Data centers in Missouri
Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.
Data Center Fact Check tracks 19 data center projects in Missouri as of November 2026: 9 operating, 5 approved and 4 under construction, totaling about 2,808 MW announced where a figure is published.
Missouri has 19 tracked data centers. Their announced capacity totals about 2,808 MW where a figure is published. Of those, 9 operating, 5 approved and 4 under construction. Every project we track here is listed below, with the public records behind it. Every figure comes from the public record linked on this page.
Data center projects in Missouri
- Amazon data center campus, Montgomery County
AnnouncedMontgomery City
- CRG data center, Festus
ApprovedFestus600 MW announced
- Data center at the former Famous-Barr warehouse (Armory Innovation District, St. Louis)
ApprovedSt. Louis
- Edged Kansas City
OperatingKansas City26 MW announced
- Google data center campus, Project Mica (Kansas City)
Under constructionKansas City700 MW announced
- Google data center, Hunt Midwest Business Center (Kansas City)
Under constructionKansas City
- Google data center, New Florence (Montgomery County)
ApprovedNew Florence
- Iron Mountain Data Centers Iron Mountain Kansas City (Kansas City; underground)
OperatingKansas City4 MW announced
- Iron Mountain KCM-1
OperatingKansas City4 MW announced
- Lambda AI Factory (Kansas City)
Under constructionKansas City24 MW announced
- LightEdge Kansas City (SubTropolis)
OperatingKansas City
- Meta data center, Kansas City (Golden Plains Technology Park)
OperatingKansas City
- Metrobloks and Lincoln Property data center campus, Liberty
ApprovedLiberty150 MW announced
- Nebius AI factory, Independence
Under constructionIndependence1,200 MW announced
- Netrality KC1 (1102 Grand)
OperatingKansas City
- NOCIX North Kansas City Campus
OperatingNorth Kansas City
- Patmos Kansas City (former Kansas City Star printing plant)
OperatingKansas City100 MW announced
- Project Kestrel data center campus (KCI-29, Kansas City)
ApprovedKansas City
- TierPoint Kansas City (KCM)
OperatingKansas City
Who serves this place
- Not collected yet.
Counties and cities in Missouri
Counties
- Clay County6 data center projects tracked
- Jackson County5 data center projects tracked
- Jefferson County1 data center project tracked
- Montgomery County2 data center projects tracked
- Platte County3 data center projects tracked
- St. Louis city1 data center project tracked
Cities and towns
- Kansas City12 data center projects tracked
- Festus1 data center project tracked
- Independence1 data center project tracked
- Liberty1 data center project tracked
- Montgomery City1 data center project tracked
- New Florence1 data center project tracked
- North Kansas City1 data center project tracked
- St. Louis1 data center project tracked
Tax breaks and payments
Sales and use tax exemption, data storage centers (RSMo Section 144.810)
Project taxpayers for a certified data storage center project are exempt from 100 percent of the state and local sales and use taxes on all machinery, equipment, computers, electrical energy, gas, water, and other utilities including telecommunication and internet services used in the facility, and on tangible personal property purchased for construction of the facility. For a new facility the project period runs up to 15 years from the Department of Economic Development's conditional approval; for an expanding facility, up to 10 years, with the exemption on utilities applying to the increase in expenditures. The total exemption is capped at the projected net fiscal benefit to the state over a ten-year period, as the Department determines using the REMI model. The Department issues exemption certificates year by year once thresholds are verified.
2026 · Nebius AI factory, Independence
Chapter 100 industrial development incentive plan (City of Independence, Missouri)
Under the approved agreement and tax incentive package, Nebius will make payments in lieu of taxes (PILOT) projected to deliver over $650 million to the city, local school districts, and other taxing jurisdictions over the 20-year term.
All tax records for Nebius AI factory, IndependenceLambda AI Factory (Kansas City)
Sales and use tax exemption, data storage centers (RSMo Section 144.810)
Missouri DED states, in its release for this project, that Lambda will benefit from the Data Center Sales Tax Exemption Program.
All tax records for Lambda AI Factory (Kansas City)Edged Kansas City
Sales and use tax exemption, data storage centers (RSMo Section 144.810)
Missouri DED states, in its release for this facility opening: "For this expansion, Edged will benefit from the Data Center Sales Tax Exemption Program."
All tax records for Edged Kansas City
Recent cases and dockets in Missouri
- Utility commission · DecidedIn the matter of Evergy Metro, Inc. and Evergy Missouri West, Inc. large load tariffs (Large Load Power Service)
- Utility commission · DecidedIn the matter of Evergy Metro, Inc. and Evergy Missouri West, Inc. large load tariffs (Large Load Power Service)
- Utility commission · Pending before the commissionApplication of Union Electric Company d/b/a Ameren Missouri for approval of new or modified tariffs for service to large load customers (Large Load Customer Rate Plan)
Bills and laws in Missouri
- HB 3369 · Died or failed · May 15, 2026One year ban on data center permits in St. Louis
- HB 3362 · Died or failed · May 15, 2026New rules for industrial utility customers
- HB 3390 · Died or failed · May 15, 2026State siting board for hyperscale data centers
- HB 2239 · Died or failed · May 15, 2026AI data center environmental accountability act
- HB 3364 · Died or failed · May 15, 2026New rules for industrial utility customers
- SB 4 · Signed into law · Apr 9, 2025Utility law requiring large load customers to cover their costs
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Questions people ask
- How many data centers are in Missouri?
- Data Center Fact Check tracks 19 data center projects in Missouri as of November 2026. Of those, 9 operating, 5 approved and 4 under construction.
- What is the biggest data center in Missouri?
- By announced capacity, the biggest data center in Missouri is Nebius AI factory, Independence, announced at 1,200 MW. It is under construction.
- How much power do data centers in Missouri use?
- The 19 projects tracked in Missouri have announced about 2,808 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
- 1Revised Statutes of Missouri, Section 144.810 (Data storage centers, exemption from sales and use tax)
Revisor of Statutes, State of MissouriTier 1 · Open the source - 2Data Center Sales Tax Exemption Program (program summary)
Missouri Department of Economic Development / Missouri PartnershipTier 2 · Open the source - 3Nebius secures approval for its first gigawatt-scale AI factory
Nebius (Business Wire)Tier 4 · Open the source - 4Lambda to establish AI factory facility in Kansas City
Missouri Department of Economic DevelopmentTier 1 · Open the source - 5Edged Data Centers opens new data center in Kansas City, investing more than $143 million
Missouri Department of Economic DevelopmentTier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Missouri." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-mo
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page