Utility commission
Electronic Application of Kentucky Utilities Company for an Adjustment of its Electric Rates and Approval of Certain Regulatory and Accounting Treatments (creating Standard Rate EHLF)
Where it stands: In effect as of Feb 16, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
Standard Rate EHLF (Extra High Load Factor) is available to a non residential customer whose total contract capacity at a single premises is greater than 50 MVA with load factor above 85 percent, under an Electricity Supply Agreement of at least 15 years. The customer must own or lease its substation and take service from a dedicated transmission line and a dedicated substation bay; minimum bill is the sum of the facilities, basic service, and maximum load charges. Billing demand is the greater of the current month’s maximum load or 80 percent of contract capacity; the customer pays 60 months notice before terminating or reducing capacity; the Capacity Reduction Fee and Exit Fee equal the unrecovered remaining minimum non fuel revenue, less facilities costs the customer already paid; collateral is 24 months of minimum bill, or 12 months if the customer has an S&P or Moody’s rating of A or A2 or better. KU tariff book charges: basic service charge $2,179.91 per delivery point per month; maximum load charge $17.28 per kVA above 50,000 kVA.
The facts
- Regulator
- Kentucky Public Service Commission
- Docket number
- 2025-00113
- Type
- Rate case
- Utility
- Kentucky Utilities Co
- State
- Kentucky
- Filed
- May 30, 2025
- Status date
- Feb 16, 2026
- Large-load rules
- Yes, for loads of 50 MW or more
Related cases and proceedings
- Utility commission · DecidedElectronic Tariff Filing of Big Rivers Electric Corporation of a Retail Electric Service Agreement with Justified DataPower LLC, a subsidiary of TeraWulf Inc.
- Utility commission · Pending before the commissionApplication of Kentucky Utilities Company d/b/a Old Dominion Power Company for an adjustment of electric base rates
- Utility commission · In effectElectronic Application of Louisville Gas and Electric Company for an Adjustment of its Electric Rates (creating Standard Rate EHLF)
- Utility commission · In effectElectronic Tariff Filing of East Kentucky Power Cooperative, Inc. to Establish a New Tariff for Data Center Power (Rate DCP)
- Utility commission · DecidedElectronic Application of Kentucky Utilities Company and Louisville Gas and Electric Company for Certificates of Public Convenience and Necessity and Site Compatibility Certificates
- Utility commission · In effectElectronic Tariff Filing of Kentucky Power Company to Revise Its Industrial General Service Tariff
In the record
- Utility case, May 30, 2025. Utility case filed: Electronic Application of Kentucky Utilities Company for an Adjustment of its Electric Rates and Approval of Certain Regulatory and Accounting Treatments (creating Standard Rate EHLF) Kentucky Public Service Commission, 2025-00113
Sources
- 1Kentucky Utilities Company tariff book, P.S.C. Ky. No. 21: Standard Rate EHLF, Extremely High Load Factor Service, Original Sheet Nos. 26, 26.1, 26.2 (issued March 6, 2026, effective February 16, 2026, by authority of Case No. 2025-00113)
Kentucky Utilities CompanyTier 1 · KU Original tariff book, Rate EHLF sheets (50 MVA and 85 percent tests, ESA term, 80 percent floor, 60 month notice, reduction and exit fees, collateral); Kentucky PSC 2025 Annual Report (2025-00113 and 2025-00114 filed May 30, 2025; orders February 16, 2026) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Electronic Application of Kentucky Utilities Company for an Adjustment of its Electric Rates and Approval of Certain Regulatory and Accounting Treatments (creating Standard Rate EHLF)." Last activity 2026-02-16. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-kentucky-utilities-ehlf-2025