Utility commission
Petition of Appalachian Power Company For approval of Revisions to the Terms and Conditions of Rate Schedule L.P.S.
Where it stands: Pending before the commission as of Nov 10, 2025
Draft research, not yet verified. Open a source to check any detail.
What it is
Under the November 10, 2025 Partial Stipulation (revising the petition as filed): the large load terms apply to new load or expansions at or above 100 MW at an individual site or 150 MW aggregated, contracted after July 1, 2025; initial contract term not less than 14 years with a load ramp of no more than 4 years; monthly billing demand not less than the greater of 80 percent of contract capacity or 80 percent of the highest billing demand in the past 11 months, plus base billing energy of contract capacity times 60 percent times billing hours; collateral as proposed in the petition, negotiable at company discretion. Capacity may be reduced up to 20 percent after year 5 with no exit fee on 42 months notice; larger reductions or termination carry an exit fee equal to the nominal remaining minimum charge over a 1 to 5 year exit fee period, with a company duty to mitigate. No rate change.
The facts
- Regulator
- Virginia State Corporation Commission
- Docket number
- PUR-2025-00057
- Type
- Large load tariff
- Utility
- Appalachian Power Co
- State
- Virginia
- Filed
- Mar 24, 2025
- Status date
- Nov 10, 2025
- Large-load rules
- Yes, for loads of 100 MW or more
Projects served by Appalachian Power Co
Related cases and proceedings
- Utility commission · DecidedApplication of Virginia Electric and Power Company for approval of a rate adjustment clause (Rider T1) pursuant to Section 56-585.1 A 4 of the Code of Virginia
- Utility commission · Pending before the commissionApplication of Virginia Electric and Power Company for approval of its large-load connection queue process standards
- Utility commission · In effectLarge Power Dedicated Facilities Contract Service Schedule LPD-2
- Utility commission · DecidedApplication of Virginia Electric and Power Company for a 2025 biennial review of the rates, terms and conditions for the provision of generation, distribution and transmission services
- Utility commission · Pending before the commissionPetition of Mecklenburg Electric Cooperative for approval to implement a new Large Power Service Rate Schedule (Schedule LPS-U)
- Utility commission · In effectPetition of Rappahannock Electric Cooperative For approval to implement a new Large Power Dedicated Facilities Rate Schedule
- Utility commission · In effectApplication for Approval of Revisions to Schedules LCP and IP (Appalachian Power Company and Wheeling Power Company)
- Utility commission · DecidedApplication of Virginia Electric and Power Company for a 2023 biennial review of the rates, terms and conditions for the provision of generation, distribution and transmission services
In the record
- Utility case, Mar 24, 2025. Utility case filed: Petition of Appalachian Power Company For approval of Revisions to the Terms and Conditions of Rate Schedule L.P.S. Virginia State Corporation Commission, PUR-2025-00057
Sources
- 1Petition of Appalachian Power Company for approval of revisions to the Terms and Conditions of Rate Schedule L.P.S., Case PUR-2025-00057
Virginia State Corporation CommissionTier 1 · Petition paras. 1 and 4 (thresholds, as-filed 12 year term, 80 percent minimum, collateral); Partial Stipulation Exhibit A, pp. 1-5 (para. 1a applicability; paras. 1b-1f term, ramp, billing demand, base billing energy, collateral, reductions and exit fee) · Open the source - 2Partial Stipulation, Case PUR-2025-00057 (filed November 10, 2025)
Virginia State Corporation CommissionTier 1 · Petition paras. 1 and 4 (thresholds, as-filed 12 year term, 80 percent minimum, collateral); Partial Stipulation Exhibit A, pp. 1-5 (para. 1a applicability; paras. 1b-1f term, ramp, billing demand, base billing energy, collateral, reductions and exit fee) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Petition of Appalachian Power Company For approval of Revisions to the Terms and Conditions of Rate Schedule L.P.S.." Last activity 2025-11-10. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-appalachian-power-lps-2025