Project File

Auburndale Technology Center

Auburndale,Polk County,FloridaIn permittingFirst public 2026Filing entity: Hillwood Development Company (site held by Pace Road DC Development Company)Last checked Nov 8, 2026

HillwoodDeveloperTampa ElectricElectric utility

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

5 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: First public date
  • Still to confirm: Electric utility
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Auburndale Technology Center is a data center project in Auburndale, Polk County, Florida. Hillwood is named as developer. It is in permitting. It was first public in 2026. It was announced at 700 MW.

Auburndale Technology Center is a data center project in Auburndale, Polk County, Florida. Hillwood is named as developer. It was announced at 700 MW. 5 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Auburndale, Polk County, Florida. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

700 MWAnnounced capacity
0Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Polk County, Florida.See every project on the map

The land, to scale

One football field
75 acres, about 57 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · New projectFirst public record of Auburndale Technology CenterIn permitting

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Florida HB 7031: Extends data center sales tax exemption, raises bar to 100 megawatts

    The act covers data centers whose owners and tenants make a cumulative capital investment of $150 million or more and reach a critical IT load of 100 megawatts or higher, with 1 megawatt or more per owner or tenant, no later than five years after construction begins, for the sales tax exemption; this project has 700 MW on record (not stated), but the project's cumulative capital investment and its critical IT load is not on record.

    “To be eligible for the exemption provided by this paragraph, the data center's owners and tenants must make a cumulative capital investment of $150 million or more for the data center and the data center must have a critical IT load of 100 megawatts or higher and a critical IT load of 1 megawatt or higher dedicated to each individual owner or tenant within the data center. Each of these requirements must be satisfied no later than 5 years after the commencement of construction of the data center.” (Section 46, s. 212.08(5)(r), Florida Statutes)

    Rule checks: Project is in Florida; 700 MW on record (not stated), threshold 100 MW (Section 46, s. 212.08(5)(r), Florida Statutes). Still to check: dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Florida SB 484: Makes large data centers pay full power and water costs

    The water permitting rules cover large-scale data centers, a single location with a data center on site and an anticipated monthly peak load of 50 megawatts or more; this project has 700 MW not stated on record, but the project's anticipated monthly peak load at a single location is not on record.

    “'Large-scale data center' means a single location, with a data center on site, that has an anticipated monthly peak load of 50 megawatts or more, calculated as the highest average load over a 15-minute interval.” (s. 373.203(4), Florida Statutes)

    Rule checks: Project is in Florida; 700 MW on record (not stated), threshold 50 MW (s. 373.203(4), Florida Statutes). Still to check: dates: not checked, who it covers: not checked

Bills and laws in Florida

All 7 in Bill Watch

Who's involved

Power

Capacity, as announced or filed

  • 350 MW · First phasewhat the figure measures is not stated
  • 700 MW · Full developmentwhat the figure measures is not stated

Public records

0 records found so far. 9 kinds of record are still being collected.

    See every record

    Questions people ask

    Where is Auburndale Technology Center?
    Auburndale Technology Center is a data center project in Auburndale, Polk County, Florida.
    Who is developing Auburndale Technology Center?
    Hillwood is named as the developer of Auburndale Technology Center.
    How big is Auburndale Technology Center?
    Auburndale Technology Center was announced at 700 MW of capacity. The site covers 75 acres.
    What stage is Auburndale Technology Center?
    Auburndale Technology Center is in permitting. It was first public in 2026.

    Sources

    Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

    1. 1
      Auburndale Technology Center project website and FAQ
      Auburndale Technology Center (Hillwood Development Company)
      Tier 4 · Captured 2026-11-08 · Open the source
    2. 2
      Data center planned for existing warehouse in Auburndale
      The Ledger (Lakeland, Florida)
      Tier 3 · Captured 2026-11-08 · Open the source

    No corrections have been published for this page. Corrections log · Report an error or send a tip on this page