Schedule HV-1, Large Power Dedicated Distribution Service

Where it stands: In effect as of Apr 1, 2023

Draft research, not yet verified. Open a source to check any detail.

What it is

Service from 115 kV facilities at delivery voltage of 12.5 kV or more, for new or additional separately metered load of at least 5,000 kW with an average annual load factor of at least 70 percent. An Electric Service Agreement is required. Billing demand is the highest of the month's maximum 30-minute demand, 5,000 kW, or the contract minimum demand. Excess facilities are charged monthly (1.37 percent substation, 1.17 percent line) or paid up front as a contribution in aid of construction at reduced monthly rates.

The facts

Regulator
Virginia State Corporation Commission
Type
Large load tariff
Utility
Northern Virginia Electric Cooperative
State
Virginia
Status date
Apr 1, 2023
Large-load rules
Yes, for loads of 5 MW or more

Projects served by Northern Virginia Electric Cooperative

Related cases and proceedings

Sources

  1. 1
    Schedule HV-1, Large Power Dedicated Distribution Service
    Northern Virginia Electric Cooperative
    Tier 1 · Schedule HV-1 (filed for informational purposes 2023-03-22, effective 2023-04-01), Availability, Billing Demand, and Excess Facilities Charge sections · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Schedule HV-1, Large Power Dedicated Distribution Service." Last activity 2023-04-01. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-novec-hv1-2023