What it is

Under the November 10, 2025 Partial Stipulation (revising the petition as filed): the large load terms apply to new load or expansions at or above 100 MW at an individual site or 150 MW aggregated, contracted after July 1, 2025; initial contract term not less than 14 years with a load ramp of no more than 4 years; monthly billing demand not less than the greater of 80 percent of contract capacity or 80 percent of the highest billing demand in the past 11 months, plus base billing energy of contract capacity times 60 percent times billing hours; collateral as proposed in the petition, negotiable at company discretion. Capacity may be reduced up to 20 percent after year 5 with no exit fee on 42 months notice; larger reductions or termination carry an exit fee equal to the nominal remaining minimum charge over a 1 to 5 year exit fee period, with a company duty to mitigate. No rate change.

The facts

Regulator
Virginia State Corporation Commission
Docket number
PUR-2025-00057
Type
Large load tariff
Utility
Appalachian Power Co
State
Virginia
Filed
Mar 24, 2025
Status date
Nov 10, 2025
Large-load rules
Yes, for loads of 100 MW or more

Projects served by Appalachian Power Co

Related cases and proceedings

In the record

  1. Utility case, Mar 24, 2025. Utility case filed: Petition of Appalachian Power Company For approval of Revisions to the Terms and Conditions of Rate Schedule L.P.S. Virginia State Corporation Commission, PUR-2025-00057

Sources

  1. 1
    Petition of Appalachian Power Company for approval of revisions to the Terms and Conditions of Rate Schedule L.P.S., Case PUR-2025-00057
    Virginia State Corporation Commission
    Tier 1 · Petition paras. 1 and 4 (thresholds, as-filed 12 year term, 80 percent minimum, collateral); Partial Stipulation Exhibit A, pp. 1-5 (para. 1a applicability; paras. 1b-1f term, ramp, billing demand, base billing energy, collateral, reductions and exit fee) · Open the source
  2. 2
    Partial Stipulation, Case PUR-2025-00057 (filed November 10, 2025)
    Virginia State Corporation Commission
    Tier 1 · Petition paras. 1 and 4 (thresholds, as-filed 12 year term, 80 percent minimum, collateral); Partial Stipulation Exhibit A, pp. 1-5 (para. 1a applicability; paras. 1b-1f term, ramp, billing demand, base billing energy, collateral, reductions and exit fee) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Petition of Appalachian Power Company For approval of Revisions to the Terms and Conditions of Rate Schedule L.P.S.." Last activity 2025-11-10. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-appalachian-power-lps-2025