Every public record we have for Aligned Data Centers Ashburn (Uunet Drive)
Loudoun County, VirginiaOperatingFirst public 2018Filing entity: Aligned Data CentersLast checked Nov 9, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
2 of 22 records · showing environmental permits only ·
2022
Air permitIssuedJul 18, 2022Virginia Department of Environmental Quality
Virginia Department of Environmental Quality, Registration No. 74169
Issued (Article 6 minor New Source Review); supersedes the permit document dated May 17, 2019
- Backup generators:
- 110 emergency diesel engine gen-sets permitted under the July 18, 2022 permit (GEN1 through GEN108, plus LSGEN-1 and LSGEN-2)
- Backup generators:
- 4 Caterpillar Model 3516C emergency diesel engine gen-sets (GEN65 through GEN68), 2,500 ekW (3,634 bhp) each, to be constructed under the July 18, 2022 permit
- Stated in the filing:
- 3,000 ekW standby rated capacity of the largest gen-set class in the July 18, 2022 permit (GEN69 through GEN108); the other classes are rated 2,250 ekW (64 units), 2,500 ekW (4 units) and 1,000 ekW (2 units)
- Backup generators:
- 2 Caterpillar Model C32 emergency diesel engine gen-sets (LSGEN-1 and LSGEN-2), 1,000 ekW (1,483 bhp) each, originally permitted May 17, 2019
- Backup generators:
- 40 Caterpillar Model 3516E and/or Caterpillar Model C175 DITA emergency diesel engine gen-sets (GEN69 through GEN108), 3,000 ekW (4,393 bhp / 4,423 bhp) each, to be constructed under the July 18, 2022 permit
- Backup generators:
- 64 Caterpillar Model 3516C emergency diesel engine gen-sets (GEN1 through GEN64), 2,250 ekW (3,273 bhp) each, originally permitted May 17, 2019
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Transmittal letter and attached permit, July 18, 2022: Aligned Energy, LLC, facility located at 21890 UUNET Drive, Ashburn, Virginia 20147 (Building 1) and 21821 UUNET Drive, Ashburn, Virginia 20147 (Building 2), Loudoun County; application deemed complete June 17, 2022; Equipment List, p. 3 (GEN1 through GEN108, LSGEN-1 and LSGEN-2)
2014
Stormwater permitIssuedJul 1, 2014Virginia Department of Environmental Quality
Virginia Department of Environmental Quality, VAR10L812
Construction general permit coverage (VAR10), Centurion at Quantum Park, at 21890, 21821, 21861 Uunet Dr, Ashburn; operator of record Aligned Energy Data Centers Ashburn LLC; coverage reissued for the cycle July 1, 2024 to June 30, 2029
- Disturbed acres:
- 28.92 acres
- Development acres:
- 125.22 acres
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
DEQ EDMA Stormwater Permits layer (MapServer layer 303), records for PERMIT_NUMBER VAR10L812: 21890, 21821, 21861 Uunet Dr, ZIP 20147; development 125.22 acres, disturbed 28.92 acres; coverage cycles effective 2014-07-01, 2019-07-01 and 2024-07-01, statuses PER_ISSUED and PER_REISS
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Building and site permits
Building permits, site plans, grading, certificates of occupancy. Usually held by: City or county building department.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Tax breaks and payments
Abatements, enterprise zones, payments in lieu of taxes, fees. Usually held by: County, city, or development authority.
- Courts and disputes
Lawsuits, appeals, settlements. Usually held by: State and federal courts.
- Company filings
Business registrations of filing entities, securities filings. Usually held by: Secretary of state business registry; SEC.
Sources
- 1Stormwater Permits (Daily), EDMA MapServer layer 303
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 2Loudoun County Board of Equalization 2025 Annual Report
Loudoun County Board of EqualizationTier 1 · Captured 2026-11-09 · Open the source - 3Stationary Source Permit to Construct and Operate, Aligned Energy, LLC, Registration No. 74169 (July 18, 2022)
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-09 · Open the source - 4Issued Air Permits for Data Centers (list as of January 29, 2026)
Virginia Department of Environmental QualityTier 1 · Captured 2026-11-08 · Open the source - 5Loudoun County Zoning Ordinance (official text, eReader)
Loudoun County, VirginiaTier 1 · Captured 2026-11-07 · Open the source - 6Land Use Considerations (county data center page)
Loudoun County, VirginiaTier 1 · Captured 2026-11-07 · Open the source - 7Virginia Electric and Power Company Entire Filed Tariff (revised June 1, 2026)
Dominion Energy VirginiaTier 1 · Captured 2026-11-07 · Open the source - 8SCC Issues Order on DEV Biennial Review 2025
Virginia State Corporation CommissionTier 1 · Captured 2026-11-07 · Open the source - 9Application of Virginia Electric and Power Company for approval of its large-load connection queue process standards, Case No. PUR-2026-00011
Virginia Electric and Power CompanyTier 1 · Captured 2026-11-07 · Open the source - 10How the SCC Rider T1 Decision Protects Ratepayers
Virginia State Corporation CommissionTier 1 · Captured 2026-11-08 · Open the source - 11Order for Notice and Hearing, Case No. PUR-2026-00056
Virginia State Corporation CommissionTier 1 · Captured 2026-11-08 · Open the source - 12Minutes, Loudoun County Planning Commission Work Session, December 10, 2020
Loudoun County Planning CommissionTier 1 · Captured 2026-11-09 · Open the source - 13Action Report of the April 13, 2022, Board of Supervisors Public Hearing (County Administrator memorandum, April 15, 2022)
Loudoun CountyTier 1 · Captured 2026-11-09 · Open the source - 14Report on the Town of Leesburg - Loudoun County Voluntary Settlement Agreement
Virginia Commission on Local Government (Department of Housing and Community Development)Tier 1 · Captured 2026-11-09 · Open the source - 15Board of Supervisors Business Meeting Minutes, March 18, 2025
Loudoun CountyTier 1 · Captured 2026-11-07 · Open the source - 16Aligned Expands into Northern Virginia with New 180-Megawatt Data Center Campus
Aligned Data CentersTier 4 · Captured 2026-11-08 · Open the source - 17Aligned Completes Phase One of Ashburn Data Center Campus
Aligned Data CentersTier 4 · Captured 2026-11-08 · Open the source - 18U.S. Census Geocoder (batch geographies endpoint)
U.S. Census BureauTier 1 · Captured 2026-11-11 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page