Utility commission
Application of Virginia Electric and Power Company for a 2023 biennial review of the rates, terms and conditions for the provision of generation, distribution and transmission services
Where it stands: Decided as of Feb 28, 2024
Draft research, not yet verified. Open a source to check any detail.
What it is
This review approved the Contract Dollar Minimum policy now in Terms and Conditions Section XXII.Q: when net distribution investment for new service exceeds $350,000, Dominion may require a written revenue guarantee with a monthly minimum of 50 percent of the customer's lowest anticipated monthly bill, secured by cash deposit, surety bond, or irrevocable letter of credit. The minimum ends when the term expires or revenues collected exceed the net investment.
The facts
- Regulator
- Virginia State Corporation Commission
- Docket number
- PUR-2023-00101
- Type
- Rate case
- Utility
- Dominion Energy Virginia
- State
- Virginia
- Filed
- Jul 3, 2023
- Status date
- Feb 28, 2024
- Large-load rules
- Yes
Projects served by Dominion Energy Virginia
- Aligned Data Centers Ashburn (Uunet Drive)
- Aligned Data Centers Sterling (Relocation Drive)
- Amazon Cosner Tech Campus
- Amazon IAD-10 (45630 Severn Way, Sterling)
- Amazon IAD-114 (20945 Loudoun County Parkway, Ashburn)
- Amazon IAD-116 (45781 Maries Road, Sterling)
- Amazon IAD-120 (23825 Erins Run Drive, Sterling)
- Amazon IAD-12 (22630 Dulles Summit Ct, Sterling)
- Amazon IAD-124 (24214 Quail Ridge Lane, Aldie)
- Amazon IAD-140 (22890 Platform Plaza, Sterling)
- Amazon IAD-144 (22945 International Drive, Sterling)
- Amazon IAD-146 (22370 and 22420 Kipper Drive, Sterling)
Related cases and proceedings
- Utility commission · DecidedApplication of Virginia Electric and Power Company for a 2025 biennial review of the rates, terms and conditions for the provision of generation, distribution and transmission services
- Utility commission · Pending before the commissionPetition of Appalachian Power Company For approval of Revisions to the Terms and Conditions of Rate Schedule L.P.S.
- Utility commission · Pending before the commissionPetition of Mecklenburg Electric Cooperative for approval to implement a new Large Power Service Rate Schedule (Schedule LPS-U)
- Utility commission · In effectPetition of Rappahannock Electric Cooperative For approval to implement a new Large Power Dedicated Facilities Rate Schedule
- Utility commission · In effectSchedule HV-1, Large Power Dedicated Distribution Service
- Utility commission · DecidedApplication of Mecklenburg Electric Cooperative for approval of a special rate (Schedule RTO)
- Court case · DecidedBoard of County Supervisors of Prince William County et al. v. Oak Valley Homeowners Association, Inc., et al. (Digital Gateway rezonings)
- Court case · DecidedTown of Leesburg and Loudoun County voluntary settlement agreement validation (Compass Creek annexation)
In the record
- Utility case, Jul 3, 2023. Utility case filed: Application of Virginia Electric and Power Company for a 2023 biennial review of the rates, terms and conditions for the provision of generation, distribution and transmission services Virginia State Corporation Commission, PUR-2023-00101
Sources
- 1Virginia Electric and Power Company Entire Filed Tariff (revised June 1, 2026)
Dominion Energy VirginiaTier 1 · Entire Filed Tariff revised 2026-06-01, Terms and Conditions Section XXII.Q (effective 2026-01-01) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Application of Virginia Electric and Power Company for a 2023 biennial review of the rates, terms and conditions for the provision of generation, distribution and transmission services." Last activity 2024-02-28. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-dominion-contract-minimum-2023