Data centers in Kansas City, Missouri

Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.

Data Center Fact Check tracks 12 data center projects in Kansas City, Missouri as of November 2026: 8 operating, 3 under construction and 1 approved, totaling about 858 MW announced where a figure is published.

Kansas City has 12 tracked data centers. Their announced capacity totals about 858 MW where a figure is published. Of those, 8 operating, 3 under construction and 1 approved. Every figure comes from the public record linked on this page.

12Data center projects we track

Data center projects in Kansas City

Who serves this place

  • Not collected yet.

More places in Jackson County

Kansas City is part of Jackson County.

Nearby places

Tax breaks and payments

  • Lambda AI Factory (Kansas City)

    Sales and use tax exemption, data storage centers (RSMo Section 144.810)

    Missouri DED states, in its release for this project, that Lambda will benefit from the Data Center Sales Tax Exemption Program.

    All tax records for Lambda AI Factory (Kansas City)
  • Edged Kansas City

    Sales and use tax exemption, data storage centers (RSMo Section 144.810)

    Missouri DED states, in its release for this facility opening: "For this expansion, Edged will benefit from the Data Center Sales Tax Exemption Program."

    All tax records for Edged Kansas City

Court cases and commission dockets in Missouri (3)

Bills and laws in Missouri

Open Bill Watch

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Questions people ask

How many data centers are in Kansas City?
Data Center Fact Check tracks 12 data center projects in Kansas City as of November 2026. Of those, 8 operating, 3 under construction and 1 approved.
What is the biggest data center in Kansas City?
By announced capacity, the biggest data center in Kansas City is Google data center campus, Project Mica (Kansas City), announced at 700 MW. It is under construction.
How much power do data centers in Kansas City use?
The 12 projects tracked in Kansas City have announced about 858 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.

Sources

  1. 1
    Lambda to establish AI factory facility in Kansas City
    Missouri Department of Economic Development
    Tier 1 · Open the source
  2. 2
    Edged Data Centers opens new data center in Kansas City, investing more than $143 million
    Missouri Department of Economic Development
    Tier 1 · Open the source

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Kansas City." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-mo-kansas-city

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page