Project File
STACK Infrastructure Loudoun County campus
Leesburg,Loudoun County,VirginiaUnder constructionFirst public 2025Filing entity: STACK InfrastructureLast checked Nov 9, 2026
STACK InfrastructureDeveloper and operator
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
6 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Capacity
- Confirmed: Electric utility
- Confirmed: First public date
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
STACK Infrastructure Loudoun County campus is a under-construction data center project in Leesburg, Loudoun County, Virginia. STACK Infrastructure is named as operator. It was first public in 2025. It was announced at 144 MW.
STACK Infrastructure Loudoun County campus is an under-construction data center project in Leesburg, Loudoun County, Virginia. STACK Infrastructure is named as operator. It was announced at 144 MW. All six of the core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Leesburg, Loudoun County, Virginia. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Newswire for Loudoun County
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
The land, to scale
Timeline
- · DecisionVirginia Department of Environmental Quality: Issued (Article 6 minor New Source Review; combined permit document combining the June 18, 2024 permit and the February 11, 2026 permit) (air permit) for STACK Infrastructure Loudoun County campusRegistration No. 74269
- · New projectFirst public record of STACK Infrastructure Loudoun County campusUnder construction
- · DecisionVirginia Commission on Local Government: Commission report and recommendation (April 30, 2024) supporting approval of the agreement. The agreement defines the STACK Property (Section 2.15) as part of the Annexation Area and provides that the Town shall provide water and sewer service to the Annex...Voluntary Settlement Agreement of Annexation and Related Issues, under Va. Code Section 15.2-3400
- · FilingFiled with Virginia Commission on Local Government for STACK Infrastructure Loudoun County campusVoluntary Settlement Agreement of Annexation and Related Issues, under Va. Code Section 15.2-3400
- · DecisionTown of Leesburg, Virginia: Approved 6-1 (Council Member Wilt in opposition): extension of Town water and sanitary sewer service to the proposed data center at Compass Creek, conditioned on the owner's written consent to annexation or boundary adjustment, execution of a water and wastewater servi...Town Council Agenda Item 13b, March 14, 2023
- · FilingFiled with Virginia Department of Environmental Quality: stormwater permit for STACK Infrastructure Loudoun County campusVAR10T460
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia HB 1393: Shifts grid costs to the largest electricity customers
The bill directs Dominion Energy Virginia to propose allocating capacity procurement and distribution infrastructure costs to its customer class with a contracted or measured demand of 25 megawatts or greater and an average load factor of 75 percent or greater, in rate proceedings commencing after January 1, 2027 and before July 1, 2033; this project is served by Dominion Energy Virginia on record, but its contracted or measured demand and its average annual load factor are not on record.
“Dominion Energy Virginia to propose to the Commission, in any proceeding to determine rates for generation and distribution services commencing after January 1, 2027, and before July 1, 2033, that certain costs related to capacity procurement requirements and distribution infrastructure investments are allocated to the utility's customer class approved to serve customers with a contracted or measured electric demand of 25 megawatts or greater and an anticipated or measured average annual electric load factor of 75 percent or greater” (LIS bill-details page for HB 1393 (2026), Summary)
Rule checks: Project is in Virginia. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia HB 153: Requires site assessments before local approval of large data centers
The act covers new high energy use facilities, facilities an applicant reasonably anticipates at the time of filing a rezoning, special exception, or special use permit application will require 100 megawatts or more of electrical power from a retail electric utility, which require a site assessment before local approval; this project has 144 MW announced on record, but whether this project is a new facility seeking such a local approval and the electrical power anticipated for it at filing is not on record.
“"high energy use facility" or "HEUF" means a facility that an applicant reasonably anticipates at the time of filing a rezoning application, special exception application, or special use permit application will require 100 megawatts or more of electrical power from an electric utility providing retail service to the facility.” (Va. Code Sec. 15.2-2209.4 A)
Rule checks: Project is in Virginia; 144 MW on record (announced), threshold 100 MW (Va. Code Sec. 15.2-2209.4 A). Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia HB 30: Budget act item taxing data center electricity at 1.1 cents per kWh
The budget item taxes every data center operator on electricity consumed at each data center from July 1, 2026 to July 1, 2028 and defines a data center to include equipment for at least one megawatt of electrical power and cooling; this project has 144 MW announced on record and a stage of announced, but whether it is an operating data center meeting the one megawatt element of the definition is not established on record.
“"Data center" means a facility whose primary services are to centralize the storage, management, and processing of digital data and is used to house (i) computer and network systems, including associated components such as servers, network equipment and appliances, telecommunications, and data storage systems; (ii) systems for monitoring and managing infrastructure performance; (iii) equipment used for the transformation, transmission, distribution, or management of at least one megawatt of capacity of electrical power and cooling, including substations, uninterruptible power supply systems, all electrical plant equipment, and associated air handlers; (iv) Internet-related equipment and services; (v) data communications connections; (vi) environmental controls; (vii) fire protection systems; and (viii) security systems and services. “Data center" does not include a facility whose primary function is to facilitate the provision of internet access service, a communication service as defined in § 58.1-647, or any combination thereof.” (Item 3-5.24, paragraph A.2 (HB 30, Chapter 1, Part 3))
Rule checks: Project is in Virginia; 144 MW on record (announced), threshold 1 MW (Item 3-5.24, paragraph A.2 (HB 30, Chapter 1, Part 3)). Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia HB 323: Directs a state study of data center waste heat
The act directs the Department of Energy to lead efforts to accelerate the use of waste heat from data centers in the Commonwealth, convene a work group, and report by September 1, 2026; it sets no project-level condition on an individual data center, and whether this project's waste heat is within the work group's scope is not on record.
“Directs the Department of Energy to lead efforts to accelerate the use of waste heat from data centers in the Commonwealth by making certain findings and recommendations and convening a work group to provide expertise, assistance, and feedback on the Department's efforts.” (LIS bill-details page for HB 323 (2026), Summary As Passed)
Rule checks: Project is in Virginia. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia HB 496: Requires monthly water use reports for data centers
The act requires a water user that provides water to another person offsite to report monthly potable and reclaimed water volumes separately for a data center with an air permit issued by the Department of Environmental Quality, effective January 1, 2027; this project is a data center in Virginia, but whether it holds an air permit issued by the Department of Environmental Quality is not on record.
“Any water user required to register water withdrawal and use data pursuant to this subsection that provides water to another person offsite shall include in its report, submitted on its regular reporting schedule, the total volume of potable water and, reported separately, the total volume of reclaimed water provided during each month for each of the following categories: (i) a data center, as that term is defined in subdivision A 43 of § 58.1-3506, with an air permit issued by the Department” (Enacted text (Chapter 623), § 62.1-44.38 C)
Rule checks: Project is in Virginia. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia HB 507: Sets Tier 4 generator emission limits in data center air permits
The section bars the Department of Environmental Quality from issuing a data center permit on an application submitted on or after July 1, 2026 unless the emission limit for each gen-set is equal to or less than the emissions achieved by a Tier 4 equivalent gen-set; no Department of Environmental Quality permit application for this project is on record, so whether an application was submitted on or after July 1, 2026 is not on record.
“For any application submitted for a data center on or after July 1, 2026, for a permit issued by the Department pursuant to this chapter, including coverage under any general permit, the Department shall not issue such permit unless the emission limit for each gen-set established by such permit is equal to or less than the emissions achieved by a Tier 4 equivalent gen-set.” (Va. Code Sec. 10.1-1322.6(B) (2026, c. 397))
Rule checks: Project is in Virginia. Still to check: who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia SB 553: Requires monthly water use reports for data centers
The act requires a water user that provides water to another person offsite to report monthly potable and reclaimed water volumes separately for a data center with an air permit issued by the Department of Environmental Quality, effective January 1, 2027; this project is a data center in Virginia, but whether it holds an air permit issued by the Department of Environmental Quality is not on record.
“Any water user required to register water withdrawal and use data pursuant to this subsection that provides water to another person offsite shall include in its report, submitted on its regular reporting schedule, the total volume of potable water and, reported separately, the total volume of reclaimed water provided during each month for each of the following categories: (i) a data center, as that term is defined in subdivision A 43 of § 58.1-3506, with an air permit issued by the Department” (Enacted text (conference substitute 26109885D, as passed), § 62.1-44.38 C)
Rule checks: Project is in Virginia. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia SB 94: Requires site assessments before local approval of large data centers
The section's site assessment duty turns on the electrical power a facility is anticipated to require from its retail electric utility, and no such figure is on record for this project; its on-record capacity is 128.138 MW of standby generator capacity and a 144 MW announced figure that does not state what it measures, neither of which measures power drawn from the utility.
“"high energy use facility" or "HEUF" means a facility that an applicant reasonably anticipates at the time of filing a rezoning application, special exception application, or special use permit application will require 100 megawatts or more of electrical power from an electric utility providing retail service to the facility.” (Chapter 568 (2026 Acts of Assembly), new Code of Virginia section 15.2-2209.4, subsection A)
Rule checks: Project is in Virginia; 144 MW on record (announced), threshold 100 MW (Chapter 568 (2026 Acts of Assembly), new Code of Virginia section 15.2-2209.4, subsection A). Still to check: who it covers: not checked
Bills and laws in Virginia
- HB 2027 · Died or failedRequires a state certificate to operate large power users
- HB 2578 · Died or failedAdds clean energy conditions to the data center tax break
- SB 843 · Filed · Oct 9, 2026Bars new data center approvals statewide for three years
- EO 22 · In effect · Sep 18, 2026Sets Virginia data center standards and bans secret project agreements
- HB 30 · In effect · Jul 1, 2026Budget act item taxing data center electricity at 1.1 cents per kWh
- HB 1393 · Signed into law · May 14, 2026Shifts grid costs to the largest electricity customers
Who's involved
- Developer and operatorSTACK Infrastructure
Power
Capacity, as announced or filed
- 128.138 MW · Generator fleet, Reg. 74269 (19265 & 19275 Compass Creek Parkway SE, Leesburg)Feb 2026 · generator_capacity
From the filings
Numbers stated in permits, agreements, and decisions, as printed. Each links to the filing.
Virginia Commission on Local Government, Voluntary Settlement Agreement of Annexation and Related Issues, under Va. Code Section 15.2-3400
- Stated in the filing
- 672,000 gallons of commissioning water for Building 1 (one-time), in the Town Council approval of March 14, 2023
- Stated in the filing
- 128,000 gallons of final mechanical water for Building 1 (one-time), in the Town Council approval of March 14, 2023
- Stated in the filing
- 28.943 acres (the STACK Property as defined in the agreement: the approximately 28.943-acre portion of the parcel with County PIN 234-38-2603, owned by SI NVA06A LLC)
- Stated in the filing
- 128,000 gallons of final mechanical water for Building 2 (one-time), in the Town Council approval of March 14, 2023
- Stated in the filing
- 336,000 gallons of commissioning water for Building 2 (one-time), in the Town Council approval of March 14, 2023
- Stated in the filing
- $75.2 million , approximate price for the combined parcel sold to SI NVA06A, LLC on August 15, 2023
Loudoun County, Virginia, MCPI 234371847000
- Stated in the filing
- 33.176 acres
- Stated in the filing
- 621,036 square feet of data center buildings on the parcel (Overall_SQ_FT: 388,150 + 232,886, two buildings), Loudoun County Existing Data Center Parcels layer, MCPI 234371847000
Virginia Department of Environmental Quality, Registration No. 74269
- Backup generators
- 1 Kohler KD1600 diesel-fired emergency engine gen-set (Ref. No. EG-43), rated 1,600 ekW (2,353 bhp) and de-rated to 1,200 ekW (1,765 bhp), originally permitted June 18, 2024
- Backup generators
- 1 Kohler KD1250 diesel-fired emergency engine gen-set (Ref. No. EG-44), rated 1,250 ekW (1,865 bhp) and de-rated to 938 ekW (1,399 bhp), equipment to be constructed under the February 11, 2026 permit
- Backup generators
- 44 emergency diesel engine gen-sets permitted under the February 11, 2026 combined permit (Ref. Nos. EG-01 through EG-44)
- Backup generators
- 42 Kohler KD3000 and/or Caterpillar C175-16 diesel-fired emergency engine gen-sets (Ref. Nos. EG-01 through EG-42), 3,000 ekW (4,332 bhp Kohler / 4,423 bhp CAT) each, originally permitted June 18, 2024
Town of Leesburg, Virginia, Town Council Agenda Item 13b, March 14, 2023
- Stated in the filing
- 1,600 gallons per day, average water demand cap for the two buildings combined (800 gallons per day each), office operations only
Virginia Department of Environmental Quality, VAR10T460
- Stated in the filing
- 24.2 acres
- Stated in the filing
- 24.2 acres
Public records
23 records found so far. 5 kinds of record are still being collected.
See every recordCourt cases and commission dockets
- Utility commission · Pending before the commission · Sep 1, 2026Petition of Northern Virginia Electric Cooperative for approval of revisions to the Terms and Conditions of Rate Schedules LP-1, DPS, HV-1 and HV-2
- Utility commission · In effect · Apr 1, 2023Schedule HV-1, Large Power Dedicated Distribution Service
Questions people ask
- Where is STACK Infrastructure Loudoun County campus?
- STACK Infrastructure Loudoun County campus is a data center project in Leesburg, Loudoun County, Virginia.
- Who operates STACK Infrastructure Loudoun County campus?
- STACK Infrastructure is named as the operator of STACK Infrastructure Loudoun County campus.
- How big is STACK Infrastructure Loudoun County campus?
- STACK Infrastructure Loudoun County campus was announced at 144 MW of capacity. The site covers 33.18 acres.
- What stage is STACK Infrastructure Loudoun County campus?
- STACK Infrastructure Loudoun County campus is under construction. It was first public in 2025.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Report on the Town of Leesburg - Loudoun County Voluntary Settlement Agreement
Virginia Commission on Local Government (Department of Housing and Community Development)Tier 1 · Captured 2026-11-09 · Open the source - 2Leesburg Town Council Approves Voluntary Settlement Agreement Related to Compass Creek Annexation
Town of Leesburg, VirginiaTier 1 · Captured 2026-11-09 · Open the source - 3Existing Data Center Parcels (county GIS layer), records for MCPI 044261032000 (Pacific Boulevard, Sterling) and MCPI 234371847000 (Compass Creek, Leesburg)
Loudoun County, VirginiaTier 1 · Captured 2026-11-09 · Open the source - 4Stationary Source Permit to Construct and Operate (combined document, February 11, 2026), SI NVA06A, LLC, Registration No. 74269
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 5Issued Air Permits for Data Centers (list as of January 29, 2026)
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-08 · Open the source - 6Town Council Meeting, March 14, 2023: agenda and official webcast captions
Town of Leesburg, Virginia (Granicus webcast archive)Tier 1 · Captured 2026-11-09 · Open the source - 7Stormwater Permits (Daily), EDMA MapServer layer 303
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 8Loudoun County Zoning Ordinance (official text, eReader)
Loudoun County, VirginiaTier 1 · Captured 2026-11-07 · Open the source - 9Land Use Considerations (county data center page)
Loudoun County, VirginiaTier 1 · Captured 2026-11-07 · Open the source - 10Order for Notice and Hearing, Case No. PUR-2026-00114 (NOVEC terms and conditions revisions)
Virginia State Corporation CommissionTier 1 · Captured 2026-11-07 · Open the source - 11Schedule HV-1, Large Power Dedicated Distribution Service
Northern Virginia Electric CooperativeTier 1 · Captured 2026-11-07 · Open the source - 12Minutes, Loudoun County Planning Commission Work Session, December 10, 2020
Loudoun County Planning CommissionTier 1 · Captured 2026-11-09 · Open the source - 13Action Report of the April 13, 2022, Board of Supervisors Public Hearing (County Administrator memorandum, April 15, 2022)
Loudoun CountyTier 1 · Captured 2026-11-09 · Open the source - 14Town Council Meeting, February 27, 2024: agenda and official webcast captions
Town of Leesburg, Virginia (Granicus webcast archive)Tier 1 · Captured 2026-11-09 · Open the source - 15Board of Supervisors Business Meeting Minutes, March 18, 2025
Loudoun CountyTier 1 · Captured 2026-11-07 · Open the source - 16Loudoun County Board of Equalization 2025 Annual Report
Loudoun County Board of EqualizationTier 1 · Captured 2026-11-09 · Open the source - 17STACK Infrastructure Expands Loudoun County Footprint with 144MW Hyperscale Campus
STACK InfrastructureTier 4 · Captured 2026-11-08 · Open the source - 18Stationary Source Permit to Construct and Operate (combined document, as amended August 21, 2025), SI NVA01 ABS, LLC, Registration No. 74079
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 19EDMA Active Air Sites layer (MapServer layer 294), facility records for STACK Infrastructure registrations in Virginia (74079, 74269, 74224, 74246, 74291)
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 20Northern Virginia market page and campus index
STACK InfrastructureTier 4 · Captured 2026-11-09 · Open the source - 21
- 22
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page