WashingtonHouse of Representatives2025-2026 Biennium, 2026 Regular SessionBill

HB 2515: Sets tariff, reporting, and clean energy rules for large energy users

Official title: Addressing emerging large energy use facilities

Official text

Draft research, not yet verified: traced to the official record by an AI research agent; an editor has not checked it yet.

Where it stands

Died or failed as of Feb 14, 2026. The official record says: Passed the House; returned to House Rules Committee for third reading.

  1. Filed (done)
  2. In committee (done)
  3. Passed one chamber (done)
  4. Passed both chambers (not reached)
  5. Signed into law (not reached)
  6. In effect (not reached)
  7. Died or failed (current stage)

What it does

  • Who pays for grid costs

    Applies to: emerging large energy use facilities (Washington)

    Starts: 2029.

    “for allowances distributed starting in calendar year 2028 for emissions year 2029, the department may not provide allowance allocation to mitigate the cost burden of the program on electricity customers that are emerging large energy use facilities as defined in section 2 of this act.”

    Sec. 7, amending RCW 70A.65.120, E2SHB 2515

  • Certification

    Applies to: emerging large energy use facilities (Washington)

    Starts: 2031.

    “Beginning in 2031 and every year thereafter, certify to the department that for the prior year it used electricity from renewable resources or nonemitting electric generation as defined in RCW 19.405.020, where the electricity generation facility commenced operation on or after January 1, 2026, to serve the load of the emerging large energy use facility in an amount that meets or exceeds 80 percent of its annual energy and capacity requirements;”

    Sec. 6(1)(a), new section in chapter 19.29A RCW, E2SHB 2515

  • Definition · threshold 20 MW

    Applies to: emerging large energy use facilities (Washington)

    “"Emerging large energy use facility" means a facility that has a maximum aggregate contract demand of 20 megawatts or more and is primarily engaged in providing a service described under code 518210 of the 2022 North American industry classification system.”

    Sec. 2, amending RCW 19.29A.010(14), E2SHB 2515

  • Incentive restriction

    Applies to: eligible computer data centers (Washington)

    Ends: 2030-07-01.

    “Each calendar year, the department may issue no more than one certificate for an exemption under this section.”

    Sec. 9(1)(c), new section in chapter 82.08 RCW, E2SHB 2515

  • Reporting duty

    Applies to: emerging large energy use facilities (Washington)

    “The owner of each emerging large energy use facility in the state must: (1) Publish a sustainability report demonstrating how the emerging large energy use facility will address and balance energy, water, and computing performance to maximize energy efficiency, water efficiency, and overall sustainability of the facility's operations. The report must include projected annual energy and water consumption for three years and the source of the energy and water.”

    Sec. 4, new section in chapter 19.29A RCW, E2SHB 2515

  • Electric rate class

    Applies to: emerging large energy use facilities (Washington)

    Starts: 2026-10-01.

    “By October 1, 2026, each investor-owned utility with an emerging large energy use facility in its service territory must submit to the commission and make publicly available an emerging large energy use facility tariff or policy for emerging large energy use facilities in the utility's service area.”

    Sec. 3(1)(a), new section in chapter 19.29A RCW, E2SHB 2515

  • Tax exemption

    Applies to: eligible computer data centers (Washington)

    “An exemption from the tax imposed by RCW 82.08.020 is provided for sales to qualifying businesses and to qualifying tenants of eligible server equipment to be installed, without intervening use, in an eligible computer data center to which a valid exemption certificate applies, and to charges made for labor and services rendered in respect to installing eligible server equipment.”

    Sec. 9(1)(a), new section in chapter 82.08 RCW, E2SHB 2515

Who it touches

No project we track is matched to this bill or order: its rules do not reach them, or a check found it does not apply.

Other projects we track in Washington (36), not affected

Who acted

  • CosponsorBerryHouse
  • CosponsorDuerrHouse
  • CosponsorFosseHouse
  • CosponsorKlobaHouse
  • CosponsorMacriHouse
  • CosponsorParshleyHouse
  • CosponsorPolletHouse
  • CosponsorRamelHouse
  • CosponsorReedHouse
  • CosponsorRyuHouse
  • CosponsorScottHouse
  • CosponsorSimmonsHouse
  • CosponsorStearnsHouse
  • CosponsorStreetHouse
  • CosponsorWylieHouse
  • Primary sponsorDoglioHouse

Timeline

Every official action on record, oldest first. An action that moved the bill to a new stage names that stage.

  1. · HouseFirst reading, referred to Environment & Energy.Stage: In committee
  2. · HousePublic hearing in the House Committee on Environment & Energy at 8:00 AM.
  3. · HouseExecutive action taken in the House Committee on Environment & Energy at 1:30 PM. ENVI - Majority; 1st substitute bill be substituted, do pass.
  4. · HouseReferred to Appropriations.
  5. · HousePublic hearing in the House Committee on Appropriations at 9:00 AM.
  6. · HouseExecutive action taken in the House Committee on Appropriations at 10:30 AM. APP - Majority; 2nd substitute bill be substituted, do pass. Referred to Rules 2 Review.
  7. · HouseRules Committee relieved of further consideration. Placed on second reading.
  8. · House2nd substitute bill substituted (APP 26). Floor amendment(s) adopted. Rules suspended. Placed on Third Reading. Third reading, passed; yeas, 51; nays, 41; absent, 0; excused, 6.Stage: Passed one chamber
  9. · SenateFirst reading, referred to Environment, Energy & Technology.
  10. · SenatePublic hearing in the Senate Committee on Environment, Energy & Technology at 10:30 AM.
  11. · SenateExecutive action taken in the Senate Committee on Environment, Energy & Technology at 1:30 PM. ENET - Majority; do pass with amendment(s). And refer to Ways & Means.
  12. · SenateReferred to Ways & Means.
  13. · SenatePublic hearing in the Senate Committee on Ways & Means at 2:30 PM.
  14. · SenateExecutive session scheduled, but no action was taken in the Senate Committee on Ways & Means at 10:30 AM.
  15. · HouseBy resolution, returned to House Rules Committee for third reading.

More from Washington

Sources

  1. 1
    HB 2515 - 2025-26 - Addressing emerging large energy use facilities - Bill summary
    Washington State Legislature
    Tier 1 · Open the source
  2. 2
    Engrossed Second Substitute House Bill 2515 (2026)
    Washington State Legislature
    Tier 1 · Open the source

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "HB 2515: Sets tariff, reporting, and clean energy rules for large energy users." Bill Watch. Updated 2026-11-13. Accessed 2026-11-29. https://datacenterfactcheck.org/policy/bills/wa-2025-26-hb-2515

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page