Project File
Bedington data center project
Berkeley County,West VirginiaIn permittingFirst public 2026Filing entity: Bedington Owner LLCLast checked Nov 8, 2026
PenzanceDeveloperPotomac EdisonElectric utilityWV Department of CommercePublic partner
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: Stage
- Confirmed: Capacity
- Confirmed: Electric utility
- Confirmed: First public date
- Still to confirm: City or address
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Bedington data center project is a data center project in Berkeley County, West Virginia. Penzance is named as developer. It is in permitting. It was first public in 2026. It was announced at 600 MW.
Bedington data center project is a data center project in Berkeley County, West Virginia. Penzance is named as developer. It was announced at 600 MW. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Berkeley County, West Virginia. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
The land, to scale
Timeline
- · New projectFirst public record of Bedington data center projectIn permitting
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026West Virginia HB 2014: Creates a certified microgrid program for large West Virginia data centers
The act covers high impact data centers, facilities with a critical IT load in the aggregate of 90 megawatts or higher that are placed into service on or after July 1, 2025 and certified by the Secretary of the Department of Commerce; this project has 600 MW on record (not stated), but the project's critical IT load, the date it was placed into service, and whether the Secretary has certified it is not on record.
“"High Impact Data Center" means a facility or group of facilities that: ... (D) Has a critical IT load in the aggregate of 90 megawatts total or higher; and (E) Is placed into service on or after July 1, 2025.” (W. Va. Code Sec. 11-6N-2(6))
Rule checks: Project is in West Virginia; 600 MW on record (not stated), threshold 90 MW (W. Va. Code Sec. 11-6N-2(6)). Still to check: dates: not checked, who it covers: not checked
Bills and laws in West Virginia
- HB 2014 · Signed into law · Apr 30, 2025Creates a certified microgrid program for large West Virginia data centers
Who's involved
- DeveloperPenzance
- Electric utilityPotomac Edison
- Public partnerWV Department of Commerce
Power
Capacity, as announced or filed
- 600 MW · what the figure measures is not stated
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is Bedington data center project?
- Bedington data center project is a data center project in Berkeley County, West Virginia.
- Who is developing Bedington data center project?
- Penzance is named as the developer of Bedington data center project.
- How big is Bedington data center project?
- Bedington data center project was announced at 600 MW of capacity. The site covers 548 acres.
- What stage is Bedington data center project?
- Bedington data center project is in permitting. It was first public in 2026.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Data Center Promises, Town Plaza Plans, and Candidate Debate
The Observer (Jefferson County, WV)Tier 3 · Captured 2026-11-08 · Open the source - 2
- 3
- 4EIA Form 861, Service Territory file, 2025 (final)
U.S. Energy Information AdministrationTier 1 · Captured 2026-11-11 · Open the source · Archived copy
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page