Project File
Google data center, New Florence (Montgomery County)
New Florence,Montgomery County,MissouriApprovedFirst public 2026Filing entity: Spade Property Owners, LLCLast checked Nov 8, 2026
Related DigitalDeveloperGoogleDeveloper and operatorAmeren MissouriElectric utility
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Electric utility
- Confirmed: First public date
- Still to confirm: Capacity
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Google data center, New Florence (Montgomery County) is an approved data center project in New Florence, Montgomery County, Missouri. Google is named as operator. It was first public in 2026. No site capacity figure is published for this project.
Google data center, New Florence (Montgomery County) is an approved data center project in New Florence, Montgomery County, Missouri. Google is named as operator. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in New Florence, Montgomery County, Missouri. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Timeline
- · New projectFirst public record of Google data center, New Florence (Montgomery County)Approved
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Missouri SB 4: Utility law requiring large load customers to cover their costs
The act covers customers of an electrical corporation serving more than two hundred fifty thousand customers who are reasonably projected to have above an annual peak demand of one hundred megawatts or more; this project has no capacity figure on record, but the project's projected annual peak demand and the customer count of its serving electrical corporation is not on record.
“Each electrical corporation providing electric service to more than two hundred fifty thousand customers shall develop and submit to the commission schedules to include in the electrical corporation's service tariff applicable to customers who are reasonably projected to have above an annual peak demand of one hundred megawatts or more. The schedules should reasonably ensure such customers' rates will reflect the customers' representative share of the costs incurred to serve the customers and prevent other customer classes' rates from reflecting any unjust or unreasonable costs arising from service to such customers.” (Section 393.130, subsection 7, TAFP text (p. 40))
Rule checks: Project is in Missouri. Still to check: size: unknown, who it covers: not checked
Bills and laws in Missouri
- HB 3369 · Died or failed · May 15, 2026One year ban on data center permits in St. Louis
- HB 3362 · Died or failed · May 15, 2026New rules for industrial utility customers
- HB 3390 · Died or failed · May 15, 2026State siting board for hyperscale data centers
- HB 2239 · Died or failed · May 15, 2026AI data center environmental accountability act
- HB 3364 · Died or failed · May 15, 2026New rules for industrial utility customers
- SB 4 · Signed into law · Apr 9, 2025Utility law requiring large load customers to cover their costs
Who's involved
- DeveloperRelated Digital
- Developer and operatorGoogle
- Electric utilityAmeren Missouri
Public records
1 records found so far. 8 kinds of record are still being collected.
See every recordCourt cases and commission dockets
- Utility commission · Pending before the commission · May 14, 2025Application of Union Electric Company d/b/a Ameren Missouri for approval of new or modified tariffs for service to large load customers (Large Load Customer Rate Plan)
Questions people ask
- Where is Google data center, New Florence (Montgomery County)?
- Google data center, New Florence (Montgomery County) is a data center project in New Florence, Montgomery County, Missouri.
- Who operates Google data center, New Florence (Montgomery County)?
- Google is named as the operator of Google data center, New Florence (Montgomery County).
- What stage is Google data center, New Florence (Montgomery County)?
- Google data center, New Florence (Montgomery County) is approved. It was first public in 2026.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Application and Request for Variance, File No. ET-2025-0184 (Union Electric Company d/b/a Ameren Missouri, Large Load Customer Rate Plan)
Missouri Public Service Commission (EFIS filing)Tier 1 · Captured 2026-11-08 · Open the source - 2Staff's Brief Regarding Ameren Missouri's Variance Request, File No. ET-2025-0184
Missouri Public Service Commission (EFIS filing)Tier 1 · Captured 2026-11-08 · Open the source - 3Missouri Secures $15 Billion Investment from Google in Montgomery County
Office of the Governor of MissouriTier 1 · Captured 2026-11-08 · Open the source - 4Direct Testimony of Robert B. Dixon, File No. EA-2026-0183
Missouri Public Service Commission (EFIS)Tier 1 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page