What it is
Base rate case seeking about $19 million ($18,976,479, 22.43 percent of total operating revenue including fuel) on a requested 10.95 percent return on equity; residential basic charge from $12.00 to $15.00 per month. It proposes a new Extremely High Load Factor standard rate schedule (proposed Rate EHLF) for customers with large demands and very high load factors, plus revisions to Power Service, time-of-day, Outdoor Sports Lighting, Special Charges and the Excess Facilities and Intermittent Loads riders. Proposed rates are suspended under Va. Code 56-238 until the final order; the public witness and evidentiary hearing is November 12, 2026.
The facts
- Regulator
- Virginia State Corporation Commission
- Docket number
- PUR-2026-00051
- Type
- Rate case
- Utility
- Kentucky Utilities Co
- State
- Virginia
- Filed
- Apr 30, 2026
- Status date
- Jun 10, 2026
- Large-load rules
- Yes
Related cases and proceedings
- Utility commission · Pending before the commissionPetition of Northern Virginia Electric Cooperative for approval of revisions to the Terms and Conditions of Rate Schedules LP-1, DPS, HV-1 and HV-2
- Utility commission · Pending before the commissionSupplemental proceeding for Dominion Energy Virginia proposed amendments to its line extension policy (direct connect transmission facilities for large load customers)
- Utility commission · DecidedApplication of Virginia Electric and Power Company for approval of a rate adjustment clause (Rider T1) pursuant to Section 56-585.1 A 4 of the Code of Virginia
- Utility commission · Pending before the commissionApplication of Virginia Electric and Power Company for approval of its large-load connection queue process standards
- Utility commission · In effectElectronic Application of Kentucky Utilities Company for an Adjustment of its Electric Rates and Approval of Certain Regulatory and Accounting Treatments (creating Standard Rate EHLF)
- Utility commission · In effectLarge Power Dedicated Facilities Contract Service Schedule LPD-2
- Utility commission · DecidedApplication of Virginia Electric and Power Company for a 2025 biennial review of the rates, terms and conditions for the provision of generation, distribution and transmission services
- Utility commission · Pending before the commissionPetition of Appalachian Power Company For approval of Revisions to the Terms and Conditions of Rate Schedule L.P.S.
In the record
- Utility case, Apr 30, 2026. Utility case filed: Application of Kentucky Utilities Company d/b/a Old Dominion Power Company for an adjustment of electric base rates Virginia State Corporation Commission, PUR-2026-00051
Sources
- 1Order for Notice and Hearing, Case No. PUR-2026-00051 (Kentucky Utilities Company d/b/a Old Dominion Power Company)
Virginia State Corporation CommissionTier 1 · Order for Notice and Hearing, 2026-06-10, pages 1-3 (filed April 30, 2026 and the $19 million request at page 1; the EHLF proposal at page 2, footnote 10, citing Hornung Direct at 2-7) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Application of Kentucky Utilities Company d/b/a Old Dominion Power Company for an adjustment of electric base rates." Last activity 2026-06-10. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-old-dominion-ehlf-2026