Project File
Iron Mountain KCM-1
Kansas City,Jackson County,MissouriOperatingLast checked Nov 10, 2026
Iron MountainOperator
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
4 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Capacity
- Still to confirm: Electric utility
- Still to confirm: First public date
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Iron Mountain KCM-1 is an operating data center project in Kansas City, Jackson County, Missouri. Iron Mountain is named as operator. It was announced at 3.9 MW.
Iron Mountain KCM-1 is an operating data center project in Kansas City, Jackson County, Missouri. Iron Mountain is named as operator. It was announced at 3.9 MW. 4 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Kansas City, Jackson County, Missouri. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

The land, to scale
Bills and laws in Missouri
- HB 3369 · Died or failed · May 15, 2026One year ban on data center permits in St. Louis
- HB 3362 · Died or failed · May 15, 2026New rules for industrial utility customers
- HB 3390 · Died or failed · May 15, 2026State siting board for hyperscale data centers
- HB 2239 · Died or failed · May 15, 2026AI data center environmental accountability act
- HB 3364 · Died or failed · May 15, 2026New rules for industrial utility customers
- SB 4 · Signed into law · Apr 9, 2025Utility law requiring large load customers to cover their costs
Who's involved
- OperatorIron Mountain
Power
Capacity, as announced or filed
- 3.9 MW · what the figure measures is not stated
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is Iron Mountain KCM-1?
- Iron Mountain KCM-1 is a data center project in Kansas City, Jackson County, Missouri.
- Who operates Iron Mountain KCM-1?
- Iron Mountain is named as the operator of Iron Mountain KCM-1.
- How big is Iron Mountain KCM-1?
- Iron Mountain KCM-1 was announced at 3.9 MW of capacity. The site covers 22 acres.
- What stage is Iron Mountain KCM-1?
- Iron Mountain KCM-1 is operating.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Kansas City Data Center (KCM-1) brochure
Iron Mountain IncorporatedTier 2 · Captured 2026-11-10 · Open the source - 2Service Locations, Kansas City metro
Cogent CommunicationsTier 2 · Captured 2026-11-10 · Open the source - 3U.S. Census Geocoder (batch geographies endpoint)
U.S. Census BureauTier 1 · Captured 2026-11-11 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page