Largest projects by announced capacity

The biggest planned data centers in the record, ranked by how much power each one says it will draw. Every project is ranked by one figure: the largest single announced capacity stated for it, printed as its source states it. Big numbers gathers the record's other counts and records.

When a data center is announced, the announcement usually states how much power the site will draw, in megawatts. This page ranks the projects we track by the largest single figure stated for each one: the top 100 of the 529 projects that publish a figure, out of the 1320 we track. Each figure is printed exactly as its source states it, with what it measures, the date it was stated, and its source. The figures are never added together: a project announces phases and campus totals at different times, so adding its figures, or every project's, would count the same capacity more than once.

How to read this ranking

One figure per project. A project can hold several capacity figures in the record: one per phase, a restatement of the same phase, or a total for the whole campus. The ranking uses the largest single figure stated, so where a source states a campus total, that is the figure ranked. Phase figures are never added together, and every figure a project holds is listed on its project page.

Figures measure different things. Some state the IT load the building will carry, some state the grid connection the utility will build, and some do not say. Each row prints what its figure measures, as the record states it, so a grid connection figure and an IT load figure are not presented as the same quantity.

Backup generator figures are not ranked. A permit can state hundreds of megawatts of standby generators behind a site; that is generation held in reserve, not the load the data center draws. 119 projects in the record state only a generator figure and no announced capacity, so they do not appear here.

Announced is not built. These are plan figures, stated by the operator or developer announcing the project or in a filing, and the stage column shows where each project stands today. Projects are ranked the same way whatever their stage, and a cancelled project's figure stays in the ranking with its stage printed, because the announcement is part of the record.

The ranking lists the top 100 of the 529 projects that publish a figure, out of the 1320 projects we track. The rest publish no capacity figure in any record we have found.

Every figure is draft research: traced to the publisher's own release, filing, or testimony by an AI research agent and not yet through verification. Each receipt says so, and names the exact place in the document the figure comes from.

The other side of the same record

Capacity is one side of what these projects mean for the places they land in. The same public record holds the other side, and each project above has its own page carrying it: the tax agreements it signed, the jobs it committed to, and what officials and residents said about it. Of the 100 projects listed here, 10 hold at least one tax agreement on record and 7 carry an impact record covering property tax, tax breaks, electricity, water, jobs, community, neighbors, and voice. For the rest, we checked their tax agreements and impact records and hold none staged yet; that is stated here rather than left blank.

This page sits under What it means for locals. Its sibling pages keep the same kind of record: grid load growth by state for the load utilities say is coming, measured water use for the water figures operators publish, and residential electricity prices for what households actually paid. The generator figures this ranking leaves out are listed on on-site generation, permit by permit. Lists from the record ranks the largest stated tax breaks and counts the tracked projects by state and operator. The megawatts to homes calculator turns a figure on this page into household terms.

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

    Loudoun County's 128 data centers paid $684.8 million in equipment tax in fiscal 2024, at the full county rate. The record, from the county's books.

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

    Per SpaceX's Form 424B4, xAI Colossus 2 in Memphis runs two clusters online: about 110,000 GB200 processors at about 210 MW, and 110,000 GB300 processors at 220 MW, 430 MW in total.

Questions people ask

What is the largest data center project by announced capacity?
The largest single announced capacity figure in the record is 11,000 MW for Fermi Project Matador (Advanced Energy and Intelligence Campus) in Carson County, Texas, stated June 26, 2025. It is one figure stated for the project, covering full build (announced total), printed with its source on its row above. Announced capacity is a plan figure, not a measurement of a running site.
How is a project's figure chosen when the record states several?
Each project is ranked by the largest single figure stated for it. Where a source states a campus total, that figure is the project's figure, because it covers the phases under it. Phase figures are never added together to make a larger one, and restatements of the same phase do not stack. Every figure a project holds, phase by phase, is listed on its project page. Figures that measure only the backup generator fleet are not counted as announced capacity: they state how much generation stands behind the site, not the load the data center draws. 119 projects hold only a generator figure and no announced capacity, so they are not ranked here.
Why is there no combined total?
Because the figures overlap in time. A campus total announced this year covers phase figures announced in earlier years, and a restated figure replaces an older one rather than adding to it. Adding the figures on this page would count the same planned capacity several times over, so the page ranks each project's single largest stated figure and adds none of them together.
Does every project publish a capacity figure?
No. 529 of the 1320 projects we track publish an announced capacity figure in a record we have found. The other 791 publish none: their permits, agreements, and announcements state no figure, or state only a generator fleet figure. A project with no figure on this page is a project whose capacity the public record does not state, not a small project.

Sources

  1. 1
    NorthWestern Energy Reports 2025 Financial Results (Form 8-K Exhibit 99.1)
    NorthWestern Energy Group, Inc.
    Tier 1 · Open the source
  2. 2
    Little Rock, Arkansas Campus (AVAIO Digital Leo project page)
    AVAIO Digital
    Tier 4 · Open the source
  3. 3
    Board Briefing Session Agenda, August 18, 2026: Data Center Zoning (draft Chapter 14.840)
    Spokane County Board of County Commissioners
    Tier 1 · Open the source
  4. 4
    TeraWulf Reports Second Quarter 2026 Results
    TeraWulf Inc. (GlobeNewswire)
    Tier 4 · Open the source
  5. 5
    Lyon County Planning Commission agenda, July 14, 2026 (Monarch Data Center agenda summary, item PLZ-2026-041)
    Lyon County
    Tier 1 · Open the source
  6. 6
    COPT Defense Properties data center shell land acquisition near Des Moines (Business Wire release)
    COPT Defense Properties
    Tier 4 · Open the source
  7. 7
    Hut 8 Beacon Point (Nueces County, Texas)
    Hut 8 Corp.
    Tier 4 · Open the source
  8. 8
    Crusoe and Lancium Announce 1.0 Gigawatt AI Data Center Campus in Childress, Texas
    Lancium (GlobeNewswire)
    Tier 4 · Open the source
  9. 9
    Meta's New AI-Optimized Data Center in El Paso
    Meta
    Tier 4 · Open the source
  10. 10
    Turner selected as one of the contractors for $10 billion Meta data center campus in Indiana
    Turner Construction Company (via HOCHTIEF)
    Tier 4 · Open the source
  11. 11
    ONE Nuclear Launches 5 GW Louisiana Portfolio of Energy Projects Comprising Nuclear, Natural Gas and Battery Storage
    ONE Nuclear Energy (Business Wire)
    Tier 4 · Open the source
  12. 12
    NNSA Selects Amentum for AI Data Center and Energy Project at Savannah River Site
    National Nuclear Security Administration, U.S. Department of Energy
    Tier 1 · Open the source
  13. 13
    New Era Energy & Digital Partners with Stream Data Centers for Flagship TCDC Campus
    New Era Energy & Digital, Inc.
    Tier 2 · Open the source
  14. 14
    Tract enters the Des Moines market with acquisition of 453 acres after successful collaboration with City of Altoona, IA
    Tract
    Tier 4 · Open the source
  15. 15
    Talen Energy Announces Receipt of Escrowed Funds for Cumulus Data Center Campus Transaction (GlobeNewswire release)
    Talen Energy Corporation
    Tier 4 · Open the source
  16. 16
    Riot Platforms Reports Third Quarter 2026 Financial Results and Strategic Highlights
    Riot Platforms, Inc. (GlobeNewswire release, wire copy)
    Tier 4 · Open the source
  17. 17
    Vantage Breaks Ground on $15B Stargate Campus in Wisconsin
    Data Center Knowledge
    Tier 3 · Open the source
  18. 18
    Preliminary Plan of Subdivision 4-23024, Brightseat Tech Park, Technical Staff Report
    Maryland-National Capital Park and Planning Commission, Prince George's County Planning Department
    Tier 1 · Open the source
  19. 19
    Tract Breaks Ground on Peru Shelf Technology Park in Storey County, Nevada
    Tract (via GlobeNewswire)
    Tier 4 · Open the source
  20. 20
    Cologix Expands Central Ohio Footprint With Land Acquisition For New AI-Ready 800MW Data Center Campus
    Cologix
    Tier 4 · Open the source
  21. 21
    Lochbuie approves five-year data center moratorium, making it the longest active pause in Colorado
    Rocky Mountain PBS
    Tier 3 · Open the source
  22. 22
    IREN Secures $9.7bn AI Cloud Contract with Microsoft
    IREN Limited (GlobeNewswire release)
    Tier 4 · Open the source
  23. 23
    Phoenix 3, QTS Data Centers
    QTS Data Centers
    Tier 4 · Open the source
  24. 24
    Auburndale Technology Center project website and FAQ
    Auburndale Technology Center (Hillwood Development Company)
    Tier 4 · Open the source
  25. 25
    Project Mica (project page)
    Port KC
    Tier 1 · Open the source
  26. 26
    Switch TAHOE RENO Now Open: Largest, Most Advanced Data Center Campus in the World
    Switch
    Tier 4 · Open the source
  27. 27
    More details on proposed data center
    Illinois Times
    Tier 3 · Open the source
  28. 28
    Alcoa Corporation Reports Third Quarter 2026 Results
    Alcoa Corporation
    Tier 4 · Open the source
  29. 29
    Rowan Digital Infrastructure (homepage, Bauxite portfolio entry)
    Rowan Digital Infrastructure
    Tier 4 · Open the source
  30. 30
    Berkeley County
    e-WV: The West Virginia Encyclopedia
    Tier 2 · Open the source
  31. 31
    Core Scientific Form 8-K: Texas Data Center Power Status Update
    Core Scientific, Inc. (SEC Form 8-K)
    Tier 4 · Open the source
  32. 32
    Festus Data Center Community Information Website
    CRG
    Tier 4 · Open the source
  33. 33
    IREN's 2GW Sweetwater Hub Included as Base Load in ERCOT Batch Zero
    IREN Limited (GlobeNewswire)
    Tier 4 · Open the source
  34. 34
    DRI #4853 Initial Information Form: Nixon Technology Center
    Georgia Department of Community Affairs
    Tier 1 · Open the source
  35. 35
    Project Ruby Data Center Site, Muscogee County, Georgia (site map)
    Choose Columbus / Development Authority of Columbus
    Tier 2 · Open the source
  36. 36
    UG of Wyandotte County Approves Master Plan for 600MW Data Center
    Ingram's
    Tier 3 · Open the source
  37. 37
    Skybox PowerCampus Austin (Hutto)
    Skybox Data Centers
    Tier 4 · Open the source
  38. 38
    STAMP Data Center: Energy Matters (memorandum to GCEDC)
    Genesee County Economic Development Center
    Tier 1 · Open the source
  39. 39
    Q2 2026 Business Update (investor presentation)
    TeraWulf Inc.
    Tier 4 · Open the source
  40. 40
    C1 Yorkville - Cyrus One CHI-11 West (Final Plat)
    United City of Yorkville
    Tier 1 · Open the source
  41. 41
    Order, Docket No. 59220: Application of Crusoe Energy Systems LLC, FGE Goodnight I, LLC and Ensign Infrastructure LLC for Approval of a Net Metering Arrangement
    Public Utility Commission of Texas
    Tier 1 · Open the source
  42. 42
    Compass Datacenters project generates $10 billion investment in Lauderdale County
    Office of Governor Tate Reeves
    Tier 1 · Open the source
  43. 43
    Data centers in Sioux Falls, and how to have your say
    Rising Together Sioux Falls (summarizing City of Sioux Falls actions and Argus Leader reporting)
    Tier 3 · Open the source
  44. 44
    Town Lane and PowerHouse Data Centers JV acquires future data center land site in Charlotte, NC
    PowerHouse Data Centers and Town Lane
    Tier 4 · Open the source
  45. 45
    STACK Infrastructure data center locations (operator’s own list)
    STACK Infrastructure
    Tier 2 · Open the source
  46. 46
    Draft Resolution (ZTA 8-14 packet): pause on acceptance of land use and permit applications for data centers
    Spokane County Board of County Commissioners
    Tier 1 · Open the source
  47. 47
    Switch buys more land at industrial park outside Las Vegas
    Data Center Dynamics
    Tier 3 · Open the source
  48. 48
    Switch data center locations (operator’s own list)
    Switch
    Tier 2 · Open the source
  49. 49
    DataBank Red Oak Campus (Dallas)
    DataBank
    Tier 4 · Open the source

Back to What it means for locals

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Largest projects by announced capacity." Updated 2026-11-29. Accessed 2026-11-29. https://datacenterfactcheck.org/benefits/largest-projects