Fort Meade data center campus (Project Stonebridge)
Fort Meade,Polk County,FloridaApprovedFirst public 2025Filing entity: Fort Meade, LLC dba Fort Meade DC, LLCLast checked Nov 8, 2026
StonebridgeDeveloper
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Capacity
- Confirmed: First public date
- Still to confirm: Electric utility
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Fort Meade data center campus (Project Stonebridge) is an approved data center project in Fort Meade, Polk County, Florida. Stonebridge is named as developer. It was first public in 2025. It was announced at 1,200 MW.
Fort Meade data center campus (Project Stonebridge) is an approved data center project in Fort Meade, Polk County, Florida. Stonebridge is named as developer. It was announced at 1,200 MW. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Fort Meade, Polk County, Florida. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
The land, to scale
Timeline
- · New projectFirst public record of Fort Meade data center campus (Project Stonebridge)Approved
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Florida HB 7031: Extends data center sales tax exemption, raises bar to 100 megawatts
The act covers data centers whose owners and tenants make a cumulative capital investment of $150 million or more and reach a critical IT load of 100 megawatts or higher, with 1 megawatt or more per owner or tenant, no later than five years after construction begins, for the sales tax exemption; this project has 1,200 MW announced on record, but the project's cumulative capital investment and its critical IT load is not on record.
“To be eligible for the exemption provided by this paragraph, the data center's owners and tenants must make a cumulative capital investment of $150 million or more for the data center and the data center must have a critical IT load of 100 megawatts or higher and a critical IT load of 1 megawatt or higher dedicated to each individual owner or tenant within the data center. Each of these requirements must be satisfied no later than 5 years after the commencement of construction of the data center.” (Section 46, s. 212.08(5)(r), Florida Statutes)
Rule checks: Project is in Florida; 1,200 MW on record (announced), threshold 100 MW (Section 46, s. 212.08(5)(r), Florida Statutes). Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Florida SB 484: Makes large data centers pay full power and water costs
The water permitting rules cover large-scale data centers, a single location with a data center on site and an anticipated monthly peak load of 50 megawatts or more; this project has 1,200 MW announced on record, but the project's anticipated monthly peak load at a single location is not on record.
“'Large-scale data center' means a single location, with a data center on site, that has an anticipated monthly peak load of 50 megawatts or more, calculated as the highest average load over a 15-minute interval.” (s. 373.203(4), Florida Statutes)
Rule checks: Project is in Florida; 1,200 MW on record (announced), threshold 50 MW (s. 373.203(4), Florida Statutes). Still to check: dates: not checked, who it covers: not checked
Bills and laws in Florida
- SB 484 · In effect · Jul 1, 2026Makes large data centers pay full power and water costs
- HB 1517 · Died or failed · Mar 13, 2026Requires state approval and public disclosure for data center facilities
- SB 1118 · Died or failed · Mar 13, 2026Hides data center siting information from public records for a year
- HB 1007 · Died or failed · Mar 11, 2026Sets data center rules, replaced by Senate companion bill
- HB 7031 · In effect · Jul 1, 2025Extends data center sales tax exemption, raises bar to 100 megawatts
- SB 1264 · Died or failed · Jun 16, 2025Repeals expiration of the data center sales tax exemption
Who's involved
- DeveloperStonebridge
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is Fort Meade data center campus (Project Stonebridge)?
- Fort Meade data center campus (Project Stonebridge) is a data center project in Fort Meade, Polk County, Florida.
- Who is developing Fort Meade data center campus (Project Stonebridge)?
- Stonebridge is named as the developer of Fort Meade data center campus (Project Stonebridge).
- How big is Fort Meade data center campus (Project Stonebridge)?
- Fort Meade data center campus (Project Stonebridge) was announced at 1,200 MW of capacity. The site covers 1,261 acres.
- What stage is Fort Meade data center campus (Project Stonebridge)?
- Fort Meade data center campus (Project Stonebridge) is approved. It was first public in 2025.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Letter from Secretary J. Alex Kelly to Mayor Jaret Landon Williams, City of Fort Meade, April 15, 2026
Florida Department of CommerceTier 1 · Captured 2026-11-08 · Open the source - 2Fort Meade commissioner asks judge to dismiss recall campaign