Large Power Dedicated Facilities Contract Service Schedule LPD-2

Where it stands: In effect as of Jan 1, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

The consumer must sign an Electric Service Agreement, have a metered load of at least 40,000 kW in the current or preceding eleven months (new consumers may ramp to that level over a period set in the ESA), and accept a minimum contract billing demand of 40,000 kW. Service is at primary voltage of 20 kV or more through dedicated facilities from a wholesale delivery point of 110 kV or higher; no backup or standby service. The ESA term is negotiable but structured to recover the full cost of distribution and sub-transmission plant including operations and maintenance, with collateral in the amount and form the Cooperative accepts; the consumer pays CIAC for all facilities costs plus monthly excess facilities charges, remains responsible for capacity and transmission charges after discontinuing service, and is billed the higher of actual demand or the contract minimum times ESA ramp percentages, with billing energy at a 0.85 factor floor.

The facts

Regulator
Virginia State Corporation Commission
Type
Large load tariff
Utility
Shenandoah Valley Electric Cooperative
State
Virginia
Filed
Oct 16, 2025
Status date
Jan 1, 2026
Large-load rules
Yes, for loads of 40 MW or more

Related cases and proceedings

In the record

  1. Utility case, Oct 16, 2025. Utility case filed: Large Power Dedicated Facilities Contract Service Schedule LPD-2 Virginia State Corporation Commission

Sources

  1. 1
    Large Power Dedicated Facilities Contract Service Schedule LPD-2 (SCC accepted for filing January 13, 2026; effective January 1, 2026)
    Shenandoah Valley Electric Cooperative
    Tier 1 · Schedule LPD-2, p. 1 (applicability: 40,000 kW tests, 20 kV service, 110 kV delivery point, collateral, ESA term) and Facilities Charge section, pp. 3-4 (CIAC and excess facilities charges); SVEC rates page, 2025 Commercial and Large Power Rate Reviews (October 16, 2025 petition; interim approval from January 1, 2026) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Large Power Dedicated Facilities Contract Service Schedule LPD-2." Last activity 2026-01-01. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-shenandoah-valley-lpd-2-2025