What it is

The Large Load Customers section of Schedules L.C.P. and I.P. applies to new load, and to expansions of existing load, contracted after January 1, 2025 where the new load or expansion itself is at least 100 MW at an individual site or 150 MW aggregated. Initial contract term not less than 12 years, commencing after a load ramp of no more than five years; monthly billing demand not less than the greater of 80 percent of contract capacity or 80 percent of the highest billing demand in the past 11 months, plus base billing energy of contract capacity times 60 percent times billing hours; collateral equal to 24 times the previous maximum monthly nonfuel bill, recomputed annually. After the first five years the customer may reduce capacity up to 20 percent in total with no exit fee on 42 months notice; larger reductions or termination carry an exit fee equal to the nominal remaining minimum charge over the remaining term (not less than one, not more than five years), less estimated PJM transmission savings, with a duty to mitigate.

The facts

Regulator
Public Service Commission of West Virginia
Docket number
24-0611-E-T-PW
Type
Large load tariff
Utility
Appalachian Power Co
State
West Virginia
Filed
Sep 25, 2024
Status date
Mar 25, 2025
Large-load rules
Yes, for loads of 100 MW or more

Projects served by Appalachian Power Co

Related cases and proceedings

In the record

  1. Utility case, Sep 25, 2024. Utility case filed: Application for Approval of Revisions to Schedules LCP and IP (Appalachian Power Company and Wheeling Power Company) Public Service Commission of West Virginia, 24-0611-E-T-PW

Sources

  1. 1
    Tariff filing with corrected Schedules L.C.P. and I.P. sheets, Case No. 24-0611-E-T-PW (filed April 7, 2025)
    Public Service Commission of West Virginia
    Tier 1 · Tariff filing of April 7, 2025: Schedule L.C.P. Sheet Nos. 14-3 (Large Load Customers, applicability) and 14-4 (contract term, billing demand, minimum charge, collateral, capacity reductions); Schedule I.P. Sheet Nos. 15-1 to 15-4 (same section); PSC 2024 Management Summary Report, appendix entry for Case No. 24-0611-E-T-PW (filing date) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Application for Approval of Revisions to Schedules LCP and IP (Appalachian Power Company and Wheeling Power Company)." Last activity 2025-03-25. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-appalachian-power-wv-lcp-ip-2024