Utility commission

Petition for a limited proceeding to approve large load tariff by Duke Energy Florida, LLC

Where it stands: Replaced by a later decision as of Apr 27, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

As proposed in 2025: large load customer defined as at least 100 MW at an initial or expanded delivery point; rates were the otherwise applicable tariff rates plus costs to serve the large load customer, requiring a minimum electrical service agreement under the Large Load Cost Recovery methodology; for combined delivery points no single point below 25 MW counted.

The facts

Regulator
Florida Public Service Commission
Docket number
20250113-EI
Type
Large load tariff
Utility
Duke Energy Florida, LLC
State
Florida
Filed
Sep 5, 2025
Status date
Apr 27, 2026
Large-load rules
Yes, for loads of 100 MW or more

Related cases and proceedings

In the record

  1. Utility case, Sep 5, 2025. Utility case filed: Petition for a limited proceeding to approve large load tariff by Duke Energy Florida, LLC Florida Public Service Commission, 20250113-EI

Sources

  1. 1
    Order No. PSC-2026-0120-PCO-EI (May 5, 2026), Case Background for Docket 20250113-EI
    Florida Public Service Commission
    Tier 1 · Order No. PSC-2026-0375-FOF-EI, rental terms paras. 1-10 (docket opening September 5, 2025; suspension October 7, 2025; abeyance March 19, 2026; withdrawal emails April 20, 2026; docket closed April 27, 2026) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Petition for a limited proceeding to approve large load tariff by Duke Energy Florida, LLC." Last activity 2026-04-27. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-duke-fl-large-load-2025