Project File

Aligned Data Centers Ashburn (Uunet Drive)

Loudoun County,VirginiaOperatingFirst public 2018Filing entity: Aligned Data CentersLast checked Nov 9, 2026

Aligned Data CentersDeveloper and operator

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

5 of 6 details confirmed

  • Confirmed: County
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: Electric utility
  • Confirmed: First public date
  • Still to confirm: City or address
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Aligned Data Centers Ashburn (Uunet Drive) is an operating data center project in Loudoun County, Virginia. Aligned Data Centers is named as operator. It was first public in 2018. It was announced at 180 MW.

Aligned Data Centers Ashburn (Uunet Drive) is an operating data center project in Loudoun County, Virginia. Aligned Data Centers is named as operator. It was announced at 180 MW. 5 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Loudoun County, Virginia. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

180 MWAnnounced capacity
22Public records we have found
110Backup generators, emergency diesel engine gen-sets permitted under the July 18, 2022 permit (GEN1 through GEN108, plus LSGEN-1 and LSGEN-2)

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Newswire for Loudoun County

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Aerial view of Aligned Data Centers Ashburn (Uunet Drive) in Loudoun County, Virginia, captured 2023
Aerial image, USDA National Agriculture Imagery Program, via the USGS National Map, Public domain (USDA NAIP), captured 2023Aerial images can be older than the campus. This one shows what was on the ground when it was taken.Source: USDA National Agriculture Imagery Program, via the USGS National MapLicense: Public domain (USDA NAIP)
Site-level positionPin placed from the position we have on file, inside Loudoun County, Virginia.See every project on the map

The land, to scale

One football field
26 acres, about 20 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · DecisionVirginia Department of Environmental Quality: Issued (Article 6 minor New Source Review); supersedes the permit document dated May 17, 2019 (air permit) for Aligned Data Centers Ashburn (Uunet Drive)Registration No. 74169
  2. · New projectFirst public record of Aligned Data Centers Ashburn (Uunet Drive)Operating
  3. · FilingFiled with Virginia Department of Environmental Quality: stormwater permit for Aligned Data Centers Ashburn (Uunet Drive)VAR10L812

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Checked by AI against the bill text, not yet by a person · Nov 29, 2026Virginia HB 30: Budget act item taxing data center electricity at 1.1 cents per kWh

    The budget item taxes every data center operator on electricity consumed at each data center from July 1, 2026 to July 1, 2028 and defines a data center to include equipment for the transformation, transmission, distribution, or management of at least one megawatt of electrical power and cooling; this project is an operating data center in Virginia with a capacity figure over one megawatt on record, so every condition the text sets is met by a fact on record.

    “"Data center" means a facility whose primary services are to centralize the storage, management, and processing of digital data and is used to house (i) computer and network systems, including associated components such as servers, network equipment and appliances, telecommunications, and data storage systems; (ii) systems for monitoring and managing infrastructure performance; (iii) equipment used for the transformation, transmission, distribution, or management of at least one megawatt of capacity of electrical power and cooling, including substations, uninterruptible power supply systems, all electrical plant equipment, and associated air handlers; (iv) Internet-related equipment and services; (v) data communications connections; (vi) environmental controls; (vii) fire protection systems; and (viii) security systems and services. “Data center" does not include a facility whose primary function is to facilitate the provision of internet access service, a communication service as defined in § 58.1-647, or any combination thereof.” (Item 3-5.24, paragraph A.2 (HB 30, Chapter 1, Part 3))

    Rule checks: Project is in Virginia; 180 MW on record (announced), threshold 1 MW (Item 3-5.24, paragraph A.2 (HB 30, Chapter 1, Part 3)). Still to check: dates: not checked, who it covers: not checked

  • Checked by AI against the bill text, not yet by a person · Nov 29, 2026Virginia HB 496: Requires monthly water use reports for data centers

    The act requires a water user that provides water to another person offsite to report monthly potable and reclaimed water volumes separately for a data center with an air permit issued by the Department of Environmental Quality, effective January 1, 2027; this project is a data center in Virginia on the DEQ issued data center permits list on record, so it falls in the reporting category the text sets.

    “Any water user required to register water withdrawal and use data pursuant to this subsection that provides water to another person offsite shall include in its report, submitted on its regular reporting schedule, the total volume of potable water and, reported separately, the total volume of reclaimed water provided during each month for each of the following categories: (i) a data center, as that term is defined in subdivision A 43 of § 58.1-3506, with an air permit issued by the Department” (Enacted text (Chapter 623), § 62.1-44.38 C)

    Rule checks: Project is in Virginia. Still to check: dates: not checked, who it covers: not checked

  • Checked by AI against the bill text, not yet by a person · Nov 29, 2026Virginia SB 553: Requires monthly water use reports for data centers

    The act requires a water user that provides water to another person offsite to report monthly potable and reclaimed water volumes separately for a data center with an air permit issued by the Department of Environmental Quality, effective January 1, 2027; this project is a data center in Virginia on the DEQ issued data center permits list on record, so it falls in the reporting category the text sets.

    “Any water user required to register water withdrawal and use data pursuant to this subsection that provides water to another person offsite shall include in its report, submitted on its regular reporting schedule, the total volume of potable water and, reported separately, the total volume of reclaimed water provided during each month for each of the following categories: (i) a data center, as that term is defined in subdivision A 43 of § 58.1-3506, with an air permit issued by the Department” (Enacted text (conference substitute 26109885D, as passed), § 62.1-44.38 C)

    Rule checks: Project is in Virginia. Still to check: dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia HB 1393: Shifts grid costs to the largest electricity customers

    The bill directs Dominion Energy Virginia to propose allocating capacity procurement and distribution infrastructure costs to its customer class with a contracted or measured demand of 25 megawatts or greater and an average load factor of 75 percent or greater, in rate proceedings commencing after January 1, 2027 and before July 1, 2033; this project is served by Dominion Energy Virginia on record, but its contracted or measured demand and its average annual load factor are not on record.

    “Dominion Energy Virginia to propose to the Commission, in any proceeding to determine rates for generation and distribution services commencing after January 1, 2027, and before July 1, 2033, that certain costs related to capacity procurement requirements and distribution infrastructure investments are allocated to the utility's customer class approved to serve customers with a contracted or measured electric demand of 25 megawatts or greater and an anticipated or measured average annual electric load factor of 75 percent or greater” (LIS bill-details page for HB 1393 (2026), Summary)

    Rule checks: Project is in Virginia. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia HB 153: Requires site assessments before local approval of large data centers

    The act covers new high energy use facilities, facilities an applicant reasonably anticipates at the time of filing a rezoning, special exception, or special use permit application will require 100 megawatts or more of electrical power from a retail electric utility, which require a site assessment before local approval; this project has 180 MW announced on record, but whether this project is a new facility seeking such a local approval and the electrical power anticipated for it at filing is not on record.

    “"high energy use facility" or "HEUF" means a facility that an applicant reasonably anticipates at the time of filing a rezoning application, special exception application, or special use permit application will require 100 megawatts or more of electrical power from an electric utility providing retail service to the facility.” (Va. Code Sec. 15.2-2209.4 A)

    Rule checks: Project is in Virginia; 180 MW on record (announced), threshold 100 MW (Va. Code Sec. 15.2-2209.4 A). Still to check: dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia HB 323: Directs a state study of data center waste heat

    The act directs the Department of Energy to lead efforts to accelerate the use of waste heat from data centers in the Commonwealth, convene a work group, and report by September 1, 2026; it sets no project-level condition on an individual data center, and whether this project's waste heat is within the work group's scope is not on record.

    “Directs the Department of Energy to lead efforts to accelerate the use of waste heat from data centers in the Commonwealth by making certain findings and recommendations and convening a work group to provide expertise, assistance, and feedback on the Department's efforts.” (LIS bill-details page for HB 323 (2026), Summary As Passed)

    Rule checks: Project is in Virginia. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia HB 507: Sets Tier 4 generator emission limits in data center air permits

    The section bars the Department of Environmental Quality from issuing a data center permit on an application submitted on or after July 1, 2026 unless the emission limit for each gen-set is equal to or less than the emissions achieved by a Tier 4 equivalent gen-set; this project is on the DEQ issued data center permits list on record, but no permit application submission date on or after July 1, 2026 is on record for it.

    “For any application submitted for a data center on or after July 1, 2026, for a permit issued by the Department pursuant to this chapter, including coverage under any general permit, the Department shall not issue such permit unless the emission limit for each gen-set established by such permit is equal to or less than the emissions achieved by a Tier 4 equivalent gen-set.” (Va. Code Sec. 10.1-1322.6(B) (2026, c. 397))

    Rule checks: Project is in Virginia. Still to check: who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Virginia SB 94: Requires site assessments before local approval of large data centers

    The section's site assessment duty turns on the electrical power a facility is anticipated to require from its retail electric utility, and no such figure is on record for this project; its on-record capacity is 276 MW of standby generator capacity and a 180 MW announced figure that does not state what it measures, neither of which measures power drawn from the utility.

    “"high energy use facility" or "HEUF" means a facility that an applicant reasonably anticipates at the time of filing a rezoning application, special exception application, or special use permit application will require 100 megawatts or more of electrical power from an electric utility providing retail service to the facility.” (Chapter 568 (2026 Acts of Assembly), new Code of Virginia section 15.2-2209.4, subsection A)

    Rule checks: Project is in Virginia; 180 MW on record (announced), threshold 100 MW (Chapter 568 (2026 Acts of Assembly), new Code of Virginia section 15.2-2209.4, subsection A). Still to check: who it covers: not checked

Bills and laws in Virginia

All 29 in Bill Watch

Who's involved

Power

Capacity, as announced or filed

  • 276 MW · Generator fleet, Reg. 74169 (Ashburn Buildings 1 and 2)Jul 2022 · generator_capacity

From the filings

Numbers stated in permits, agreements, and decisions, as printed. Each links to the filing.

  • Virginia Department of Environmental Quality, VAR10L812

    Stated in the filing
    28.92 acres
    Stated in the filing
    125.22 acres
  • Loudoun County Board of Equalization

    Stated in the filing
    $631.8 million
    Stated in the filing
    $443.7 million
    Stated in the filing
    $1.26 billion
    Stated in the filing
    8.85 acres
    Stated in the filing
    $981.6 million
    Stated in the filing
    10.85 acres
  • Virginia Department of Environmental Quality, Registration No. 74169

    Backup generators
    110 emergency diesel engine gen-sets permitted under the July 18, 2022 permit (GEN1 through GEN108, plus LSGEN-1 and LSGEN-2)
    Backup generators
    4 Caterpillar Model 3516C emergency diesel engine gen-sets (GEN65 through GEN68), 2,500 ekW (3,634 bhp) each, to be constructed under the July 18, 2022 permit
    Stated in the filing
    3,000 ekW standby rated capacity of the largest gen-set class in the July 18, 2022 permit (GEN69 through GEN108); the other classes are rated 2,250 ekW (64 units), 2,500 ekW (4 units) and 1,000 ekW (2 units)
    Backup generators
    2 Caterpillar Model C32 emergency diesel engine gen-sets (LSGEN-1 and LSGEN-2), 1,000 ekW (1,483 bhp) each, originally permitted May 17, 2019
    Backup generators
    40 Caterpillar Model 3516E and/or Caterpillar Model C175 DITA emergency diesel engine gen-sets (GEN69 through GEN108), 3,000 ekW (4,393 bhp / 4,423 bhp) each, to be constructed under the July 18, 2022 permit
    Backup generators
    64 Caterpillar Model 3516C emergency diesel engine gen-sets (GEN1 through GEN64), 2,250 ekW (3,273 bhp) each, originally permitted May 17, 2019

Public records

22 records found so far. 5 kinds of record are still being collected.

See every record

Questions people ask

Where is Aligned Data Centers Ashburn (Uunet Drive)?
Aligned Data Centers Ashburn (Uunet Drive) is a data center project in Loudoun County, Virginia.
Who operates Aligned Data Centers Ashburn (Uunet Drive)?
Aligned Data Centers is named as the operator of Aligned Data Centers Ashburn (Uunet Drive).
How big is Aligned Data Centers Ashburn (Uunet Drive)?
Aligned Data Centers Ashburn (Uunet Drive) was announced at 180 MW of capacity. The site covers 26 acres.
What stage is Aligned Data Centers Ashburn (Uunet Drive)?
Aligned Data Centers Ashburn (Uunet Drive) is operating. It was first public in 2018.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Stormwater Permits (Daily), EDMA MapServer layer 303
    Virginia Department of Environmental Quality
    Tier 1 · Captured 2026-11-09 · Open the source
  2. 2
    Loudoun County Board of Equalization 2025 Annual Report
    Loudoun County Board of Equalization
    Tier 1 · Captured 2026-11-09 · Open the source
  3. 3
    Stationary Source Permit to Construct and Operate, Aligned Energy, LLC, Registration No. 74169 (July 18, 2022)
    Virginia Department of Environmental Quality
    Tier 1 · Captured 2026-11-09 · Open the source
  4. 4
    Issued Air Permits for Data Centers (list as of January 29, 2026)
    Virginia Department of Environmental Quality
    Tier 1 · Captured 2026-11-08 · Open the source
  5. 5
    Loudoun County Zoning Ordinance (official text, eReader)
    Loudoun County, Virginia
    Tier 1 · Captured 2026-11-07 · Open the source
  6. 6
    Land Use Considerations (county data center page)
    Loudoun County, Virginia
    Tier 1 · Captured 2026-11-07 · Open the source
  7. 7
    Virginia Electric and Power Company Entire Filed Tariff (revised June 1, 2026)
    Dominion Energy Virginia
    Tier 1 · Captured 2026-11-07 · Open the source
  8. 8
    SCC Issues Order on DEV Biennial Review 2025
    Virginia State Corporation Commission
    Tier 1 · Captured 2026-11-07 · Open the source
  9. 9
    Application of Virginia Electric and Power Company for approval of its large-load connection queue process standards, Case No. PUR-2026-00011
    Virginia Electric and Power Company
    Tier 1 · Captured 2026-11-07 · Open the source
  10. 10
    How the SCC Rider T1 Decision Protects Ratepayers
    Virginia State Corporation Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  11. 11
    Order for Notice and Hearing, Case No. PUR-2026-00056
    Virginia State Corporation Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  12. 12
    Minutes, Loudoun County Planning Commission Work Session, December 10, 2020
    Loudoun County Planning Commission
    Tier 1 · Captured 2026-11-09 · Open the source
  13. 13
    Action Report of the April 13, 2022, Board of Supervisors Public Hearing (County Administrator memorandum, April 15, 2022)
    Loudoun County
    Tier 1 · Captured 2026-11-09 · Open the source
  14. 14
    Report on the Town of Leesburg - Loudoun County Voluntary Settlement Agreement
    Virginia Commission on Local Government (Department of Housing and Community Development)
    Tier 1 · Captured 2026-11-09 · Open the source
  15. 15
    Board of Supervisors Business Meeting Minutes, March 18, 2025
    Loudoun County
    Tier 1 · Captured 2026-11-07 · Open the source
  16. 16
    Aligned Expands into Northern Virginia with New 180-Megawatt Data Center Campus
    Aligned Data Centers
    Tier 4 · Captured 2026-11-08 · Open the source
  17. 17
    Aligned Completes Phase One of Ashburn Data Center Campus
    Aligned Data Centers
    Tier 4 · Captured 2026-11-08 · Open the source
  18. 18
    U.S. Census Geocoder (batch geographies endpoint)
    U.S. Census Bureau
    Tier 1 · Captured 2026-11-11 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page