Project File

Aligned Chicago Campus (ORD-01, ORD-02)

Northlake,Cook County,IllinoisOperatingFirst public 2021Last checked Nov 8, 2026

Aligned Data CentersDeveloper and operator

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

5 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: First public date
  • Still to confirm: Electric utility
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Aligned Chicago Campus (ORD-01, ORD-02) is an operating data center project in Northlake, Cook County, Illinois. Aligned Data Centers is named as operator. It was first public in 2021. It was announced at 48 MW.

Aligned Chicago Campus (ORD-01, ORD-02) is an operating data center project in Northlake, Cook County, Illinois. Aligned Data Centers is named as operator. It was announced at 48 MW. 5 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Northlake, Cook County, Illinois. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

Aligned Chicago video · 2 min 16 sec

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

48 MWAnnounced capacity
1Public records we have found
1Tax agreement on record

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Aerial view of Aligned Chicago Campus (ORD-01, ORD-02) (Aligned Data Centers) in Northlake, Cook County, Illinois, captured 2019
Aerial image, USDA National Agriculture Imagery Program, via the USGS National Map, Public domain (USDA NAIP), captured 2019Aerial images can be older than the campus. This one shows what was on the ground when it was taken.Source: USDA National Agriculture Imagery Program, via the USGS National MapLicense: Public domain (USDA NAIP)
Site-level positionPin placed from the position we have on file, inside Cook County, Illinois.See every project on the map

The land, to scale

One football field
18.5 acres, about 14 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · New projectFirst public record of Aligned Chicago Campus (ORD-01, ORD-02)Operating
  2. · Tax dealTax agreement approved: Sales and use tax exemptions and credits (20 ilcs 605/605-1025) for Aligned Data CentersState sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benef...

Bills and laws in Illinois

All 28 in Bill Watch

Who's involved

Power

Capacity, as announced or filed

  • 170 MW · Apr 2021 · grid connection
  • 48 MW · ORD-01Apr 2022 · what the figure measures is not stated
  • 108 MW · Apr 2022 · grid connection

Public records

1 records found so far. 8 kinds of record are still being collected.

See every record

Questions people ask

Where is Aligned Chicago Campus (ORD-01, ORD-02)?
Aligned Chicago Campus (ORD-01, ORD-02) is a data center project in Northlake, Cook County, Illinois.
Who operates Aligned Chicago Campus (ORD-01, ORD-02)?
Aligned Data Centers is named as the operator of Aligned Chicago Campus (ORD-01, ORD-02).
How big is Aligned Chicago Campus (ORD-01, ORD-02)?
Aligned Chicago Campus (ORD-01, ORD-02) was announced at 48 MW of capacity. The site covers 18.5 acres.
What stage is Aligned Chicago Campus (ORD-01, ORD-02)?
Aligned Chicago Campus (ORD-01, ORD-02) is operating. It was first public in 2021.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Data Center Investment Program 2025 Annual Report
    Illinois Department of Commerce and Economic Opportunity
    Tier 1 · Captured 2026-11-09 · Open the source
  2. 2
    Aligned Breaks Ground on Chicago Hyperscale Data Center Campus
    Aligned Data Centers
    Tier 4 · Captured 2026-11-08 · Open the source
  3. 3
    Aligned Launches Chicago Hyperscale Data Center Campus and Breaks Ground on Second Adjacent Facility
    Aligned Data Centers
    Tier 4 · Captured 2026-11-08 · Open the source
  4. 4
    U.S. Census Geocoder (batch geographies endpoint)
    U.S. Census Bureau
    Tier 1 · Captured 2026-11-11 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page