What it is
Service from 115 kV facilities at delivery voltage of 12.5 kV or more, for new or additional separately metered load of at least 5,000 kW with an average annual load factor of at least 70 percent. An Electric Service Agreement is required. Billing demand is the highest of the month's maximum 30-minute demand, 5,000 kW, or the contract minimum demand. Excess facilities are charged monthly (1.37 percent substation, 1.17 percent line) or paid up front as a contribution in aid of construction at reduced monthly rates.
The facts
- Regulator
- Virginia State Corporation Commission
- Type
- Large load tariff
- Utility
- Northern Virginia Electric Cooperative
- State
- Virginia
- Status date
- Apr 1, 2023
- Large-load rules
- Yes, for loads of 5 MW or more
Projects served by Northern Virginia Electric Cooperative
Related cases and proceedings
- Utility commission · Pending before the commissionPetition of Appalachian Power Company For approval of Revisions to the Terms and Conditions of Rate Schedule L.P.S.
- Utility commission · Pending before the commissionPetition of Mecklenburg Electric Cooperative for approval to implement a new Large Power Service Rate Schedule (Schedule LPS-U)
- Utility commission · In effectPetition of Rappahannock Electric Cooperative For approval to implement a new Large Power Dedicated Facilities Rate Schedule
- Utility commission · DecidedApplication of Virginia Electric and Power Company for a 2023 biennial review of the rates, terms and conditions for the provision of generation, distribution and transmission services
- Utility commission · DecidedApplication of Mecklenburg Electric Cooperative for approval of a special rate (Schedule RTO)
- Court case · DecidedBoard of County Supervisors of Prince William County et al. v. Oak Valley Homeowners Association, Inc., et al. (Digital Gateway rezonings)
- Court case · DecidedTown of Leesburg and Loudoun County voluntary settlement agreement validation (Compass Creek annexation)
Sources
- 1Schedule HV-1, Large Power Dedicated Distribution Service
Northern Virginia Electric CooperativeTier 1 · Schedule HV-1 (filed for informational purposes 2023-03-22, effective 2023-04-01), Availability, Billing Demand, and Excess Facilities Charge sections · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Schedule HV-1, Large Power Dedicated Distribution Service." Last activity 2023-04-01. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-novec-hv1-2023