Electronic Tariff Filing of East Kentucky Power Cooperative, Inc. to Establish a New Tariff for Data Center Power (Rate DCP)
Where it stands: In effect as of Oct 30, 2025
Draft research, not yet verified. Open a source to check any detail.
What it is
Rate DCP is available at any point of adequate capacity and suitable voltage to data centers with a minimum monthly demand of 15,000 kW or greater and a minimum monthly load factor of 60 percent. Service is provided only under a Commission approved special contract specific to each customer; the customer furnishes a prepayment deposit equal to two months of expected maximum billing (refundable under conditions) and an application fee of $75,000 plus $1,000 per MW above 15 MW, capped at $250,000. Loads above 250 MW require dedicated resources (new generation or a purchased power agreement) and are charged the costs those resources are intended to recover. The tariff sets no fixed contract term or minimum demand percentage; those are fixed in each special contract.
The facts
- Regulator
- Kentucky Public Service Commission
- Docket number
- 2025-00140
- Type
- Large load tariff
- Utility
- East Kentucky Power Cooperative, Inc.
- State
- Kentucky
- Filed
- Apr 30, 2025
- Status date
- Oct 30, 2025
- Large-load rules
- Yes, for loads of 15 MW or more
Projects served by East Kentucky Power Cooperative, Inc.
Related cases and proceedings
- Utility commission · DecidedElectronic Tariff Filing of Big Rivers Electric Corporation of a Retail Electric Service Agreement with Justified DataPower LLC, a subsidiary of TeraWulf Inc.
- Utility commission · In effectElectronic Application of Kentucky Utilities Company for an Adjustment of its Electric Rates and Approval of Certain Regulatory and Accounting Treatments (creating Standard Rate EHLF)
- Utility commission · In effectElectronic Application of Louisville Gas and Electric Company for an Adjustment of its Electric Rates (creating Standard Rate EHLF)
- Utility commission · DecidedElectronic Application of Kentucky Utilities Company and Louisville Gas and Electric Company for Certificates of Public Convenience and Necessity and Site Compatibility Certificates
- Utility commission · In effectElectronic Tariff Filing of Kentucky Power Company to Revise Its Industrial General Service Tariff
In the record
- Utility case, Apr 30, 2025. Utility case filed: Electronic Tariff Filing of East Kentucky Power Cooperative, Inc. to Establish a New Tariff for Data Center Power (Rate DCP) Kentucky Public Service Commission, 2025-00140
Sources
- 1Order, Case No. 2025-00140, East Kentucky Power Cooperative Data Center Power tariff (October 30, 2025)
Kentucky Public Service CommissionTier 1 · Order of October 30, 2025, pp. 6-7 (Rate DCP availability: 15,000 kW, 60 percent load factor, special contracts, deposit, application fee, 250 MW dedicated resources threshold) · Open the source
Report an error or send a tip on this page