SB 484: Makes large data centers pay full power and water costs

Official title: Data Centers

Official text

Draft research, not yet verified: traced to the official record by an AI research agent; an editor has not checked it yet.

Where it stands

In effect as of Jul 1, 2026. The official record says: Approved by Governor; Chapter No. 2026-65.

  1. Filed (done)
  2. In committee (done)
  3. Passed one chamber (done)
  4. Passed both chambers (done)
  5. Signed into law (done)
  6. In effect (current stage)

What it means for a household (draft rating)

Helps households. The act requires utility tariffs to make each large load customer bear its own full cost of service, with no shift to the general body of ratepayers.

"The minimum tariff and service requirements must reasonably ensure that each large load customer bears its own full cost of service and that such cost is not shifted to the general body of ratepayers."new s. 366.043(3)(a), F.S., enrolled text

We rate a bill as helping or costing households only when its own text says who pays or who is exempt. Otherwise it is unclear. This is a draft rating and has not been verified yet.

What it does

  • Disclosure

    Applies to: economic development project information relating to data centers (Florida)

    Starts: 2026-07-01.

    “This subparagraph does not apply to information described in subparagraph 1. relating to data centers.”

    Section amending s. 288.075(2)(a)2., Florida Statutes

  • Definition

    Applies to: data centers seeking water allocations in Florida (Florida)

    Starts: 2026-07-01.

    “'Data center' means a facility that primarily contains electronic equipment used to process, store, and transmit digital information, which may be: (a) A free-standing structure; or (b) A facility within a larger structure which uses environmental control equipment to maintain the proper conditions for the operation of electronic equipment.”

    s. 373.203(3), Florida Statutes

  • Effective date

    Applies to: the whole act (Florida)

    Starts: 2026-07-01.

    “Except as otherwise expressly provided in this act and except for this section, which shall take effect upon becoming a law, this act shall take effect July 1, 2026.”

    Section 8 of Chapter 2026-65

  • Service terms

    Applies to: public utilities and foreign entity customers in Florida (Florida)

    Starts: 2026-07-01.

    “A public utility may not knowingly provide electric service to a customer that would otherwise qualify as a large load customer if that customer is a foreign entity.”

    s. 366.043(7), Florida Statutes

  • Who pays for grid costs

    Applies to: large load customers of public utilities in Florida (Florida)

    Starts: 2026-07-01.

    “The minimum tariff and service requirements must reasonably ensure that each large load customer bears its own full cost of service and that such cost is not shifted to the general body of ratepayers. The risk of nonpayment of such costs may not be borne by the general body of ratepayers.”

    s. 366.043(3)(a), Florida Statutes

  • Definition · threshold 50 MW

    Applies to: large load customers of public utilities in Florida (Florida)

    Starts: 2026-07-01.

    “'Large load customer' means a customer with an anticipated monthly peak load of 50 megawatts or more, calculated as the highest average load over a 15-minute interval at a single location.”

    s. 366.043(2)(d), Florida Statutes

  • Definition · threshold 50 MW

    Applies to: large-scale data centers in Florida (Florida)

    Starts: 2026-07-01.

    “'Large-scale data center' means a single location, with a data center on site, that has an anticipated monthly peak load of 50 megawatts or more, calculated as the highest average load over a 15-minute interval.”

    s. 373.203(4), Florida Statutes

  • Preemption

    Applies to: local governments and large load customers in Florida (Florida)

    Starts: 2026-05-07.

    “Local governments shall maintain the authority to exercise the powers and responsibilities for comprehensive planning and land development regulation granted by law with respect to large load customers. A large load customer may not be considered an electric substation for the purposes of s. 163.3208.”

    Section 1, new s. 163.326(2), Florida Statutes

  • Service terms

    Applies to: customers of public utilities in Florida (Florida)

    Starts: 2026-07-01.

    “A customer may not separate an electrical load at a single location into multiple smaller connections to avoid being classified as a large load customer.”

    s. 366.043(4), Florida Statutes

  • Reporting duty

    Applies to: public utilities in Florida (Florida)

    Starts: 2026-10-01.

    “No later than October 1, 2026, each public utility shall file, for commission approval, a tariff that complies with this section.”

    s. 366.043(8), Florida Statutes

  • Service terms

    Applies to: large-scale data center water permit applicants in Florida (Florida)

    Starts: 2026-07-01.

    “may not issue a permit to a large-scale data center applicant for an allocation of water if the proposed use of the water is harmful to the water resources of the area or is prohibited by the applicable local government zoning regulations and comprehensive plan. A permit shall be issued to a large-scale data center applicant for an allocation of water if the applicant establishes that the proposed use of water: (a) Is a reasonable-beneficial use as defined in s. 373.019; (b) Will not interfere with any presently existing legal use of water; and (c) Is consistent with the public interest.”

    s. 373.262(2), Florida Statutes

Who it touches (12)

Projects this may apply to, from the bill's own place and size rules. Each says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Auburndale Technology Center

    The water permitting rules cover large-scale data centers, a single location with a data center on site and an anticipated monthly peak load of 50 megawatts or more; this project has 700 MW not stated on record, but the project's anticipated monthly peak load at a single location is not on record.

    “'Large-scale data center' means a single location, with a data center on site, that has an anticipated monthly peak load of 50 megawatts or more, calculated as the highest average load over a 15-minute interval.” (s. 373.203(4), Florida Statutes)

    Rule checks: Project is in Florida; 700 MW on record (not stated), threshold 50 MW (s. 373.203(4), Florida Statutes). Still to check: dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Cologix LAK1 (Lakeland)

    The act covers large load customers of public utilities, customers with an anticipated monthly peak load of 50 megawatts or more at a single location, who must bear their own full cost of service; this project has no capacity figure on record, but the project's anticipated monthly peak load at a single location is not on record. Status part: the bill's status (Approved by Governor; Chapter No. 2026-65) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “'Large load customer' means a customer with an anticipated monthly peak load of 50 megawatts or more, calculated as the highest average load over a 15-minute interval at a single location.” (s. 366.043(2)(d), Florida Statutes)

    Rule checks: Project is in Florida. Still to check: size: unknown, dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026DCIP Group data center (Roan Road, DeSoto County)

    The water permitting rules cover large-scale data centers, a single location with a data center on site and an anticipated monthly peak load of 50 megawatts or more; this project has no capacity figure on record, and the project's anticipated monthly peak load at a single location is not on record.

    “'Large-scale data center' means a single location, with a data center on site, that has an anticipated monthly peak load of 50 megawatts or more, calculated as the highest average load over a 15-minute interval.” (s. 373.203(4), Florida Statutes)

    Rule checks: Project is in Florida. Still to check: size: unknown, dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty MIA10 (Miami)

    The act covers large load customers of public utilities, customers with an anticipated monthly peak load of 50 megawatts or more at a single location, who must bear their own full cost of service; this project has no capacity figure on record, but the project's anticipated monthly peak load at a single location is not on record. Status part: the bill's status (Approved by Governor; Chapter No. 2026-65) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “'Large load customer' means a customer with an anticipated monthly peak load of 50 megawatts or more, calculated as the highest average load over a 15-minute interval at a single location.” (s. 366.043(2)(d), Florida Statutes)

    Rule checks: Project is in Florida. Still to check: size: unknown, dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix MI1 (Miami)

    The act covers large load customers of public utilities, customers with an anticipated monthly peak load of 50 megawatts or more at a single location, who must bear their own full cost of service; this project has no capacity figure on record, but the project's anticipated monthly peak load at a single location is not on record. Status part: the bill's status (Approved by Governor; Chapter No. 2026-65) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “'Large load customer' means a customer with an anticipated monthly peak load of 50 megawatts or more, calculated as the highest average load over a 15-minute interval at a single location.” (s. 366.043(2)(d), Florida Statutes)

    Rule checks: Project is in Florida. Still to check: size: unknown, dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix MI2 (Miami)

    The act covers large load customers of public utilities, customers with an anticipated monthly peak load of 50 megawatts or more at a single location, who must bear their own full cost of service; this project has no capacity figure on record, but the project's anticipated monthly peak load at a single location is not on record. Status part: the bill's status (Approved by Governor; Chapter No. 2026-65) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “'Large load customer' means a customer with an anticipated monthly peak load of 50 megawatts or more, calculated as the highest average load over a 15-minute interval at a single location.” (s. 366.043(2)(d), Florida Statutes)

    Rule checks: Project is in Florida. Still to check: size: unknown, dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix MI3 (Miami)

    The act covers large load customers of public utilities, customers with an anticipated monthly peak load of 50 megawatts or more at a single location, who must bear their own full cost of service; this project has no capacity figure on record, but the project's anticipated monthly peak load at a single location is not on record. Status part: the bill's status (Approved by Governor; Chapter No. 2026-65) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “'Large load customer' means a customer with an anticipated monthly peak load of 50 megawatts or more, calculated as the highest average load over a 15-minute interval at a single location.” (s. 366.043(2)(d), Florida Statutes)

    Rule checks: Project is in Florida. Still to check: size: unknown, dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix MI6 (Miami)

    The act covers large load customers of public utilities, customers with an anticipated monthly peak load of 50 megawatts or more at a single location, who must bear their own full cost of service; this project has no capacity figure on record, but the project's anticipated monthly peak load at a single location is not on record. Status part: the bill's status (Approved by Governor; Chapter No. 2026-65) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “'Large load customer' means a customer with an anticipated monthly peak load of 50 megawatts or more, calculated as the highest average load over a 15-minute interval at a single location.” (s. 366.043(2)(d), Florida Statutes)

    Rule checks: Project is in Florida. Still to check: size: unknown, dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Fort Meade data center campus (Project Stonebridge)

    The water permitting rules cover large-scale data centers, a single location with a data center on site and an anticipated monthly peak load of 50 megawatts or more; this project has 1,200 MW announced on record, but the project's anticipated monthly peak load at a single location is not on record.

    “'Large-scale data center' means a single location, with a data center on site, that has an anticipated monthly peak load of 50 megawatts or more, calculated as the highest average load over a 15-minute interval.” (s. 373.203(4), Florida Statutes)

    Rule checks: Project is in Florida; 1,200 MW on record (announced), threshold 50 MW (s. 373.203(4), Florida Statutes). Still to check: dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026NextNRG Nassau County data center site

    The water permitting rules cover large-scale data centers, a single location with a data center on site and an anticipated monthly peak load of 50 megawatts or more; this project has no capacity figure on record, and the project's anticipated monthly peak load at a single location is not on record.

    “'Large-scale data center' means a single location, with a data center on site, that has an anticipated monthly peak load of 50 megawatts or more, calculated as the highest average load over a 15-minute interval.” (s. 373.203(4), Florida Statutes)

    Rule checks: Project is in Florida. Still to check: size: unknown, dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Project Tango (Central Park Commerce Center)

    The water permitting rules cover large-scale data centers, a single location with a data center on site and an anticipated monthly peak load of 50 megawatts or more; this project has no capacity figure on record, and the project's anticipated monthly peak load at a single location is not on record.

    “'Large-scale data center' means a single location, with a data center on site, that has an anticipated monthly peak load of 50 megawatts or more, calculated as the highest average load over a 15-minute interval.” (s. 373.203(4), Florida Statutes)

    Rule checks: Project is in Florida. Still to check: size: unknown, dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026QTS Miami

    The act covers large load customers of public utilities, customers with an anticipated monthly peak load of 50 megawatts or more at a single location, who must bear their own full cost of service; this project has no capacity figure on record, but the project's anticipated monthly peak load at a single location is not on record. Status part: the bill's status (Approved by Governor; Chapter No. 2026-65) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.

    “'Large load customer' means a customer with an anticipated monthly peak load of 50 megawatts or more, calculated as the highest average load over a 15-minute interval at a single location.” (s. 366.043(2)(d), Florida Statutes)

    Rule checks: Project is in Florida. Still to check: size: unknown, dates: not checked, who it covers: not checked

Other projects we track in Florida (5), not affected

Who acted

  • CosponsorGaetzSenate
  • CosponsorYarboroughSenate
  • Primary sponsorAvilaSenate

Timeline

Every official action on record, oldest first. An action that moved the bill to a new stage names that stage.

  1. · SenateFiledStage: Filed
  2. · SenateIntroduced
  3. · SenateCS passed as amended; YEAS 37 NAYS 0Stage: Passed one chamber
  4. · HouseCS passed as amended; YEAS 92, NAYS 16Stage: Passed both chambers
  5. · SenateConcurred in 1 amendment(s) (383957); CS passed as amended; YEAS 31 NAYS 6
  6. Signed by Officers and presented to Governor
  7. Approved by GovernorStage: Signed into law
  8. Chapter No. 2026-65

More from Florida

Sources

  1. 1
    SB 484 (2026) bill page and history
    Florida Senate
    Tier 1 · Open the source
  2. 2
    Chapter 2026-65, Laws of Florida (SB 484)
    Florida Legislature
    Tier 1 · Open the source

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "SB 484: Makes large data centers pay full power and water costs." Bill Watch. Updated 2026-11-12. Accessed 2026-11-29. https://datacenterfactcheck.org/policy/bills/fl-2026-sb-484

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page