What it is
LLCS-1 and LLCS-2 apply to customers with a minimum demand requirement of 50 MW or greater at one physical location with a minimum monthly load factor of 85 percent. Minimum term: 20 years including the ramp up period, with termination requiring two years advance written notice. During the ramp up period the minimum bill is 70 percent of the otherwise applicable minimum bill computed at 100 percent of the then-applicable contract demand; after the ramp up period the minimum bill is 70 percent of the bill computed at 100 percent of the then-applicable contract demand excluding the fuel clause. CIAC contributions offset facilities built specifically for the customer. LLCS-1 is limited to customers in an area where approval would not require FPL to secure added generation or transmission capacity, and the combined LLCS-1 and LLCS-2 customer group is capped at 3 GW.
The facts
- Regulator
- Florida Public Service Commission
- Docket number
- 20250011-EI
- Type
- Rate case
- Utility
- Florida Power & Light Co
- State
- Florida
- Filed
- Feb 28, 2025
- Status date
- Jan 29, 2026
- Large-load rules
- Yes, for loads of 50 MW or more
Related cases and proceedings
- Utility commission · Pending before the commissionFlorida Power & Light Company’s Compliance Filing Pursuant to Section 366.043, Florida Statutes
- Utility commission · Pending before the commissionPetition by Florida Public Utilities Company to Implement a Large Load Service Tariff
- Utility commission · Pending before the commissionPetition for Approval of Large Load Customer Tariffs by Tampa Electric Company
- Utility commission · Replaced by a later decisionPetition for a limited proceeding to approve large load tariff by Duke Energy Florida, LLC
In the record
- Utility case, Feb 28, 2025. Utility case filed: Petition for rate increase by Florida Power & Light Company (creating Large Load Cost Recovery Schedules LLCS-1 and LLCS-2) Florida Public Service Commission, 20250011-EI
Sources
- 1Florida Power and Light Company Compliance Filing Pursuant to Section 366.043, Florida Statutes, Docket 20260149-EI (filed October 1, 2026), Exhibit A reproducing the in-effect LLCS-1 and LLCS-2 tariff sheets
Florida Public Service CommissionTier 1 · FPL filing of October 1, 2026, recital paragraphs (Docket 20250011-EI; Order No. PSC-2026-0022-SEI dated January 29, 2026; Section 366.043 created by Chapter 2025-208, Laws of Florida) and Attachment B, LLCS-1 and LLCS-2 sheets (50 MW, 85 percent load factor, 20 year term, 70 percent minimum bill, CIAC, zone limit, 3 GW cap) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Petition for rate increase by Florida Power & Light Company (creating Large Load Cost Recovery Schedules LLCS-1 and LLCS-2)." Last activity 2026-01-29. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-fpl-rate-case-llcs-2025