Electronic Tariff Filing of Kentucky Power Company to Revise Its Industrial General Service Tariff

Where it stands: In effect as of Mar 18, 2025

Draft research, not yet verified. Open a source to check any detail.

What it is

Applies only to incremental or new load of 150 MW or more added on or after March 18, 2025, served under Tariff I.G.S. Customer contract provisions: primary initial term of 20 years with five years advance written notice to terminate; minimum billing demand not less than 90 percent of the highest billing demand established during the contract term, with a minimum monthly bill per contract MW during the ramp period; collateral equal to the maximum monthly non fuel bill times a factor of 24, recalculated annually; contract closure payment equal to five years of minimum billing charges for the contracted capacity, calculated on an average monthly basis at the time of cessation.

The facts

Regulator
Kentucky Public Service Commission
Docket number
2024-00305
Type
Large load tariff
Utility
Kentucky Power Co
State
Kentucky
Filed
Aug 30, 2024
Status date
Mar 18, 2025
Large-load rules
Yes, for loads of 150 MW or more

Related cases and proceedings

In the record

  1. Utility case, Aug 30, 2024. Utility case filed: Electronic Tariff Filing of Kentucky Power Company to Revise Its Industrial General Service Tariff Kentucky Public Service Commission, 2024-00305

Sources

  1. 1
    Final Order, Case No. 2024-00305, Kentucky Power Company Industrial General Service tariff revisions (March 18, 2025)
    Kentucky Public Service Commission
    Tier 1 · Final Order, Appendix A, pp. 49-50 (150 MW applicability; 20 year term; 90 percent minimum billing demand; collateral factor 24); Appendix A, p. 3 (defined terms) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Electronic Tariff Filing of Kentucky Power Company to Revise Its Industrial General Service Tariff." Last activity 2025-03-18. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-kentucky-power-igs-2024