In effect as of Jul 1, 2025. The official record says: Approved by Governor; Chapter No. 2025-208.

  1. Filed (done)
  2. In committee (done)
  3. Passed one chamber (done)
  4. Passed both chambers (done)
  5. Signed into law (done)
  6. In effect (current stage)

What it does

  • Sunset

    Applies to: data center sales tax exemption certificates in Florida (Florida)

    Starts: 2025-08-01. Ends: 2037-06-30.

    “After June 30, 2037, the department may not issue a temporary tax exemption certificate pursuant to this paragraph.”

    Section 46, s. 212.08(5)(r), Florida Statutes

  • Definition

    Applies to: data centers claiming the sales tax exemption in Florida (Florida)

    Starts: 2025-08-01.

    “'Critical IT load' means that portion of electric power capacity, expressed in terms of megawatts, which is reserved solely for owners or tenants of a data center to operate their computer server equipment. The term does not include any ancillary load for cooling, lighting, common areas, or other equipment.”

    Section 46, s. 212.08(5)(r), Florida Statutes

  • Tax exemption · threshold 100 MW

    Applies to: data centers claiming the sales tax exemption in Florida (Florida)

    Starts: 2025-08-01.

    “To be eligible for the exemption provided by this paragraph, the data center's owners and tenants must make a cumulative capital investment of $150 million or more for the data center and the data center must have a critical IT load of 100 megawatts or higher and a critical IT load of 1 megawatt or higher dedicated to each individual owner or tenant within the data center. Each of these requirements must be satisfied no later than 5 years after the commencement of construction of the data center.”

    Section 46, s. 212.08(5)(r), Florida Statutes

  • Tax exemption

    Applies to: data center property in Florida (Florida)

    Starts: 2025-08-01.

    “Data center property is exempt from the tax imposed by this chapter, except for the tax imposed by s. 212.031.”

    Section 46, s. 212.08(5)(r), Florida Statutes

Who it touches (12)

Projects this may apply to, from the bill's own place and size rules. Each says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Auburndale Technology Center

    The act covers data centers whose owners and tenants make a cumulative capital investment of $150 million or more and reach a critical IT load of 100 megawatts or higher, with 1 megawatt or more per owner or tenant, no later than five years after construction begins, for the sales tax exemption; this project has 700 MW on record (not stated), but the project's cumulative capital investment and its critical IT load is not on record.

    “To be eligible for the exemption provided by this paragraph, the data center's owners and tenants must make a cumulative capital investment of $150 million or more for the data center and the data center must have a critical IT load of 100 megawatts or higher and a critical IT load of 1 megawatt or higher dedicated to each individual owner or tenant within the data center. Each of these requirements must be satisfied no later than 5 years after the commencement of construction of the data center.” (Section 46, s. 212.08(5)(r), Florida Statutes)

    Rule checks: Project is in Florida; 700 MW on record (not stated), threshold 100 MW (Section 46, s. 212.08(5)(r), Florida Statutes). Still to check: dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Cologix LAK1 (Lakeland)

    The act covers data centers whose owners and tenants make a cumulative capital investment of $150 million or more and reach a critical IT load of 100 megawatts or higher, with 1 megawatt or more per owner or tenant, no later than five years after construction begins, for the sales tax exemption; this project has no capacity figure on record, but the project's cumulative capital investment and its critical IT load is not on record. Status part: the bill's status (Approved by Governor; Chapter No. 2025-208) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “To be eligible for the exemption provided by this paragraph, the data center's owners and tenants must make a cumulative capital investment of $150 million or more for the data center and the data center must have a critical IT load of 100 megawatts or higher and a critical IT load of 1 megawatt or higher dedicated to each individual owner or tenant within the data center. Each of these requirements must be satisfied no later than 5 years after the commencement of construction of the data center.” (Section 46, s. 212.08(5)(r), Florida Statutes)

    Rule checks: Project is in Florida. Still to check: size: unknown, dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026DCIP Group data center (Roan Road, DeSoto County)

    The act covers data centers whose owners and tenants make a cumulative capital investment of $150 million or more and reach a critical IT load of 100 megawatts or higher, with 1 megawatt or more per owner or tenant, no later than five years after construction begins, for the sales tax exemption; this project has no capacity figure on record, but the project's cumulative capital investment and its critical IT load is not on record.

    “To be eligible for the exemption provided by this paragraph, the data center's owners and tenants must make a cumulative capital investment of $150 million or more for the data center and the data center must have a critical IT load of 100 megawatts or higher and a critical IT load of 1 megawatt or higher dedicated to each individual owner or tenant within the data center. Each of these requirements must be satisfied no later than 5 years after the commencement of construction of the data center.” (Section 46, s. 212.08(5)(r), Florida Statutes)

    Rule checks: Project is in Florida. Still to check: size: unknown, dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty MIA10 (Miami)

    The act covers data centers whose owners and tenants make a cumulative capital investment of $150 million or more and reach a critical IT load of 100 megawatts or higher, with 1 megawatt or more per owner or tenant, no later than five years after construction begins, for the sales tax exemption; this project has no capacity figure on record, but the project's cumulative capital investment and its critical IT load is not on record. Status part: the bill's status (Approved by Governor; Chapter No. 2025-208) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “To be eligible for the exemption provided by this paragraph, the data center's owners and tenants must make a cumulative capital investment of $150 million or more for the data center and the data center must have a critical IT load of 100 megawatts or higher and a critical IT load of 1 megawatt or higher dedicated to each individual owner or tenant within the data center. Each of these requirements must be satisfied no later than 5 years after the commencement of construction of the data center.” (Section 46, s. 212.08(5)(r), Florida Statutes)

    Rule checks: Project is in Florida. Still to check: size: unknown, dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix MI1 (Miami)

    The act covers data centers whose owners and tenants make a cumulative capital investment of $150 million or more and reach a critical IT load of 100 megawatts or higher, with 1 megawatt or more per owner or tenant, no later than five years after construction begins, for the sales tax exemption; this project has no capacity figure on record, but the project's cumulative capital investment and its critical IT load is not on record. Status part: the bill's status (Approved by Governor; Chapter No. 2025-208) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “To be eligible for the exemption provided by this paragraph, the data center's owners and tenants must make a cumulative capital investment of $150 million or more for the data center and the data center must have a critical IT load of 100 megawatts or higher and a critical IT load of 1 megawatt or higher dedicated to each individual owner or tenant within the data center. Each of these requirements must be satisfied no later than 5 years after the commencement of construction of the data center.” (Section 46, s. 212.08(5)(r), Florida Statutes)

    Rule checks: Project is in Florida. Still to check: size: unknown, dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix MI2 (Miami)

    The act covers data centers whose owners and tenants make a cumulative capital investment of $150 million or more and reach a critical IT load of 100 megawatts or higher, with 1 megawatt or more per owner or tenant, no later than five years after construction begins, for the sales tax exemption; this project has no capacity figure on record, but the project's cumulative capital investment and its critical IT load is not on record. Status part: the bill's status (Approved by Governor; Chapter No. 2025-208) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “To be eligible for the exemption provided by this paragraph, the data center's owners and tenants must make a cumulative capital investment of $150 million or more for the data center and the data center must have a critical IT load of 100 megawatts or higher and a critical IT load of 1 megawatt or higher dedicated to each individual owner or tenant within the data center. Each of these requirements must be satisfied no later than 5 years after the commencement of construction of the data center.” (Section 46, s. 212.08(5)(r), Florida Statutes)

    Rule checks: Project is in Florida. Still to check: size: unknown, dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix MI3 (Miami)

    The act covers data centers whose owners and tenants make a cumulative capital investment of $150 million or more and reach a critical IT load of 100 megawatts or higher, with 1 megawatt or more per owner or tenant, no later than five years after construction begins, for the sales tax exemption; this project has no capacity figure on record, but the project's cumulative capital investment and its critical IT load is not on record. Status part: the bill's status (Approved by Governor; Chapter No. 2025-208) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “To be eligible for the exemption provided by this paragraph, the data center's owners and tenants must make a cumulative capital investment of $150 million or more for the data center and the data center must have a critical IT load of 100 megawatts or higher and a critical IT load of 1 megawatt or higher dedicated to each individual owner or tenant within the data center. Each of these requirements must be satisfied no later than 5 years after the commencement of construction of the data center.” (Section 46, s. 212.08(5)(r), Florida Statutes)

    Rule checks: Project is in Florida. Still to check: size: unknown, dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix MI6 (Miami)

    The act covers data centers whose owners and tenants make a cumulative capital investment of $150 million or more and reach a critical IT load of 100 megawatts or higher, with 1 megawatt or more per owner or tenant, no later than five years after construction begins, for the sales tax exemption; this project has no capacity figure on record, but the project's cumulative capital investment and its critical IT load is not on record. Status part: the bill's status (Approved by Governor; Chapter No. 2025-208) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “To be eligible for the exemption provided by this paragraph, the data center's owners and tenants must make a cumulative capital investment of $150 million or more for the data center and the data center must have a critical IT load of 100 megawatts or higher and a critical IT load of 1 megawatt or higher dedicated to each individual owner or tenant within the data center. Each of these requirements must be satisfied no later than 5 years after the commencement of construction of the data center.” (Section 46, s. 212.08(5)(r), Florida Statutes)

    Rule checks: Project is in Florida. Still to check: size: unknown, dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Fort Meade data center campus (Project Stonebridge)

    The act covers data centers whose owners and tenants make a cumulative capital investment of $150 million or more and reach a critical IT load of 100 megawatts or higher, with 1 megawatt or more per owner or tenant, no later than five years after construction begins, for the sales tax exemption; this project has 1,200 MW announced on record, but the project's cumulative capital investment and its critical IT load is not on record.

    “To be eligible for the exemption provided by this paragraph, the data center's owners and tenants must make a cumulative capital investment of $150 million or more for the data center and the data center must have a critical IT load of 100 megawatts or higher and a critical IT load of 1 megawatt or higher dedicated to each individual owner or tenant within the data center. Each of these requirements must be satisfied no later than 5 years after the commencement of construction of the data center.” (Section 46, s. 212.08(5)(r), Florida Statutes)

    Rule checks: Project is in Florida; 1,200 MW on record (announced), threshold 100 MW (Section 46, s. 212.08(5)(r), Florida Statutes). Still to check: dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026NextNRG Nassau County data center site

    The act covers data centers whose owners and tenants make a cumulative capital investment of $150 million or more and reach a critical IT load of 100 megawatts or higher, with 1 megawatt or more per owner or tenant, no later than five years after construction begins, for the sales tax exemption; this project has no capacity figure on record, but the project's cumulative capital investment and its critical IT load is not on record.

    “To be eligible for the exemption provided by this paragraph, the data center's owners and tenants must make a cumulative capital investment of $150 million or more for the data center and the data center must have a critical IT load of 100 megawatts or higher and a critical IT load of 1 megawatt or higher dedicated to each individual owner or tenant within the data center. Each of these requirements must be satisfied no later than 5 years after the commencement of construction of the data center.” (Section 46, s. 212.08(5)(r), Florida Statutes)

    Rule checks: Project is in Florida. Still to check: size: unknown, dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Project Tango (Central Park Commerce Center)

    The act covers data centers whose owners and tenants make a cumulative capital investment of $150 million or more and reach a critical IT load of 100 megawatts or higher, with 1 megawatt or more per owner or tenant, no later than five years after construction begins, for the sales tax exemption; this project has no capacity figure on record, but the project's cumulative capital investment and its critical IT load is not on record.

    “To be eligible for the exemption provided by this paragraph, the data center's owners and tenants must make a cumulative capital investment of $150 million or more for the data center and the data center must have a critical IT load of 100 megawatts or higher and a critical IT load of 1 megawatt or higher dedicated to each individual owner or tenant within the data center. Each of these requirements must be satisfied no later than 5 years after the commencement of construction of the data center.” (Section 46, s. 212.08(5)(r), Florida Statutes)

    Rule checks: Project is in Florida. Still to check: size: unknown, dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026QTS Miami

    The act covers data centers whose owners and tenants make a cumulative capital investment of $150 million or more and reach a critical IT load of 100 megawatts or higher, with 1 megawatt or more per owner or tenant, no later than five years after construction begins, for the sales tax exemption; this project has no capacity figure on record, but the project's cumulative capital investment and its critical IT load is not on record. Status part: the bill's status (Approved by Governor; Chapter No. 2025-208) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “To be eligible for the exemption provided by this paragraph, the data center's owners and tenants must make a cumulative capital investment of $150 million or more for the data center and the data center must have a critical IT load of 100 megawatts or higher and a critical IT load of 1 megawatt or higher dedicated to each individual owner or tenant within the data center. Each of these requirements must be satisfied no later than 5 years after the commencement of construction of the data center.” (Section 46, s. 212.08(5)(r), Florida Statutes)

    Rule checks: Project is in Florida. Still to check: size: unknown, dates: not checked, who it covers: not checked

Other projects we track in Florida (5), not affected

Who acted

  • SponsorWays & Means CommitteeHouse

Timeline

Every official action on record, oldest first. An action that moved the bill to a new stage names that stage.

  1. Signed by Officers and presented to Governor
  2. Approved by GovernorStage: Signed into law
  3. Chapter No. 2025-208

More from Florida

Sources

  1. 1
    HB 7031 (2025) bill page and history
    Florida Senate
    Tier 1 · Open the source
  2. 2
    Chapter 2025-208, Laws of Florida (HB 7031)
    Florida Legislature
    Tier 1 · Open the source

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "HB 7031: Extends data center sales tax exemption, raises bar to 100 megawatts." Bill Watch. Updated 2026-11-12. Accessed 2026-11-29. https://datacenterfactcheck.org/policy/bills/fl-2025-hb-7031

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page