Nebius AI factory, Independence

Independence,Jackson County,MissouriUnder constructionFirst public 2025Last checked Nov 10, 2026

NebiusDeveloper and operatorIndependence Power & Light (IPL)Electric utility

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

5 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: First public date
  • Still to confirm: Electric utility
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Nebius AI factory, Independence is a under-construction data center project in Independence, Jackson County, Missouri. Nebius is named as operator. It was first public in 2025. It was announced at 1,200 MW.

Nebius AI factory, Independence is an under-construction data center project in Independence, Jackson County, Missouri. Nebius is named as operator. It was announced at 1,200 MW. 5 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Independence, Jackson County, Missouri. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

1,200 MWAnnounced capacity
2Public records we have found
1Tax agreement on record

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Aerial view of Nebius AI factory, Independence in Independence, Jackson County, Missouri, captured 2022
Aerial image, USDA National Agriculture Imagery Program, via the USGS National Map, Public domain (USDA NAIP), captured 2022Aerial images can be older than the campus. This one shows what was on the ground when it was taken.Source: USDA National Agriculture Imagery Program, via the USGS National MapLicense: Public domain (USDA NAIP)
Site-level positionPin placed from the position we have on file, inside Jackson County, Missouri.See every project on the map

The land, to scale

One football field
400 acres, about 303 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · DecisionCity of Independence, Missouri (City Council): approved for Nebius AI factory, Independence
  2. · Tax dealTax agreement approved: Chapter 100 industrial development incentive plan (city of independence, missouri) for NebiusUnder the approved agreement and tax incentive package, Nebius will make payments in lieu of taxes (PILOT) projected to deliver over $650 million to the city, local school districts, and other taxing jurisdictions over the 20-year term.
  3. · New projectFirst public record of Nebius AI factory, IndependenceUnder construction

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Missouri SB 4: Utility law requiring large load customers to cover their costs

    The act covers customers of an electrical corporation serving more than two hundred fifty thousand customers who are reasonably projected to have above an annual peak demand of one hundred megawatts or more; this project has 1,200 MW on record (not stated), but the project's projected annual peak demand and the customer count of its serving electrical corporation is not on record.

    “Each electrical corporation providing electric service to more than two hundred fifty thousand customers shall develop and submit to the commission schedules to include in the electrical corporation's service tariff applicable to customers who are reasonably projected to have above an annual peak demand of one hundred megawatts or more. The schedules should reasonably ensure such customers' rates will reflect the customers' representative share of the costs incurred to serve the customers and prevent other customer classes' rates from reflecting any unjust or unreasonable costs arising from service to such customers.” (Section 393.130, subsection 7, TAFP text (p. 40))

    Rule checks: Project is in Missouri; 1,200 MW on record (not stated), threshold 100 MW (Section 393.130, subsection 7, TAFP text (p. 40)). Still to check: who it covers: not checked

Bills and laws in Missouri

Open Bill Watch

Who's involved

Power

Capacity, as announced or filed

  • 1,200 MW · Full build-outMar 2026 · what the figure measures is not stated

From the filings

Numbers stated in permits, agreements, and decisions, as printed. Each links to the filing.

  • City of Independence, Missouri (City Council)

    Stated in the filing
    approximately 1,200 construction jobs and around 130 permanent positions at full operation
    Stated in the filing
    400 acres

Public records

2 records found so far. 7 kinds of record are still being collected.

See every record

Questions people ask

Where is Nebius AI factory, Independence?
Nebius AI factory, Independence is a data center project in Independence, Jackson County, Missouri.
Who operates Nebius AI factory, Independence?
Nebius is named as the operator of Nebius AI factory, Independence.
How big is Nebius AI factory, Independence?
Nebius AI factory, Independence was announced at 1,200 MW of capacity. The site covers 400 acres.
What stage is Nebius AI factory, Independence?
Nebius AI factory, Independence is under construction. It was first public in 2025.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Nebius secures approval for its first gigawatt-scale AI factory
    Nebius (Business Wire)
    Tier 4 · Captured 2026-11-08 · Open the source
  2. 2
    Nebius AI Factory, Independence, Missouri (project page)
    Nebius
    Tier 4 · Captured 2026-11-08 · Open the source
  3. 3
    U.S. Census Geocoder (batch geographies endpoint)
    U.S. Census Bureau
    Tier 1 · Captured 2026-11-11 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page