Utility commission
Petition for a limited proceeding to approve large load tariff by Duke Energy Florida, LLC (Section 366.043 refiling)
Where it stands: Pending before the commission as of Nov 3, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
Refiled package: a Large Load Customer Program (LLCP) and a Large Load Service Agreement (LLCA) for new or expanded loads of 50 MW or more, with no new rate; initial service is billed under Schedules GSD-1 and GSDT-1. Facilities costs are recovered in the next base rate case (target effective date January 1, 2028) or a standalone recovery filing; staff’s recommended modification guarantees facilities cost recovery and sets financial security at two months of minimum billing amounts, with a default right to suspend service; staff also recommended barring service to any entity designated as a covered person under 10 CFR Part 810.3. The exact minimum term and minimum billing percentage figures in Duke’s 2026 petition text were not read in this sweep (gap logged).
The facts
- Regulator
- Florida Public Service Commission
- Docket number
- 20260064-EI
- Type
- Large load tariff
- Utility
- Duke Energy Florida, LLC
- State
- Florida
- Filed
- Apr 22, 2026
- Status date
- Nov 3, 2026
- Large-load rules
- Yes, for loads of 50 MW or more
Related cases and proceedings
- Utility commission · Pending before the commissionFlorida Power & Light Company’s Compliance Filing Pursuant to Section 366.043, Florida Statutes
- Utility commission · Pending before the commissionPetition by Florida Public Utilities Company to Implement a Large Load Service Tariff
- Utility commission · Pending before the commissionPetition for Approval of Large Load Customer Tariffs by Tampa Electric Company
- Utility commission · Replaced by a later decisionPetition for a limited proceeding to approve large load tariff by Duke Energy Florida, LLC
- Utility commission · DecidedPetition for rate increase by Florida Power & Light Company (creating Large Load Cost Recovery Schedules LLCS-1 and LLCS-2)
In the record
- Utility case, Apr 22, 2026. Utility case filed: Petition for a limited proceeding to approve large load tariff by Duke Energy Florida, LLC (Section 366.043 refiling) Florida Public Service Commission, 20260064-EI
Sources
- 1Commission Vote Sheet, Item 3, Docket 20260064-EI (November 3, 2026)
Florida Public Service CommissionTier 1 · Vote sheet, Docket No. 20260064-EI (filed April 22, 2026; November 3, 2026 vote: Issue 1A denied as filed with leave to refile; Issues 1C, 1D, 1E, 1, 2, 3, 4 moot; Issue 5 approved, docket remains open) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Petition for a limited proceeding to approve large load tariff by Duke Energy Florida, LLC (Section 366.043 refiling)." Last activity 2026-11-03. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-duke-fl-large-load-2026