Petition for rate increase by Florida Power & Light Company (creating Large Load Cost Recovery Schedules LLCS-1 and LLCS-2)

Where it stands: Decided as of Jan 29, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

LLCS-1 and LLCS-2 apply to customers with a minimum demand requirement of 50 MW or greater at one physical location with a minimum monthly load factor of 85 percent. Minimum term: 20 years including the ramp up period, with termination requiring two years advance written notice. During the ramp up period the minimum bill is 70 percent of the otherwise applicable minimum bill computed at 100 percent of the then-applicable contract demand; after the ramp up period the minimum bill is 70 percent of the bill computed at 100 percent of the then-applicable contract demand excluding the fuel clause. CIAC contributions offset facilities built specifically for the customer. LLCS-1 is limited to customers in an area where approval would not require FPL to secure added generation or transmission capacity, and the combined LLCS-1 and LLCS-2 customer group is capped at 3 GW.

The facts

Regulator
Florida Public Service Commission
Docket number
20250011-EI
Type
Rate case
Utility
Florida Power & Light Co
State
Florida
Filed
Feb 28, 2025
Status date
Jan 29, 2026
Large-load rules
Yes, for loads of 50 MW or more

Related cases and proceedings

In the record

  1. Utility case, Feb 28, 2025. Utility case filed: Petition for rate increase by Florida Power & Light Company (creating Large Load Cost Recovery Schedules LLCS-1 and LLCS-2) Florida Public Service Commission, 20250011-EI

Sources

  1. 1
    Florida Power and Light Company Compliance Filing Pursuant to Section 366.043, Florida Statutes, Docket 20260149-EI (filed October 1, 2026), Exhibit A reproducing the in-effect LLCS-1 and LLCS-2 tariff sheets
    Florida Public Service Commission
    Tier 1 · FPL filing of October 1, 2026, recital paragraphs (Docket 20250011-EI; Order No. PSC-2026-0022-SEI dated January 29, 2026; Section 366.043 created by Chapter 2025-208, Laws of Florida) and Attachment B, LLCS-1 and LLCS-2 sheets (50 MW, 85 percent load factor, 20 year term, 70 percent minimum bill, CIAC, zone limit, 3 GW cap) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Petition for rate increase by Florida Power & Light Company (creating Large Load Cost Recovery Schedules LLCS-1 and LLCS-2)." Last activity 2026-01-29. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-fpl-rate-case-llcs-2025