Utility commission
Petition of Northern Virginia Electric Cooperative for approval of revisions to the Terms and Conditions of Rate Schedules LP-1, DPS, HV-1 and HV-2
Where it stands: Pending before the commission as of Sep 1, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
Revises the terms and conditions, not the rates, of NOVEC's four large load schedules. The Commission's order calls them tariffs governing service to large load, high load factor customers. The revised schedules took effect on an interim basis on September 1, 2026, subject to further review; hearings are set for April 21, 2027.
The facts
- Regulator
- Virginia State Corporation Commission
- Docket number
- PUR-2026-00114
- Type
- Other
- Utility
- Northern Virginia Electric Cooperative
- State
- Virginia
- Filed
- Jul 17, 2026
- Status date
- Sep 1, 2026
- Large-load rules
- Yes
Projects served by Northern Virginia Electric Cooperative
Related cases and proceedings
- Utility commission · Pending before the commissionSupplemental proceeding for Dominion Energy Virginia proposed amendments to its line extension policy (direct connect transmission facilities for large load customers)
- Utility commission · Pending before the commissionApplication of Kentucky Utilities Company d/b/a Old Dominion Power Company for an adjustment of electric base rates
- Utility commission · DecidedApplication of Virginia Electric and Power Company for approval of a rate adjustment clause (Rider T1) pursuant to Section 56-585.1 A 4 of the Code of Virginia
- Utility commission · Pending before the commissionApplication of Virginia Electric and Power Company for approval of its large-load connection queue process standards
- Utility commission · In effectLarge Power Dedicated Facilities Contract Service Schedule LPD-2
- Utility commission · DecidedApplication of Virginia Electric and Power Company for a 2025 biennial review of the rates, terms and conditions for the provision of generation, distribution and transmission services
- Utility commission · Pending before the commissionPetition of Appalachian Power Company For approval of Revisions to the Terms and Conditions of Rate Schedule L.P.S.
- Utility commission · Pending before the commissionPetition of Mecklenburg Electric Cooperative for approval to implement a new Large Power Service Rate Schedule (Schedule LPS-U)
In the record
- Utility case, Jul 17, 2026. Utility case filed: Petition of Northern Virginia Electric Cooperative for approval of revisions to the Terms and Conditions of Rate Schedules LP-1, DPS, HV-1 and HV-2 Virginia State Corporation Commission, PUR-2026-00114
Sources
- 1Order for Notice and Hearing, Case No. PUR-2026-00114 (NOVEC terms and conditions revisions)
Virginia State Corporation CommissionTier 1 · Order for Notice and Hearing, 2026-08-21 (Doc. Con. Cen. No. 260840118), paragraphs 1-2 and ordering paragraph 2 · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Petition of Northern Virginia Electric Cooperative for approval of revisions to the Terms and Conditions of Rate Schedules LP-1, DPS, HV-1 and HV-2." Last activity 2026-09-01. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-novec-terms-2026