Data centers in West Virginia
Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.
Data Center Fact Check tracks 8 data center projects in West Virginia as of November 2026: 4 in permitting, 2 announced and 1 proposed, totaling about 6,160 MW announced where a figure is published.
West Virginia has 8 tracked data centers. Their announced capacity totals about 6,160 MW where a figure is published. Of those, 4 in permitting, 2 announced and 1 proposed. Every figure comes from the public record linked on this page.
Data center projects in West Virginia
- Bedington data center project
In permitting600 MW announced
- Google Buffalo data center campus
In permittingBuffalo
- Monarch Compute Campus
Under constructionPoint Pleasant2,000 MW announced
- Project Country Roads
Announced1,400 MW announced
- Project Tamarack
Announced2,160 MW announced
- QTS Kearneysville
In permitting
- Ridgeline Facility
In permitting
- Summit Point data center project
Proposed
Who serves this place
- Not collected yet.
Counties and cities in West Virginia
Counties
- Berkeley County2 data center projects tracked
- Boone County1 data center project tracked
- Jefferson County1 data center project tracked
- Mason County2 data center projects tracked
- Putnam County1 data center project tracked
- Tucker County1 data center project tracked
Cities and towns
- Buffalo1 data center project tracked
- Point Pleasant1 data center project tracked
Tax breaks and payments
2009
Property tax valuation at salvage value (W. Va. Code Sections 11-6J-1 to 11-6J-7, High-Technology Business Property Valuation Act)
Servers and tangible personal property directly used in a high-technology business are valued at salvage value, defined as five percent of original cost, for ad valorem property tax, instead of appraised value (Sections 11-6J-2 and 11-6J-3). The same definition feeds the consumers sales tax exemption in Section 11-15-9h for property installed for direct use in a high-technology business.
2025
Program certification with state preemption of local regulation (W. Va. Code Sections 5B-2-21a and 5B-2-21b, created by HB 2014, 2025)
A data center certified by the Secretary of Commerce as a certified high impact data center is assisted by the Department of Commerce through a designated Data Economy Liaison, and the state occupies the field of its creation and regulation: counties and municipalities may not apply zoning, building permitting or inspection, licensing, or land use ordinances to a certified project (Section 5B-2-21b(c) and (d)). This is not a tax exemption: a certified project still pays ad valorem tax at the same millage as any other business, business and occupation tax, municipal sales and use taxes, and local service fees (Section 5B-2-21b(e)).
Recent cases and dockets in West Virginia
- Utility commission · Pending before the commissionApplication for a certificate of public convenience and necessity to construct and operate an approximate 1200 MW combined cycle gas plant at the Fort Martin power station and 70 MW of solar generation
- Utility commission · In effectApplication for Approval of Revisions to Schedules LCP and IP (Appalachian Power Company and Wheeling Power Company)
Bills and laws in West Virginia
- HB 2014 · Signed into law · Apr 30, 2025Creates a certified microgrid program for large West Virginia data centers
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Officials we track for West Virginia
The lawmakers and local officials whose recorded jurisdiction is West Virginia, with the bills and votes we have on record for each.
- Bill AndersonState Delegate · 010
- Bob FehrenbacherState Delegate · 011
- Clay RileyState Delegate · 072
- James Robert Akers IIState Delegate · 055
- Mark ZatezaloState Delegate · 002
- Patrick MorriseyGovernor
- Roger HanshawState Delegate · 062
- Sean HornbuckleState Delegate · 025
Questions people ask
- How many data centers are in West Virginia?
- Data Center Fact Check tracks 8 data center projects in West Virginia as of November 2026. Of those, 4 in permitting, 2 announced and 1 proposed.
- What is the biggest data center in West Virginia?
- By announced capacity, the biggest data center in West Virginia is Project Tamarack, announced at 2,160 MW. It is announced.
- How much power do data centers in West Virginia use?
- The 8 projects tracked in West Virginia have announced about 6,160 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
- 1West Virginia Code Chapter 11, Article 6J: High-Technology Business Property Valuation Act
West Virginia LegislatureTier 1 · Open the source - 2West Virginia Code Section 5B-2-21b: Authority to assist certified high impact data center projects
West Virginia LegislatureTier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.