What it is
Created Schedule RTO, a single-customer large power contract rate for one new customer with data center load, because none of the cooperative's tariffs fit the size of the load. Supply charges pass through the wholesale supplier, Old Dominion Electric Cooperative, including true-ups. Delivery charges track the customer's three-phase load ramp at the Boydton and Coleman Creek substations. First-year gross revenues were stated at $4.7 million, rising to $120 million at full capacity.
The facts
- Regulator
- Virginia State Corporation Commission
- Docket number
- PUR-2021-00059
- Type
- Other
- Utility
- Mecklenburg Electric Cooperative
- State
- Virginia
- Filed
- Apr 14, 2021
- Status date
- Dec 14, 2021
- Large-load rules
- Yes
Projects served by Mecklenburg Electric Cooperative
Related cases and proceedings
- Utility commission · Pending before the commissionPetition of Mecklenburg Electric Cooperative for approval to implement a new Large Power Service Rate Schedule (Schedule LPS-U)
- Utility commission · In effectPetition of Rappahannock Electric Cooperative For approval to implement a new Large Power Dedicated Facilities Rate Schedule
- Utility commission · DecidedApplication of Virginia Electric and Power Company for a 2023 biennial review of the rates, terms and conditions for the provision of generation, distribution and transmission services
- Utility commission · In effectSchedule HV-1, Large Power Dedicated Distribution Service
- Court case · DecidedBoard of County Supervisors of Prince William County et al. v. Oak Valley Homeowners Association, Inc., et al. (Digital Gateway rezonings)
- Court case · DecidedTown of Leesburg and Loudoun County voluntary settlement agreement validation (Compass Creek annexation)
In the record
- Utility case, Apr 14, 2021. Utility case filed: Application of Mecklenburg Electric Cooperative for approval of a special rate (Schedule RTO) Virginia State Corporation Commission, PUR-2021-00059
Sources
- 1Order Granting Approval, Case No. PUR-2021-00059 (Mecklenburg Electric Cooperative special rate, Schedule RTO)
Virginia State Corporation CommissionTier 1 · Order Granting Approval, 2021-12-14 (case caption, Schedule LP - Contract - RTO, revenue figures, findings) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Application of Mecklenburg Electric Cooperative for approval of a special rate (Schedule RTO)." Last activity 2021-12-14. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-mecklenburg-rto-2021