Petition by Florida Public Utilities Company to Implement a Large Load Service Tariff

Where it stands: Pending before the commission as of Oct 1, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

Schedule LLS applies to a single site requiring at least 50 MW of service with a load profile different from the typical Schedule GSLD profile. LLS sets no fixed rates, charges, or contract term: service is taken only under a customer specific Large Load Service Agreement, approved by the Commission, that sets the terms, rates, facilities, security, and cost recovery for that customer. FPUC states it has no customers currently meeting the 50 MW definition and that no facilities or generation are expected in 2027.

The facts

Regulator
Florida Public Service Commission
Docket number
20260148-EI
Type
Large load tariff
Utility
Florida Public Utilities Co
State
Florida
Filed
Oct 1, 2026
Status date
Oct 1, 2026
Large-load rules
Yes, for loads of 50 MW or more

Related cases and proceedings

In the record

  1. Utility case, Oct 1, 2026. Utility case filed: Petition by Florida Public Utilities Company to Implement a Large Load Service Tariff Florida Public Service Commission, 20260148-EI

Sources

  1. 1
    Petition by Florida Public Utilities Company to Implement a Large Load Service Tariff, Docket 20260148-EI (filed October 1, 2026)
    Florida Public Service Commission
    Tier 1 · Petition paras. 5-7 (50 MW single site; FPUC service areas) and para. 9 (Schedule LLS text: customer specific agreement, Commission approval, rates and terms in the agreement) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Petition by Florida Public Utilities Company to Implement a Large Load Service Tariff." Last activity 2026-10-01. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-fpuc-large-load-2026