracts entered into on or after the effective date of the act; this project has 450 MW announced on record, but the project's expected total peak demand and the date of its electric service contract is not on record.
“As used in this Code section, the term 'large load customer' means customers with an expected total peak demand of 100 megawatts or greater at one or more premises located on one tract or contiguous tracts of land.” (Part I, Section 1-2, new Code Section 46-2-25.4(a))
Rule checks: Project is in Georgia; 450 MW on record (announced), threshold 100 MW (Part I, Section 1-2, new Code Section 46-2-25.4(a)). Still to check: who it covers: not checked
Bills and laws in Georgia
- SB 410 · Passed one chamber · Mar 6, 2026Ends new data center tax breaks, sets large load contract terms
- SB 34 · Died or failed · Feb 26, 2026Bars shifting data center power costs onto other utility customers
- HB 1387 · Died or failed · Feb 20, 2026Funds homestead exemption from property taxes collected on data centers
- SB 530 · Died or failed · Feb 19, 2026Deposits data center tax collections into a property tax relief fund
- HB 1323 · Died or failed · Feb 18, 2026Requires new data centers to operate as hybrid power facilities
- HB 1063 · Passed one chamber · Feb 17, 2026Requires utility contracts shielding other customers from data center costs
Who's involved
- DeveloperIndustrial VI Enterprises
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is 75 South Data Center Campus?
- 75 South Data Center Campus is a data center project in Spalding County, Georgia.
- Who is developing 75 South Data Center Campus?
- Industrial VI Enterprises is named as the developer of 75 South Data Center Campus.
- How big is 75 South Data Center Campus?
- 75 South Data Center Campus was announced at 450 MW of capacity.
- What stage is 75 South Data Center Campus?
- 75 South Data Center Campus is proposed. It was first public in 2026.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1DRI #4607 Initial Information Form: 75 South Data Center Campus
Georgia Department of Community AffairsTier 1 · Captured 2026-11-08 · Open the source - 2DRI #4607 Information Form Part 2: 75 South Data Center Campus
Georgia Department of Community AffairsTier 1 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page