Google data center, New Florence (Montgomery County)

New Florence,Montgomery County,MissouriApprovedFirst public 2026Filing entity: Spade Property Owners, LLCLast checked Nov 8, 2026

Related DigitalDeveloperGoogleDeveloper and operatorAmeren MissouriElectric utility

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

5 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Electric utility
  • Confirmed: First public date
  • Still to confirm: Capacity
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Google data center, New Florence (Montgomery County) is an approved data center project in New Florence, Montgomery County, Missouri. Google is named as operator. It was first public in 2026. No site capacity figure is published for this project.

Google data center, New Florence (Montgomery County) is an approved data center project in New Florence, Montgomery County, Missouri. Google is named as operator. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in New Florence, Montgomery County, Missouri. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

1Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Montgomery County, Missouri.See every project on the map

Timeline

  1. · New projectFirst public record of Google data center, New Florence (Montgomery County)Approved

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Missouri SB 4: Utility law requiring large load customers to cover their costs

    The act covers customers of an electrical corporation serving more than two hundred fifty thousand customers who are reasonably projected to have above an annual peak demand of one hundred megawatts or more; this project has no capacity figure on record, but the project's projected annual peak demand and the customer count of its serving electrical corporation is not on record.

    “Each electrical corporation providing electric service to more than two hundred fifty thousand customers shall develop and submit to the commission schedules to include in the electrical corporation's service tariff applicable to customers who are reasonably projected to have above an annual peak demand of one hundred megawatts or more. The schedules should reasonably ensure such customers' rates will reflect the customers' representative share of the costs incurred to serve the customers and prevent other customer classes' rates from reflecting any unjust or unreasonable costs arising from service to such customers.” (Section 393.130, subsection 7, TAFP text (p. 40))

    Rule checks: Project is in Missouri. Still to check: size: unknown, who it covers: not checked

Bills and laws in Missouri

Open Bill Watch

Who's involved

Public records

1 records found so far. 8 kinds of record are still being collected.

See every record

Questions people ask

Where is Google data center, New Florence (Montgomery County)?
Google data center, New Florence (Montgomery County) is a data center project in New Florence, Montgomery County, Missouri.
Who operates Google data center, New Florence (Montgomery County)?
Google is named as the operator of Google data center, New Florence (Montgomery County).
What stage is Google data center, New Florence (Montgomery County)?
Google data center, New Florence (Montgomery County) is approved. It was first public in 2026.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Application and Request for Variance, File No. ET-2025-0184 (Union Electric Company d/b/a Ameren Missouri, Large Load Customer Rate Plan)
    Missouri Public Service Commission (EFIS filing)
    Tier 1 · Captured 2026-11-08 · Open the source
  2. 2
    Staff's Brief Regarding Ameren Missouri's Variance Request, File No. ET-2025-0184
    Missouri Public Service Commission (EFIS filing)
    Tier 1 · Captured 2026-11-08 · Open the source
  3. 3
    Missouri Secures $15 Billion Investment from Google in Montgomery County
    Office of the Governor of Missouri
    Tier 1 · Captured 2026-11-08 · Open the source
  4. 4
    Direct Testimony of Robert B. Dixon, File No. EA-2026-0183
    Missouri Public Service Commission (EFIS)
    Tier 1 · Captured 2026-11-08 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page