Project File

Amazon Attalia Data Center Campus

Wallula,Walla Walla County,WashingtonIn permittingFirst public 2026Filing entity: Amazon Data Services, Inc.Last checked Nov 8, 2026

AmazonDeveloper and end userColumbia REAElectric utility

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

5 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Electric utility
  • Confirmed: First public date
  • Still to confirm: Capacity
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Amazon Attalia Data Center Campus is a data center project in Wallula, Walla Walla County, Washington. Amazon is named as developer. It is in permitting. It was first public in 2026. No site capacity figure is published for this project.

Amazon Attalia Data Center Campus is a data center project in Wallula, Walla Walla County, Washington. Amazon is named as developer. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Wallula, Walla Walla County, Washington. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

0Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Walla Walla County, Washington.See every project on the map

The land, to scale

One football field
134 acres, about 101 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · New projectFirst public record of Amazon Attalia Data Center CampusIn permitting

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Washington SB 5982: Applies clean energy deadlines to large customers buying market power

    The act covers affected market customers, electricity consumers who become a market customer after May 7, 2019, who must meet the chapter's reporting and compliance requirements; this project has no capacity figure on record, but whether this project is an affected market customer that obtains electricity as a market customer is not on record.

    “An "affected market customer" is an electricity consumer who becomes a market customer after May 7, 2019.” (Sec. 1, amending RCW 19.405.020, SSB 5982 session law)

    Rule checks: Project is in Washington. Still to check: dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Washington SB 6231: Ends a tax break for replacement data center equipment

    The act covers the state data center exemption programs under RCW 82.08.986 and 82.08.9861, under which no new exemption certificates may be issued on or after July 1, 2028 and the exemptions later expire; this project has no capacity figure on record, but whether this project holds or seeks an exemption certificate under either program is not on record.

    “No new exemption certificates may be issued on or after July 1, 2028.” (Sec. 3, RCW 82.08.9861(1)(c))

    Rule checks: Project is in Washington. Still to check: dates: not checked, who it covers: not checked

Bills and laws in Washington

Open Bill Watch

Who's involved

Public records

0 records found so far. 9 kinds of record are still being collected.

    See every record

    Questions people ask

    Where is Amazon Attalia Data Center Campus?
    Amazon Attalia Data Center Campus is a data center project in Wallula, Walla Walla County, Washington.
    Who is developing Amazon Attalia Data Center Campus?
    Amazon is named as the developer of Amazon Attalia Data Center Campus.
    How big is Amazon Attalia Data Center Campus?
    The site covers 134 acres.
    What stage is Amazon Attalia Data Center Campus?
    Amazon Attalia Data Center Campus is in permitting. It was first public in 2026.

    Sources

    Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

    1. 1
      Notice of Incomplete Application: Amazon Data Services, SDP26-01 / SEPA26-05, Attalia
      Walla Walla County Community Development Department
      Tier 1 · Captured 2026-11-08 · Open the source

    No corrections have been published for this page. Corrections log · Report an error or send a tip on this page