State Card

Data centers in Florida

Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.

Data Center Fact Check tracks 17 data center projects in Florida as of November 2026: 11 operating, 2 approved and 1 announced, totaling about 1,930 MW announced where a figure is published.

Florida has 17 tracked data centers. Their announced capacity totals about 1,930 MW where a figure is published. Of those, 11 operating, 2 approved and 1 announced. Every project we track here is listed below, with the public records behind it. Every figure comes from the public record linked on this page.

17Data center projects we track

Data center projects in Florida

Who serves this place

  • Not collected yet.

Counties and cities in Florida

Counties

Cities and towns

Tax breaks and payments

  • Sales and use tax exemption (Fla. Stat. Section 212.08(5)(s))

    Data center property, meaning property used exclusively at a qualifying data center to construct, outfit, operate, support, power, cool, secure, or protect the facility and its contiguous dedicated substations, including electricity used exclusively at the data center, is exempt from state sales and use tax. The Department of Revenue issues a temporary exemption certificate (Form DR-1214DCP) and then a permanent certificate (Form DR-5DCP); temporary certificates may be issued through June 30, 2037, and compliance is reviewed every five years.

  • Local option ad valorem tax exemption with data center terms (Fla. Stat. Section 196.1995)

    Where voters have authorized it, a county or municipality may by ordinance exempt up to 100 percent of the assessed value of improvements and tangible personal property of a new business or an expansion. All data center equipment for a data center is exempt from ad valorem taxation for the term of the approved exemption, and an exemption may run up to 20 years for a data center (10 years for other facilities). The exemption covers only taxes levied by the granting unit and does not apply to bond taxes or voter approved taxes.

Local rules for data centers

  • In effect · Moratorium · Adopted Sep 24, 2026

    One-year moratorium on large-scale data center applications in unincorporated Palm Beach County

    Palm Beach County adopted an ordinance revising its Unified Land Development Code to add the Large-Scale Data Center use and establish a one-year moratorium: the county will not accept process or approve zoning requests or related comprehensive plan amendments for large-scale data centers in unincorporated areas while permanent rules are drafted.

  • In effect · Moratorium · Adopted Jul 28, 2026

    Temporary one-year moratorium on data center facility approvals in unincorporated DeSoto County

    DeSoto County established a one-year moratorium under which the county will not accept process review approve issue or grant any development approval for the construction expansion or operation of a data center facility in the unincorporated county. Development under the March 2026 DCIP rezoning (Ordinance 2026-004 application RZNE-0077-2025) and the pending DCIP rezoning applications are exempt.

  • In effect · Moratorium · Adopted Jun 8, 2026

    Temporary moratorium on data center facility applications in unincorporated Nassau County

    Nassau County imposed a temporary moratorium on the acceptance review processing or approval of applications for data center facilities in the unincorporated county while it studies amendments to its comprehensive plan land development code and code of ordinances. A Fact-Finding Committee on Data Center Development was created the same season under Resolution No. 2026-102.

Recent cases and dockets in Florida

All 6 court cases and commission dockets in Florida

Bills and laws in Florida

Open Bill Watch

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Questions people ask

How many data centers are in Florida?
Data Center Fact Check tracks 17 data center projects in Florida as of November 2026. Of those, 11 operating, 2 approved and 1 announced.
What is the biggest data center in Florida?
By announced capacity, the biggest data center in Florida is Fort Meade data center campus (Project Stonebridge), announced at 1,200 MW. It is approved.
How much power do data centers in Florida use?
The 17 projects tracked in Florida have announced about 1,930 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.

Sources

  1. 1
    Board of County Commissioners Public Hearing Result List 2026-09-24
    Palm Beach County
    Tier 1 · Open the source
  2. 2
    Ordinance establishing a temporary one-year moratorium on data center facilities (text)
    DeSoto County Board of County Commissioners
    Tier 1 · Open the source
  3. 3
    Ordinance Number 2026-044 (temporary data center moratorium) full text
    Nassau County Board of County Commissioners
    Tier 1 · Open the source
  4. 4
    Data Centers page (moratorium and Fact-Finding Committee summary)
    Nassau County
    Tier 1 · Open the source
  5. 5
    Form DR-5DCP, Application for Data Center Property Certificate of Exemption (Rule 12A-1.097)
    Florida Department of Revenue
    Tier 1 · Open the source
  6. 6
    Florida Statutes Section 196.1995, Economic development ad valorem tax exemption
    Florida Legislature
    Tier 1 · Open the source

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Florida." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-fl

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page