Utility commission
Electronic Tariff Filing of Kentucky Power Company to Revise Its Industrial General Service Tariff
Where it stands: In effect as of Mar 18, 2025
Draft research, not yet verified. Open a source to check any detail.
What it is
Applies only to incremental or new load of 150 MW or more added on or after March 18, 2025, served under Tariff I.G.S. Customer contract provisions: primary initial term of 20 years with five years advance written notice to terminate; minimum billing demand not less than 90 percent of the highest billing demand established during the contract term, with a minimum monthly bill per contract MW during the ramp period; collateral equal to the maximum monthly non fuel bill times a factor of 24, recalculated annually; contract closure payment equal to five years of minimum billing charges for the contracted capacity, calculated on an average monthly basis at the time of cessation.
The facts
- Regulator
- Kentucky Public Service Commission
- Docket number
- 2024-00305
- Type
- Large load tariff
- Utility
- Kentucky Power Co
- State
- Kentucky
- Filed
- Aug 30, 2024
- Status date
- Mar 18, 2025
- Large-load rules
- Yes, for loads of 150 MW or more
Related cases and proceedings
- Utility commission · In effectElectronic Application of Kentucky Utilities Company for an Adjustment of its Electric Rates and Approval of Certain Regulatory and Accounting Treatments (creating Standard Rate EHLF)
- Utility commission · In effectElectronic Application of Louisville Gas and Electric Company for an Adjustment of its Electric Rates (creating Standard Rate EHLF)
- Utility commission · In effectElectronic Tariff Filing of East Kentucky Power Cooperative, Inc. to Establish a New Tariff for Data Center Power (Rate DCP)
- Utility commission · DecidedElectronic Application of Kentucky Utilities Company and Louisville Gas and Electric Company for Certificates of Public Convenience and Necessity and Site Compatibility Certificates
In the record
- Utility case, Aug 30, 2024. Utility case filed: Electronic Tariff Filing of Kentucky Power Company to Revise Its Industrial General Service Tariff Kentucky Public Service Commission, 2024-00305
Sources
- 1Final Order, Case No. 2024-00305, Kentucky Power Company Industrial General Service tariff revisions (March 18, 2025)
Kentucky Public Service CommissionTier 1 · Final Order, Appendix A, pp. 49-50 (150 MW applicability; 20 year term; 90 percent minimum billing demand; collateral factor 24); Appendix A, p. 3 (defined terms) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Electronic Tariff Filing of Kentucky Power Company to Revise Its Industrial General Service Tariff." Last activity 2025-03-18. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-kentucky-power-igs-2024