Project File

Big Rock Data Center Project

Spokane County,WashingtonProposedFirst public 2026Filing entity: Big Rock Data LLCLast checked Nov 8, 2026

Apricus Energy PartnersDeveloperAvistaElectric utility

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

4 of 6 details confirmed

  • Confirmed: County
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: First public date
  • Still to confirm: City or address
  • Still to confirm: Electric utility
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Big Rock Data Center Project is a proposed data center project in Spokane County, Washington. Apricus Energy Partners is named as developer. It was first public in 2026. It was announced at 1,000 MW.

Big Rock Data Center Project is a proposed data center project in Spokane County, Washington. Apricus Energy Partners is named as developer. It was announced at 1,000 MW. 4 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Spokane County, Washington. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

1,000 MWAnnounced capacity
1Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Spokane County, Washington.See every project on the map

The land, to scale

One football field
514 acres, about 389 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · New projectFirst public record of Big Rock Data Center ProjectProposed

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Washington SB 5982: Applies clean energy deadlines to large customers buying market power

    The act covers affected market customers, electricity consumers who become a market customer after May 7, 2019, who must meet the chapter's reporting and compliance requirements; this project has 1,000 MW announced on record, but whether this project is an affected market customer that obtains electricity as a market customer is not on record.

    “An "affected market customer" is a customer of a utility, an electricity consumer who becomes a market customer after May 7, 2019.” (Sec. 1, amending RCW 19.405.020, SSB 5982 session law)

    Rule checks: Project is in Washington. Still to check: dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Washington SB 6231: Ends a tax break for replacement data center equipment

    The act covers the state data center exemption programs under RCW 82.08.986 and 82.08.9861, under which no new exemption certificates may be issued on or after July 1, 2028 and the exemptions later expire; this project has 1,000 MW announced on record, but whether this project holds or seeks an exemption certificate under either program is not on record.

    “No new exemption certificates may be issued on or after July 1, 2028.” (Sec. 3, RCW 82.08.9861(1)(c))

    Rule checks: Project is in Washington. Still to check: dates: not checked, who it covers: not checked

Bills and laws in Washington

Open Bill Watch

Who's involved

Public records

1 records found so far. 8 kinds of record are still being collected.

See every record

Questions people ask

Where is Big Rock Data Center Project?
Big Rock Data Center Project is a data center project in Spokane County, Washington.
Who is developing Big Rock Data Center Project?
Apricus Energy Partners is named as the developer of Big Rock Data Center Project.
How big is Big Rock Data Center Project?
Big Rock Data Center Project was announced at 1,000 MW of capacity. The site covers 514 acres.
What stage is Big Rock Data Center Project?
Big Rock Data Center Project is proposed. It was first public in 2026.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Resolution adopting a pause on the acceptance of land use and permit applications for data centers (text)
    Spokane County Board of County Commissioners
    Tier 1 · Captured 2026-11-08 · Open the source
  2. 2
    Board Briefing Session Agenda, August 18, 2026: Data Center Zoning (draft Chapter 14.840)
    Spokane County Board of County Commissioners
    Tier 1 · Captured 2026-11-08 · Open the source