Data centers in DuPage County, Illinois

Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.

Data Center Fact Check tracks 6 data center projects in DuPage County, Illinois as of November 2026: 5 operating and 1 under construction, totaling about 143 MW announced where a figure is published.

DuPage County has 6 tracked data centers. Their announced capacity totals about 143 MW where a figure is published. Of those, 5 operating and 1 under construction. Every project we track here is listed below, with the public records behind it. Every figure comes from the public record linked on this page.

NTT Chicago Itasca video · 2 min 11 sec

Full project file: NTT Chicago Campus (Itasca)

6Data center projects we track

Data center projects in DuPage County

Who serves this place

  • Not collected yet.

Places in and around DuPage County

DuPage County is part of Illinois.

Cities and towns

  • Aurora3 data center projects tracked
  • Itasca1 data center project tracked
  • Lisle1 data center project tracked
  • Lombard1 data center project tracked
  • Oak Brook1 data center project tracked
  • Wood Dale1 data center project tracked

Nearby places

Tax breaks and payments

  • 2020 · NTT Chicago Campus (Itasca)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for NTT Chicago Campus (Itasca)
  • 2022 · CyrusOne Aurora Campus (CHI1-CHI3)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for CyrusOne Aurora Campus (CHI1-CHI3)
  • 2024 · CyrusOne Aurora Campus (CHI1-CHI3)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for CyrusOne Aurora Campus (CHI1-CHI3)
  • 2024 · CyrusOne Wood Dale Campus

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for CyrusOne Wood Dale Campus
  • 2025 · Centersquare ORD4 (Lisle)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for Centersquare ORD4 (Lisle)

Court cases and commission dockets in Illinois (3)

Bills and laws in Illinois

All 28 in Bill Watch

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Questions people ask

How many data centers are in DuPage County?
Data Center Fact Check tracks 6 data center projects in DuPage County as of November 2026. Of those, 5 operating and 1 under construction.
What is the biggest data center in DuPage County?
By announced capacity, the biggest data center in DuPage County is NTT Chicago Campus (Itasca), announced at 104 MW. It is operating.
How much power do data centers in DuPage County use?
The 6 projects tracked in DuPage County have announced about 143 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.

Sources

  1. 1
    Data Center Investment Program 2025 Annual Report
    Illinois Department of Commerce and Economic Opportunity
    Tier 1 · Open the source

Cite this page

Copy this citation when you reuse a figure or a finding from this page.